Thiruvananthapuram Project AE7
Date: 13/02/2024

Work has been completed | 100% Completed

work completed

Thiruvananthapuram Project AE7
Date: 21/12/2023

Work has been completed | 100% Completed

work completed

Thiruvananthapuram Project AE7
Date: 20/12/2023

Work has been completed | 100% Completed

work completed

Thiruvananthapuram Project AE7
Date: 19/12/2023

Work in progress | 99% Completed

Site clearing work going on

Thiruvananthapuram Project AE7
Date: 18/12/2023

Work in progress | 98% Completed

Balance pipe shifting work

Thiruvananthapuram Project AE7
Date: 17/12/2023

Work in progress | 96% Completed

No work today

Thiruvananthapuram Project AE7
Date: 16/12/2023

Work in progress | 96% Completed

Levelling work and site clearing

Thiruvananthapuram Project AE7
Date: 15/12/2023

Work in progress | 94% Completed

Earth filling and Levelling work

Thiruvananthapuram Project AE7
Date: 14/12/2023

Work in progress | 92% Completed

Pressure Test completed

Attached images

img img img img

Thiruvananthapuram Project AE7
Date: 13/12/2023

Work in progress | 90% Completed

No work today

Thiruvananthapuram Project AE7
Date: 12/12/2023

Work in progress | 90% Completed

No work today

Thiruvananthapuram Project AE7
Date: 11/12/2023

Work in progress | 90% Completed

No work today

Thiruvananthapuram Project AE7
Date: 10/12/2023

Work in progress | 90% Completed

No work today

Thiruvananthapuram Project AE7
Date: 09/12/2023

Work in progress | 90% Completed

No work today

Thiruvananthapuram Project AE7
Date: 08/12/2023

Work in progress | 90% Completed

No work today

Thiruvananthapuram Project AE7
Date: 07/12/2023

Work in progress | 90% Completed

No work today

Thiruvananthapuram Project AE7
Date: 06/12/2023

Work in progress | 90% Completed

No work today

Thiruvananthapuram Project AE7
Date: 05/12/2023

Work in progress | 90% Completed

No work today

Thiruvananthapuram Project AE7
Date: 04/12/2023

Work in progress | 90% Completed

Pipe laying

Attached images

img img

Thiruvananthapuram Project AE7
Date: 03/12/2023

Work in progress | 90% Completed

No work today

Thiruvananthapuram Project AE7
Date: 02/12/2023

Work in progress | 90% Completed

Bend concrete work

Attached images

img img

Thiruvananthapuram Project AE7
Date: 01/12/2023

Work in progress | 90% Completed

Bend fixing work

Attached images

img

Thiruvananthapuram Project AE7
Date: 30/11/2023

Work in progress | 89% Completed

Excavation work

Attached images

img

Thiruvananthapuram Project AE7
Date: 29/11/2023

Work in progress | 88% Completed

Pipe lifting work

Attached images

img

Thiruvananthapuram Project AE7
Date: 28/11/2023

Work in progress | 88% Completed

Excavation work

Attached images

img

Thiruvananthapuram Project AE7
Date: 27/11/2023

Work in progress | 88% Completed

Excavation work

Attached images

img

Thiruvananthapuram Project AE7
Date: 26/11/2023

Work in progress | 88% Completed

Pipe jointing work

Attached images

img

Thiruvananthapuram Project AE7
Date: 25/11/2023

Work in progress | 88% Completed

Levelling work

Attached images

img

Thiruvananthapuram Project AE7
Date: 24/11/2023

Work in progress | 88% Completed

Levelling work

Attached images

img img

Thiruvananthapuram Project AE7
Date: 23/11/2023

Work in progress | 88% Completed

Excavation work

Attached images

img

Thiruvananthapuram Project AE7
Date: 22/11/2023

Work in progress | 88% Completed

Pipe laying

Attached images

img

Thiruvananthapuram Project AE7
Date: 21/11/2023

Work in progress | 85% Completed

Pipe laying

Attached images

img

Thiruvananthapuram Project AE7
Date: 20/11/2023

Work in progress | 82% Completed

No work today

Thiruvananthapuram Project AE7
Date: 19/11/2023

Work in progress | 82% Completed

No work today

Thiruvananthapuram Project AE7
Date: 18/11/2023

Work in progress | 82% Completed

No work today

Thiruvananthapuram Project AE7
Date: 17/11/2023

Work in progress | 82% Completed

No work today

Thiruvananthapuram Project AE7
Date: 16/11/2023

Work in progress | 82% Completed

No work toady

Thiruvananthapuram Project AE7
Date: 15/11/2023

Work in progress | 82% Completed

Pipe lifting and pipe laying

Attached images

img img

Thiruvananthapuram Project AE7
Date: 14/11/2023

Work in progress | 81% Completed

Pipe lifting and pipe laying

Attached images

img img

Thiruvananthapuram Project AE7
Date: 13/11/2023

Work in progress | 80% Completed

No work today

Thiruvananthapuram Project AE7
Date: 12/11/2023

Work in progress | 80% Completed

No work today

Thiruvananthapuram Project AE7
Date: 11/11/2023

Work in progress | 80% Completed

Pipe laying and pipe lifting

Attached images

img img

Thiruvananthapuram Project AE7
Date: 10/11/2023

Work in progress | 75% Completed

Excavation, Pipe laying and pipe lifting

Attached images

img img

Thiruvananthapuram Project AE7
Date: 09/11/2023

Work in progress | 66% Completed

Excavation for pipe laying work

Attached images

img

Thiruvananthapuram Project AE7
Date: 08/11/2023

Work in progress | 60% Completed

No work today

Thiruvananthapuram Project AE7
Date: 07/11/2023

Work in progress | 60% Completed

No work today

Thiruvananthapuram Project AE7
Date: 06/11/2023

Work in progress | 51% Completed

No work today

Thiruvananthapuram Project AE7
Date: 05/11/2023

Work in progress | 51% Completed

No work today

Thiruvananthapuram Project AE7
Date: 04/11/2023

Work in progress | 51% Completed

No work today

Thiruvananthapuram Project AE7
Date: 03/11/2023

Work in progress | 51% Completed

No work today

Thiruvananthapuram Project AE7
Date: 02/11/2023

Work in progress | 51% Completed

No work today

Thiruvananthapuram Project AE7
Date: 01/11/2023

Work in progress | 51% Completed

No work today

Thiruvananthapuram Project AE7
Date: 31/10/2023

Work in progress | 51% Completed

No work today

Thiruvananthapuram Project AE7
Date: 30/10/2023

Work in progress | 51% Completed

No work today

Thiruvananthapuram Project AE7
Date: 29/10/2023

Work in progress | 51% Completed

No work today

Thiruvananthapuram Project AE7
Date: 28/10/2023

Work in progress | 51% Completed

Pipe laying and pipe lifting

Attached images

img img

Thiruvananthapuram Project AE7
Date: 27/10/2023

Work in progress | 44% Completed

Pipe lifting and pipe laying

Attached images

img img

Thiruvananthapuram Project AE7
Date: 26/10/2023

Work in progress | 41% Completed

No work today

Thiruvananthapuram Project AE7
Date: 25/10/2023

Work in progress | 41% Completed

Pipe laying

Attached images

img img

Thiruvananthapuram Project AE7
Date: 24/10/2023

Work in progress | 37% Completed

No work today

Thiruvananthapuram Project AE7
Date: 23/10/2023

Work in progress | 37% Completed

No work today

Thiruvananthapuram Project AE7
Date: 22/10/2023

Work in progress | 37% Completed

Pipe laying and pipe lifting

Attached images

img img

Thiruvananthapuram Project AE7
Date: 21/10/2023

Work in progress | 34% Completed

Pipe lifting and pipe laying

Attached images

img img

Thiruvananthapuram Project AE7
Date: 20/10/2023

Work in progress | 30% Completed

No work today

Thiruvananthapuram Project AE7
Date: 19/10/2023

Work in progress | 30% Completed

No work today

Thiruvananthapuram Project AE7
Date: 18/10/2023

Work in progress | 30% Completed

No work today

Thiruvananthapuram Project AE7
Date: 17/10/2023

Work in progress | 30% Completed

Earth filling work only

Attached images

img

Thiruvananthapuram Project AE7
Date: 16/10/2023

Work in progress | 25% Completed

Pipe laying and pipe lifting

Attached images

img img

Thiruvananthapuram Project AE7
Date: 15/10/2023

Work in progress | 18% Completed

No work toady

Thiruvananthapuram Project AE7
Date: 14/10/2023

Work in progress | 18% Completed

Pipe laying

Attached images

img

Thiruvananthapuram Project AE7
Date: 13/10/2023

Work in progress | 17% Completed

Pipe laying

Attached images

img img

Thiruvananthapuram Project AE7
Date: 12/10/2023

Work in progress | 16% Completed

Pipe lifting and pipe laying

Attached images

img img

Thiruvananthapuram Project AE7
Date: 11/10/2023

Work in progress | 15% Completed

Pipe laying

Attached images

img img

Thiruvananthapuram Project AE7
Date: 10/10/2023

Work in progress | 14% Completed

Pipe laying

Attached images

img

Thiruvananthapuram Project AE7
Date: 09/10/2023

Work in progress | 14% Completed

Pipe lifting and Pipe Laying

Attached images

img img

Thiruvananthapuram Project AE7
Date: 08/10/2023

Work in progress | 13% Completed

No work today

Thiruvananthapuram Project AE7
Date: 07/10/2023

Work in progress | 13% Completed

No work today

Thiruvananthapuram Project AE7
Date: 06/10/2023

Work in progress | 13% Completed

No work today

Thiruvananthapuram Project AE7
Date: 05/10/2023

Work in progress | 13% Completed

No work today

Thiruvananthapuram Project AE7
Date: 04/10/2023

Work in progress | 13% Completed

No work today

Thiruvananthapuram Project AE7
Date: 03/10/2023

Work in progress | 13% Completed

No work today

Thiruvananthapuram Project AE7
Date: 02/10/2023

Work in progress | 13% Completed

No work today

Thiruvananthapuram Project AE7
Date: 01/10/2023

Work in progress | 13% Completed

No work

Thiruvananthapuram Project AE7
Date: 30/09/2023

Work in progress | 13% Completed

Earth filling

Attached images

img

Thiruvananthapuram Project AE7
Date: 29/09/2023

Work in progress | 12% Completed

No work today

Thiruvananthapuram Project AE7
Date: 28/09/2023

Work in progress | 12% Completed

Excavation, Pipe lifting & Pipe Laying

Attached images

img img

Thiruvananthapuram Project AE7
Date: 27/09/2023

Work in progress | 8% Completed

Excavation, Pipe lifting & Pipe Laying

Attached images

img img

Thiruvananthapuram Project AE7
Date: 26/09/2023

Work in progress | 4% Completed

Excavation, Pipe lifting & Pipe Laying

Attached images

img img

Thiruvananthapuram Project AE7
Date: 25/09/2023

Work in progress | 3% Completed

Excavation & Pipe Laying

Attached images

img img

Thiruvananthapuram Project AE7
Date: 24/09/2023

Work in progress | 3% Completed

Excavation ,Pipe lifting & Pipe Laying

Attached images

img img

Thiruvananthapuram Project AE7
Date: 23/09/2023

Work in progress | 2% Completed

Excavation ,Pipe lifting & Pipe Laying

Attached images

img img

Thiruvananthapuram Project AE7
Date: 22/09/2023

Work in progress | 1% Completed

Excavation,Pipe lifting & Pipe Laying

Attached images

img img