Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Sasthamcotta WS Sn 2 HW - AE
Date: 02/04/2023

Work has been completed | 100% Completed

Agrement executed .Pump & motor are supplied by the contractor, bill submitted

Sasthamcotta WS Sn 2 HW - AE
Date: 31/03/2023

Work has been completed | 100% Completed

Agrement executed .Pump & motor are supplied by the contractor, bill submitted.

Sasthamcotta WS Sn 2 HW - AE
Date: 25/03/2023

Work has been completed | 100% Completed

Agrement executed .Pump & motor are supplied by the contractor, bill submitted.

Sasthamcotta WS Sn 2 HW - AE
Date: 21/03/2023

Work has been completed | 100% Completed

Agrement executed .Pump & motor are supplied by the contractor, bill submitted.

Sasthamcotta WS Sn 2 HW - AE
Date: 23/02/2023

Work has been completed | 100% Completed

Agrement executed .Pump & motor are supplied by the contractor, bill submitted.

Sasthamcotta WS Sn 2 HW - AE
Date: 17/02/2023

Work in progress | 75% Completed

Agrement executed .Pump & motor are supplied by the contractor, bill under progress.

Sasthamcotta WS Sn 2 HW - AE
Date: 04/02/2023

Work in progress | 75% Completed

Agrement executed .Pump & motor are supplied by the contractor, bill under progress.

Sasthamcotta WS Sn 2 HW - AE
Date: 31/01/2023

Work in progress | 75% Completed

Agrement executed .Pump & motor are supplied by the contractor,bill under progress.

Sasthamcotta WS Sn 2 HW - AE
Date: 25/01/2023

Work in progress | 75% Completed

Agrement executed .Pump & motor (spare)are supplied by the contractor,bill under progress.

Sasthamcotta WS Sn 2 HW - AE
Date: 20/01/2023

Work has started | 0% Completed

Work order issued.

Sasthamcotta WS Sn 2 HW - AE
Date: 16/01/2023

Work has started | 0% Completed

Work order issued.

Sasthamcotta WS Sn 2 HW - AE
Date: 07/01/2023

Work has started | 0% Completed

Work order issued.

Sasthamcotta WS Sub-Dn - AEE
Date: 21/12/2022

Work has started | 0% Completed

Work tendered