Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Kozhikode Dist 1 Sn 2 - AE
Date: 11/09/2024

Work has been completed | 100% Completed

Final bill submitted

Kozhikode Dist 1 Sn 2 - AE
Date: 21/08/2024

Work has been completed | 100% Completed

Work completed and final bill to be submitted

Kozhikode PH Dn EE
Date: 20/04/2024

Work in progress | 95% Completed

Work in progress

Kozhikode PH Dn EE
Date: 04/04/2024

Work in progress | 93% Completed

Work in progress

Kozhikode PH Dn EE
Date: 12/03/2024

Work in progress | 90% Completed

Work in progress

Kozhikode PH Dn EE
Date: 01/03/2024

Work in progress | 88% Completed

Work in progress

Kozhikode PH Dn EE
Date: 14/02/2024

Work in progress | 85% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 27/01/2024

Work in progress | 83% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 11/01/2024

Work in progress | 80% Completed

Work in progress

Kozhikode PH Dn EE
Date: 11/12/2023

Work in progress | 68% Completed

Work in progress

Kozhikode PH Dn EE
Date: 28/11/2023

Work in progress | 65% Completed

Work in progress

Kozhikode PH Dn EE
Date: 09/11/2023

Work in progress | 58% Completed

Pipe laying started

Kozhikode PH Dn EE
Date: 27/10/2023

Work in progress | 55% Completed

Pipe laying started

Kozhikode PH Dn EE
Date: 17/10/2023

Work in progress | 50% Completed

Pipe laying started

Kozhikode PH Dn EE
Date: 14/09/2023

Work in progress | 41% Completed

Pipe laying started

Kozhikode PH Dn EE
Date: 05/09/2023

Work in progress | 40% Completed

Pipe laying started

Kozhikode PH Dn EE
Date: 17/08/2023

Work in progress | 30% Completed

Pipe laying started

Kozhikode PH Dn EE
Date: 07/08/2023

Work in progress | 25% Completed

Pipe laying started

Kozhikode PH Dn EE
Date: 24/07/2023

Work in progress | 20% Completed

Pipe laying started

Kozhikode PH Dn EE
Date: 12/07/2023

Work in progress | 12% Completed

Pipe laying started.

Kozhikode PH Dn EE
Date: 05/07/2023

Work in progress | 10% Completed

Pipe laying started.

Kozhikode PH Dn EE
Date: 30/06/2023

Work in progress | 9% Completed

Pipe laying started.

Kozhikode PH Dn EE
Date: 20/06/2023

Work in progress | 7% Completed

Pipe laying started.

Kozhikode PH Dn EE
Date: 13/06/2023

Work in progress | 6% Completed

Pipe laying started.

Kozhikode PH Dn EE
Date: 08/06/2023

Work in progress | 5% Completed

Pipe laying started. Almost 106 meter of pipe laid

Kozhikode PH Dn EE
Date: 05/06/2023

Work in progress | 1% Completed

Agreement Executed

Kozhikode PH Dn EE
Date: 01/06/2023

Work in progress | 1% Completed

Agreement Executed

Kozhikode PH Dn EE
Date: 25/05/2023

Work in progress | 1% Completed

Agreement Executed