Cherthala PH SUb Dn
Date: 15/07/2022

Work has been completed | 100% Completed

Bill submitted to Division office after correction

Cherthala PH SUb Dn
Date: 01/06/2022

Work has been completed | 100% Completed

Bill returned from Division for correction

Cherthala PH SUb Dn
Date: 06/05/2022

Work has been completed | 100% Completed

Completed, bill submitted to Division Office

Cherthala PH SUb Dn
Date: 05/05/2022

Work has been completed | 100% Completed

Completed, bill submitted to Division Office

Cherthala PH SUb Dn
Date: 02/05/2022

Work has been completed | 100% Completed

Completed, bill submitted to Division Office

Cherthala PH SUb Dn
Date: 30/04/2022

Work has been completed | 100% Completed

Completed, bill submitted to Division Office

Cherthala PH SUb Dn
Date: 28/04/2022

Work has been completed | 100% Completed

Completed, bill submitted to Division Office

Cherthala PH SUb Dn
Date: 27/04/2022

Work has been completed | 100% Completed

Completed, bill submitted to Division Office

Cherthala PH SUb Dn
Date: 26/04/2022

Work has been completed | 100% Completed

Completed, bill submitted to Division Office

Cherthala PH SUb Dn
Date: 25/04/2022

Work has been completed | 100% Completed

Completed, bill submitted to Division Office

Cherthala PH SUb Dn
Date: 23/04/2022

Work has been completed | 100% Completed

Completed, bill submitted to Divison Office

Cherthala PH SUb Dn
Date: 22/04/2022

Work has been completed | 100% Completed

Completed, bill submitted to Divison Office

Cherthala PH SUb Dn
Date: 21/04/2022

Work has been completed | 100% Completed

Completed, bill submitted to Divison Office

Cherthala PH SUb Dn
Date: 20/04/2022

Work has been completed | 100% Completed

Completed, bill submitted to Divison Office

Cherthala PH SUb Dn
Date: 19/04/2022

Work has been completed | 100% Completed

Completed, bill under scrutiny in Sub Divison

Cherthala PH SUb Dn
Date: 18/04/2022

Work has been completed | 100% Completed

Completed, bill under scrutiny in Sub Divison

Cherthala PH SUb Dn
Date: 13/04/2022

Work has been completed | 100% Completed

Completed, bill under scrutiny in Sub Divison

Cherthala PH SUb Dn
Date: 12/04/2022

Work has been completed | 100% Completed

Completed, bill under scrutiny in Sub Divison

Cherthala PH SUb Dn
Date: 11/04/2022

Work has been completed | 100% Completed

Completed, bill under scrutiny in Sub Divison

Cherthala PH SUb Dn
Date: 08/04/2022

Work has been completed | 100% Completed

Completed, bill under scrutiny in Sub Divison

Cherthala PH SUb Dn
Date: 07/04/2022

Work has been completed | 100% Completed

Completed, bill under scrutiny in Sub Divison

Cherthala PH SUb Dn
Date: 06/04/2022

Work has been completed | 100% Completed

Completed, bill under scrutiny in Sub Divison

Cherthala PH SUb Dn
Date: 05/04/2022

Work has been completed | 100% Completed

Completed, bill under preparation

Cherthala PH SUb Dn
Date: 04/04/2022

Work has been completed | 100% Completed

Completed

Cherthala PH SUb Dn
Date: 02/04/2022

Work has been completed | 100% Completed

Completed

Cherthala PH SUb Dn
Date: 01/04/2022

Work has been completed | 100% Completed

Completed

Cherthala PH SUb Dn
Date: 31/03/2022

Work in progress | 95% Completed

Completed except interconnection works

Cherthala PH SUb Dn
Date: 30/03/2022

Work in progress | 95% Completed

Completed except interconnection works

Cherthala PH SUb Dn
Date: 26/03/2022

Work in progress | 95% Completed

Completed except interconnection works

Cherthala PH SUb Dn
Date: 25/03/2022

Work in progress | 95% Completed

Completed except interconnection works

Cherthala PH SUb Dn
Date: 24/03/2022

Work in progress | 95% Completed

Completed except interconnection works

Cherthala PH SUb Dn
Date: 23/03/2022

Work in progress | 95% Completed

Completed except interconnection works

Cherthala PH SUb Dn
Date: 22/03/2022

Work in progress | 95% Completed

Completed except interconnection works

Cherthala PH SUb Dn
Date: 19/03/2022

Work in progress | 95% Completed

Completed except interconnection works

Cherthala PH SUb Dn
Date: 18/03/2022

Work in progress | 90% Completed

520 m laid out of 575m

Cherthala PH SUb Dn
Date: 17/03/2022

Work in progress | 90% Completed

520 m laid out of 575m

Cherthala PH SUb Dn
Date: 16/03/2022

Work in progress | 90% Completed

520 m laid out of 575m

Cherthala PH SUb Dn
Date: 14/03/2022

Work in progress | 90% Completed

520 m laid out of 575m

Cherthala PH SUb Dn
Date: 11/03/2022

Work in progress | 90% Completed

520 m laid out of 575m

Cherthala PH SUb Dn
Date: 10/03/2022

Work in progress | 90% Completed

520 m laid out of 575m

Cherthala PH SUb Dn
Date: 09/03/2022

Work in progress | 90% Completed

520 m laid out of 575m

Cherthala PH SUb Dn
Date: 08/03/2022

Work in progress | 90% Completed

520 m laid out of 575m

Cherthala PH SUb Dn
Date: 07/03/2022

Work in progress | 90% Completed

520 m laid out of 575m

Cherthala PH SUb Dn
Date: 05/03/2022

Work in progress | 90% Completed

520 m laid out of 575m

Cherthala PH SUb Dn
Date: 04/03/2022

Work in progress | 90% Completed

520 m laid out of 575m

Cherthala PH SUb Dn
Date: 03/03/2022

Work in progress | 90% Completed

520 m laid out of 575m

Cherthala PH SUb Dn
Date: 02/03/2022

Work in progress | 90% Completed

520 m laid out of 575m

Cherthala PH SUb Dn
Date: 28/02/2022

Work in progress | 83% Completed

478 m laid out of 575m

Cherthala PH SUb Dn
Date: 26/02/2022

Work in progress | 75% Completed

431m laid out of 575m

Cherthala PH SUb Dn
Date: 25/02/2022

Work in progress | 75% Completed

431m laid out of 575m

Cherthala PH SUb Dn
Date: 24/02/2022

Work in progress | 75% Completed

431m laid out of 575m

Cherthala PH SUb Dn
Date: 23/02/2022

Work in progress | 70% Completed

404m laid out of 575m

Cherthala PH SUb Dn
Date: 22/02/2022

Work in progress | 66% Completed

380 m laid out of 575m

Cherthala PH SUb Dn
Date: 21/02/2022

Work in progress | 50% Completed

290 m laid out of 575m

Cherthala PH SUb Dn
Date: 19/02/2022

Work in progress | 20% Completed

115 m laid out of 575m