Kondotty AE |
Date: 26/06/2024 |
Work in progress | 7% Completed
FHTC work in progress, 1020 Nos. connections are completed
Kondotty AE |
Date: 22/06/2024 |
Work in progress | 7% Completed
FHTC work in progress, 1020 Nos. connections are completed
Kondotty AE |
Date: 13/06/2024 |
Work in progress | 7% Completed
FHTC work in progress, 1020 Nos. connections are completed
Kondotty AE |
Date: 25/05/2024 |
Work in progress | 7% Completed
FHTC work in progress, 1020 Nos. connections are completed
Kondotty AE |
Date: 18/05/2024 |
Work in progress | 5% Completed
FHTC work in progress, 950 Nos. connections are completed
Kondotty AE |
Date: 14/05/2024 |
Work in progress | 5% Completed
FHTC work in progress, 900 Nos. connections are completed
Kondotty AE |
Date: 09/05/2024 |
Work in progress | 5% Completed
FHTC work in progress, 900 Nos. connections are completed
Kondotty AE |
Date: 27/04/2024 |
Work in progress | 5% Completed
FHTC work in progress, 900 Nos. connections are completed
Kondotty AE |
Date: 23/04/2024 |
Work in progress | 5% Completed
FHTC work in progress, 900 Nos. connections are completed
Kondotty AE |
Date: 17/04/2024 |
Work in progress | 5% Completed
FHTC work in progress, 900 Nos. connections are completed
Kondotty AE |
Date: 06/04/2024 |
Work in progress | 5% Completed
HTC work in progress, 845 Nos. connections are completed
Kondotty AE |
Date: 23/03/2024 |
Work in progress | 5% Completed
65mm GI pipe 242m laid, 80mm GI pipe 1645m laid, 75mm PVC pipe 48m laid and 225m 90mm PVC pipe laid,
Kondotty AE |
Date: 15/03/2024 |
Work in progress | 5% Completed
FHTC work in progress, 840 Nos. connections are completed
Kondotty AE |
Date: 06/03/2024 |
Work in progress | 5% Completed
FHTC work in progress, 803 Nos. connections are completed
Kondotty AE |
Date: 02/03/2024 |
Work in progress | 5% Completed
FHTC work in progress, 803 Nos. connections are completed
Kondotty AE |
Date: 26/02/2024 |
Work in progress | 5% Completed
FHTC work in progress, 803 Nos. connections are completed
Kondotty AE |
Date: 21/02/2024 |
Work in progress | 5% Completed
FHTC work in progress, 800 Nos. connections are completed
Kondotty AE |
Date: 17/02/2024 |
Work in progress | 4% Completed
FHTC work in progress, 780 Nos. connections are completed
Malappuram PH Dn EE |
Date: 14/02/2024 |
Work in progress | 4% Completed
FHTC work in progress, 752 Nos. connections are completed
Kondotty AE |
Date: 05/02/2024 |
Work in progress | 4% Completed
FHTC work in progress, 752 Nos. connections are completed
Kondotty AE |
Date: 27/01/2024 |
Work in progress | 4% Completed
FHTC work in progress, 752 Nos. connections are completed
Kondotty AE |
Date: 17/01/2024 |
Work in progress | 4% Completed
FHTC work in progress, 650 Nos. connections are completed
Kondotty AE |
Date: 11/01/2024 |
Work in progress | 4% Completed
FHTC work in progress, 640 Nos. connections are completed O
Kondotty AE |
Date: 06/01/2024 |
Work in progress | 4% Completed
FHTC work in progress, 640 Nos. connections are completed
Kondotty AE |
Date: 03/01/2024 |
Work in progress | 4% Completed
FHTC work in progress, 640 Nos. connections are completed
Kondotty AE |
Date: 30/12/2023 |
Work in progress | 4% Completed
FHTC work in progress, 640 Nos. connections are completed
Kondotty AE |
Date: 26/12/2023 |
Work in progress | 4% Completed
FHTC work in progress, 620 Nos. connections are completed
Kondotty AE |
Date: 22/12/2023 |
Work in progress | 4% Completed
FHTC work in progress, 605 Nos. connections are completed
Kondotty AE |
Date: 18/12/2023 |
Work in progress | 4% Completed
FHTC work in progress, 605 Nos. connections are completed
Kondotty AE |
Date: 14/12/2023 |
Work in progress | 4% Completed
FHTC work in progress, 600 nos. connections are completed
Kondotty AE |
Date: 11/12/2023 |
Work in progress | 4% Completed
FHTC work in progress, 600 nos. connections are completed
Kondotty AE |
Date: 05/12/2023 |
Work in progress | 4% Completed
FHTC work in progress, 600 nos. connections are completed
Kondotty AE |
Date: 30/11/2023 |
Work in progress | 4% Completed
FHTC work in progress, 600 nos. connections are completed
Kondotty AE |
Date: 25/11/2023 |
Work in progress | 4% Completed
FHTC work in progress, 600 nos. connections are completed
Kondotty AE |
Date: 23/11/2023 |
Work in progress | 4% Completed
FHTC work in progress, 600 nos. connections are completed
Kondotty AE |
Date: 18/11/2023 |
Work in progress | 4% Completed
FHTC work in progress, 600 nos. connections are completed
Kondotty AE |
Date: 14/11/2023 |
Work in progress | 3% Completed
FHTC work in progress, 535 nos. connections are completed
Kondotty AE |
Date: 08/11/2023 |
Work in progress | 3% Completed
FHTC work in progress, 535 nos. connections are completed
Kondotty AE |
Date: 04/11/2023 |
Work in progress | 3% Completed
FHTC work in progress, 510 nos. connections are completed
Kondotty AE |
Date: 01/11/2023 |
Work in progress | 3% Completed
HTC work in progress, 480 nos. connections are completed
Kondotty AE |
Date: 27/10/2023 |
Work in progress | 3% Completed
HTC work in progress, 430 nos. connections are completed
Kondotty AE |
Date: 21/10/2023 |
Work in progress | 2% Completed
FHTC work in progress, 330 nos. connections are completed
Kondotty AE |
Date: 18/10/2023 |
Work in progress | 2% Completed
FHTC work in progress, 315 nos. connections are completed
Kondotty AE |
Date: 13/10/2023 |
Work in progress | 2% Completed
FHTC work in progress, 315 nos. connections are completed
Kondotty AE |
Date: 09/10/2023 |
Work in progress | 2% Completed
FHTC work in progress, 305 nos. connections are completed
Kondotty AE |
Date: 04/10/2023 |
Work in progress | 2% Completed
FHTC work in progress, 305 nos. connections are completed
Kondotty AE |
Date: 26/09/2023 |
Work in progress | 2% Completed
FHTC work in progress, 300 nos. connections are completed
Kondotty AE |
Date: 20/09/2023 |
Work in progress | 2% Completed
FHTC work in progress, 245 nos. connections are completed
Kondotty AE |
Date: 16/09/2023 |
Work in progress | 2% Completed
FHTC work in progress, 245 nos. connections are completed
Kondotty AE |
Date: 13/09/2023 |
Work in progress | 2% Completed
FHTC work in progress, 230nos. connections are completed
Kondotty AE |
Date: 02/09/2023 |
Work in progress | 2% Completed
FHTC work in progress, 160nos. connections are completed
Kondotty AE |
Date: 14/08/2023 |
Work in progress | 2% Completed
FHTC work in progress, 125nos. connections are completed
Kondotty AE |
Date: 08/08/2023 |
Work in progress | 2% Completed
FHTC work in progress, 91nos. connections are completed
Kondotty AE |
Date: 31/07/2023 |
Work in progress | 1% Completed
FHTC Work on progress
Kondotty AE |
Date: 26/07/2023 |
Work in progress | 1% Completed
FHTC Work on progress
Malappuram PH Dn EE |
Date: 22/07/2023 |
Work in progress | 1% Completed
FHTC work started
Kondotty AE |
Date: 19/07/2023 |
Work in progress | 1% Completed
Work started
Kondotty AE |
Date: 13/07/2023 |
Work in progress | 1% Completed
Work started , providing FHTC in ward 1-3 started