Perlassery Sn 2 AE |
Date: 25/06/2024 |
Work in progress | 55% Completed
Work in progress | 55% Completed
Perlassery Sn 2 AE |
Date: 20/06/2024 |
Work in progress | 55% Completed
Work in progress | 55% Completed
Perlassery Sn 2 AE |
Date: 10/06/2024 |
Work in progress | 55% Completed
Work in progress | 55% Completed
Perlassery Sn 2 AE |
Date: 01/06/2024 |
Work in progress | 55% Completed
400Nos FHTCS provided.Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 22/05/2024 |
Work in progress | 50% Completed
399Nos FHTCS provided.Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 17/05/2024 |
Perlassery Sn 2 AE |
Date: 08/05/2024 |
Work in progress | 50% Completed
399Nos FHTCS provided.Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 25/04/2024 |
Work in progress | 50% Completed
396Nos FHTCS provided.Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 18/04/2024 |
Work in progress | 50% Completed
378Nos FHTCS provided.Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 06/04/2024 |
Work in progress | 50% Completed
378Nos FHTCS provided.Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 27/03/2024 |
Work in progress | 50% Completed
373Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 18/03/2024 |
Work in progress | 50% Completed
348 Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 11/03/2024 |
Work in progress | 50% Completed
347 Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 28/02/2024 |
Work in progress | 50% Completed
347 Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 14/02/2024 |
Work in progress | 50% Completed
342Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 06/02/2024 |
Work in progress | 50% Completed
342Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 29/01/2024 |
Work in progress | 50% Completed
342Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 11/01/2024 |
Work in progress | 50% Completed
340Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 05/01/2024 |
Work in progress | 50% Completed
2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged.
Perlassery Sn 2 AE |
Date: 20/12/2023 |
Work in progress | 50% Completed
2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged.
Perlassery Sn 2 AE |
Date: 07/12/2023 |
Work in progress | 50% Completed
322Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 25/11/2023 |
Work in progress | 50% Completed
290Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 18/11/2023 |
Work in progress | 50% Completed
290Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 09/11/2023 |
Work in progress | 45% Completed
276Nos FHTCS provided .Pipe supply, 2.597km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 02/11/2023 |
Work in progress | 35% Completed
256Nos FHTCS provided .Pipe supply, 1.743km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 27/10/2023 |
Work in progress | 35% Completed
239Nos FHTCS provided .Pipe supply, 1.743km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 21/10/2023 |
Work in progress | 35% Completed
235Nos FHTCS provided .Pipe supply, 1.743km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 20/10/2023 |
Work in progress | 35% Completed
222Nos FHTCS provided .Pipe supply, 1.596km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 12/10/2023 |
Work in progress | 35% Completed
222Nos FHTCS provided .Pipe supply, 1.596km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 03/10/2023 |
Work in progress | 32% Completed
208Nos FHTCS provided .Pipe supply, 1.594km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 27/09/2023 |
Work in progress | 32% Completed
208Nos FHTCS provided .Pipe supply, 1.594km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 21/09/2023 |
Perlassery Sn 2 AE |
Date: 13/09/2023 |
Work in progress | 32% Completed
199Nos FHTCS provided .Pipe supply, 1.586km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 01/09/2023 |
Work in progress | 32% Completed
192Nos FHTCS provided .Pipe supply, 1.586km laying and 143nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 24/08/2023 |
Work in progress | 32% Completed
192Nos FHTCS provided .Pipe supply, 1.586km laying and 143no's FHTCS bill submitted.
Kannur PH Dn EE |
Date: 17/08/2023 |
Work in progress | 32% Completed
183Nos FHTCS provided .Pipe supply, 686 km laying and 42 no's FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 09/08/2023 |
Perlassery Sn 2 AE |
Date: 04/08/2023 |
Work in progress | 32% Completed
170 Nos FHTCS provided .Pipe supply, 686 km laying and 42 nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 31/07/2023 |
Work in progress | 32% Completed
166 Nos FHTCS provided .Pipe supply, 686 km laying and 42 nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 27/07/2023 |
Work in progress | 30% Completed
158 Nos FHTCS provided .Pipe supply, 686 km laying and 42 nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 19/07/2023 |
Work in progress | 30% Completed
149Nos FHTCS provided .Pipe supply, 686 km laying and 42 nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 14/07/2023 |
Work in progress | 30% Completed
143Nos FHTCS provided .Pipe supply, 686 km laying and 42 nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 10/07/2023 |
Work in progress | 30% Completed
143Nos FHTCS provided .Pipe supply, 0.626 km laying and 42 nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 04/07/2023 |
Work in progress | 30% Completed
137Nos FHTCS provided .Pipe supply, 0.626 km laying and 42 nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 30/06/2023 |
Work in progress | 30% Completed
111Nos FHTCS provided .Pipe supply, 0.626 km laying and 42 nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 24/06/2023 |
Work in progress | 30% Completed
94Nos FHTCS provided .Pipe supply, 0.626 km laying and 42 nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 19/06/2023 |
Work in progress | 26% Completed
80Nos FHTCS provided .Pipe supply, 0.626 km laying and 42 nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 16/06/2023 |
Work in progress | 26% Completed
78 Nos FHTCS provided .Pipe supply, 0.626 km laying and 42 nos FHTCS bill submitted.
Perlassery Sn 2 AE |
Date: 08/06/2023 |
Work in progress | 26% Completed
64Nos FHTC provided, Nos HTC provided
Perlassery Sn 2 AE |
Date: 01/06/2023 |
Perlassery Sn 2 AE |
Date: 24/05/2023 |
Work in progress | 25% Completed
41Nos FHTC provided,65Nos HTC provided
Perlassery Sn 2 AE |
Date: 18/05/2023 |
Work in progress | 25% Completed
41Nos FHTC provided,65Nos HTC provided
Perlassery Sn 2 AE |
Date: 15/05/2023 |
Work in progress | 25% Completed
41Nos FHTC provided,65Nos HTC provided
Perlassery Sn 2 AE |
Date: 10/05/2023 |
Work in progress | 25% Completed
41Nos FHTC provided,59Nos HTC provided
Perlassery Sn 2 AE |
Date: 04/05/2023 |
Work in progress | 25% Completed
41Nos FHTC provided,59Nos HTC provided
Perlassery Sn 2 AE |
Date: 26/04/2023 |
Work in progress | 25% Completed
37Nos FHTC provided,92Nos HTC provided
Perlassery Sn 2 AE |
Date: 19/04/2023 |
Work in progress | 24% Completed
34Nos FHTC provided,92Nos HTC provided
Perlassery Sn 2 AE |
Date: 13/04/2023 |
Work in progress | 22% Completed
34Nos FHTC provided, 72Nos HTC provided
Perlassery Sn 2 AE |
Date: 09/04/2023 |
Work in progress | 22% Completed
34Nos FHTC provided, 28 Nos HTC provided
Perlassery Sn 2 AE |
Date: 03/04/2023 |
Work in progress | 22% Completed
23 Nos FHTC provided, 37 Nos HTC provided
Perlassery Sn 2 AE |
Date: 29/03/2023 |
Work in progress | 20% Completed
23 Nos FHTC provided, 33 Nos HTC provided
Perlassery Sn 2 AE |
Date: 22/03/2023 |
Work in progress | 20% Completed
56 Nos HTC provided. Pipe supplied
Perlassery Sn 2 AE |
Date: 18/03/2023 |
Work in progress | 20% Completed
54 Nos HTC provided. Pipe supplied
Perlassery Sn 2 AE |
Date: 14/03/2023 |
Work in progress | 15% Completed
work in progress
Perlassery Sn 2 AE |
Date: 09/03/2023 |
Work in progress | 15% Completed
Pipe supplied ,550m pipe laid &laying in progress
Perlassery Sn 2 AE |
Date: 04/03/2023 |
Work in progress | 15% Completed
10% WORK COMPLETED
Perlassery Sn 2 AE |
Date: 27/02/2023 |
Work in progress | 5% Completed
work in progress
Perlassery Sn 2 AE |
Date: 21/02/2023 |
Work in progress | 3% Completed
ongoing
Kannur PH Dn EE |
Date: 27/01/2023 |
Work has started | 0% Completed
AGREEMENT EXECUTED ON 27.01.2023
Kannur PH Dn EE |
Date: 18/01/2023 |
Work has started | 0% Completed
WORK ORDER ISSUED ON 18.01.2023
Kannur PH Dn EE |
Date: 09/12/2022 |
Work in progress | 1% Completed
TS Issued for the balance work.