| Sasthamcotta WS Sn 2 HW - AE |
| Date: 02/04/2023 |
Work has been completed | 100% Completed
Agrement executed .Pump & motor are supplied by the contractor, bill submitted
| Sasthamcotta WS Sn 2 HW - AE |
| Date: 31/03/2023 |
Work has been completed | 100% Completed
Agrement executed .Pump & motor are supplied by the contractor, bill submitted.
| Sasthamcotta WS Sn 2 HW - AE |
| Date: 25/03/2023 |
Work has been completed | 100% Completed
Agrement executed .Pump & motor are supplied by the contractor, bill submitted.
| Sasthamcotta WS Sn 2 HW - AE |
| Date: 21/03/2023 |
Work has been completed | 100% Completed
Agrement executed .Pump & motor are supplied by the contractor, bill submitted.
| Sasthamcotta WS Sn 2 HW - AE |
| Date: 23/02/2023 |
Work has been completed | 100% Completed
Agrement executed .Pump & motor are supplied by the contractor, bill submitted.
| Sasthamcotta WS Sn 2 HW - AE |
| Date: 17/02/2023 |
Work in progress | 75% Completed
Agrement executed .Pump & motor are supplied by the contractor, bill under progress.
| Sasthamcotta WS Sn 2 HW - AE |
| Date: 04/02/2023 |
Work in progress | 75% Completed
Agrement executed .Pump & motor are supplied by the contractor, bill under progress.
| Sasthamcotta WS Sn 2 HW - AE |
| Date: 31/01/2023 |
Work in progress | 75% Completed
Agrement executed .Pump & motor are supplied by the contractor,bill under progress.
| Sasthamcotta WS Sn 2 HW - AE |
| Date: 25/01/2023 |
Work in progress | 75% Completed
Agrement executed .Pump & motor (spare)are supplied by the contractor,bill under progress.
| Sasthamcotta WS Sn 2 HW - AE |
| Date: 20/01/2023 |
Work has started | 0% Completed
Work order issued.
| Sasthamcotta WS Sn 2 HW - AE |
| Date: 16/01/2023 |
Work has started | 0% Completed
Work order issued.
| Sasthamcotta WS Sn 2 HW - AE |
| Date: 07/01/2023 |
Work has started | 0% Completed
Work order issued.
| Sasthamcotta WS Sub-Dn - AEE |
| Date: 21/12/2022 |
Work has started | 0% Completed
Work tendered