| Chavara AE |
| Date: 24/02/2026 |
Work has been completed | 100% Completed
work completed
| Chavara AE |
| Date: 11/02/2026 |
Work in progress | 60% Completed
No work currently ongoing
| Chavara AE |
| Date: 06/02/2026 |
Work in progress | 60% Completed
No work currently ongoing
| Chavara AE |
| Date: 02/02/2026 |
Work in progress | 60% Completed
No work currently ongoing
| Chavara AE |
| Date: 29/01/2026 |
Work in progress | 60% Completed
Electrical work completed. Applied for electrical connection
| Chavara AE |
| Date: 24/01/2026 |
Work in progress | 60% Completed
Electrical work completed. Applied for electrical connection
| Chavara AE |
| Date: 20/01/2026 |
Work in progress | 60% Completed
Electrical work completed. Applied for electrical connection.
| Chavara AE |
| Date: 16/01/2026 |
Work in progress | 60% Completed
Electrical work completed. Applied for electrical connection.
| Chavara AE |
| Date: 12/01/2026 |
Work in progress | 60% Completed
Electrical work completed. Applied for electrical connection.
| Chavara AE |
| Date: 07/01/2026 |
| Chavara AE |
| Date: 03/01/2026 |
Work in progress | 50% Completed
No work on going currently
| Chavara AE |
| Date: 31/12/2025 |
Work in progress | 50% Completed
No work on going currently
| Chavara AE |
| Date: 27/12/2025 |
Work in progress | 50% Completed
No work on going currently
| Chavara AE |
| Date: 24/12/2025 |
Work in progress | 50% Completed
Floor concrete and plastering work completed
| Chavara AE |
| Date: 19/12/2025 |
| Chavara AE |
| Date: 15/12/2025 |
Work in progress | 42% Completed
Development of Tube well completed. Started pump house Construction.
| Chavara AE |
| Date: 11/12/2025 |
| Chavara AE |
| Date: 03/12/2025 |
Work in progress | 40% Completed
Works till development of tubewell completed.
| Chavara AE |
| Date: 29/11/2025 |
Work in progress | 40% Completed
Works till development of tubewell completed.
| Chavara AE |
| Date: 18/11/2025 |
| Chavara AE |
| Date: 13/11/2025 |