Perlassery Sn 2 AE
Date: 25/06/2024

Work in progress | 55% Completed

Work in progress | 55% Completed

Perlassery Sn 2 AE
Date: 20/06/2024

Work in progress | 55% Completed

Work in progress | 55% Completed

Perlassery Sn 2 AE
Date: 10/06/2024

Work in progress | 55% Completed

Work in progress | 55% Completed

Perlassery Sn 2 AE
Date: 01/06/2024

Work in progress | 55% Completed

400Nos FHTCS provided.Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 22/05/2024

Work in progress | 50% Completed

399Nos FHTCS provided.Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 17/05/2024

Work in progress | 50% Completed

399Nos FHTCS provided.Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.

Attached images

img

Perlassery Sn 2 AE
Date: 08/05/2024

Work in progress | 50% Completed

399Nos FHTCS provided.Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 25/04/2024

Work in progress | 50% Completed

396Nos FHTCS provided.Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 18/04/2024

Work in progress | 50% Completed

378Nos FHTCS provided.Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 06/04/2024

Work in progress | 50% Completed

378Nos FHTCS provided.Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 27/03/2024

Work in progress | 50% Completed

373Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 18/03/2024

Work in progress | 50% Completed

348 Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 11/03/2024

Work in progress | 50% Completed

347 Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 28/02/2024

Work in progress | 50% Completed

347 Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 14/02/2024

Work in progress | 50% Completed

342Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 06/02/2024

Work in progress | 50% Completed

342Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 29/01/2024

Work in progress | 50% Completed

342Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 11/01/2024

Work in progress | 50% Completed

340Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 05/01/2024

Work in progress | 50% Completed

2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged.

Perlassery Sn 2 AE
Date: 20/12/2023

Work in progress | 50% Completed

2299 Nos FHTCS provided and 28 km pipe line extended Physical progress 79 %. Pipe supply, 24.8 km laying and 2293 no's FHTCS bill submitted Remaining bill submitted-Balance work arranged.

Perlassery Sn 2 AE
Date: 07/12/2023

Work in progress | 50% Completed

322Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 25/11/2023

Work in progress | 50% Completed

290Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 18/11/2023

Work in progress | 50% Completed

290Nos FHTCS provided .Pipe supply, 2.634km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 09/11/2023

Work in progress | 45% Completed

276Nos FHTCS provided .Pipe supply, 2.597km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 02/11/2023

Work in progress | 35% Completed

256Nos FHTCS provided .Pipe supply, 1.743km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 27/10/2023

Work in progress | 35% Completed

239Nos FHTCS provided .Pipe supply, 1.743km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 21/10/2023

Work in progress | 35% Completed

235Nos FHTCS provided .Pipe supply, 1.743km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 20/10/2023

Work in progress | 35% Completed

222Nos FHTCS provided .Pipe supply, 1.596km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 12/10/2023

Work in progress | 35% Completed

222Nos FHTCS provided .Pipe supply, 1.596km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 03/10/2023

Work in progress | 32% Completed

208Nos FHTCS provided .Pipe supply, 1.594km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 27/09/2023

Work in progress | 32% Completed

208Nos FHTCS provided .Pipe supply, 1.594km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 21/09/2023

Work in progress | 32% Completed

199Nos FHTCS provided .Pipe supply, 1.586km laying and 143nos FHTCS bill submitted.

Attached images

img

Perlassery Sn 2 AE
Date: 13/09/2023

Work in progress | 32% Completed

199Nos FHTCS provided .Pipe supply, 1.586km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 01/09/2023

Work in progress | 32% Completed

192Nos FHTCS provided .Pipe supply, 1.586km laying and 143nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 24/08/2023

Work in progress | 32% Completed

192Nos FHTCS provided .Pipe supply, 1.586km laying and 143no's FHTCS bill submitted.

Kannur PH Dn EE
Date: 17/08/2023

Work in progress | 32% Completed

183Nos FHTCS provided .Pipe supply, 686 km laying and 42 no's FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 09/08/2023

Work in progress | 32% Completed

183Nos FHTCS provided .Pipe supply, 686 km laying and 42 nos FHTCS bill submitted.

Attached images

img

Perlassery Sn 2 AE
Date: 04/08/2023

Work in progress | 32% Completed

170 Nos FHTCS provided .Pipe supply, 686 km laying and 42 nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 31/07/2023

Work in progress | 32% Completed

166 Nos FHTCS provided .Pipe supply, 686 km laying and 42 nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 27/07/2023

Work in progress | 30% Completed

158 Nos FHTCS provided .Pipe supply, 686 km laying and 42 nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 19/07/2023

Work in progress | 30% Completed

149Nos FHTCS provided .Pipe supply, 686 km laying and 42 nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 14/07/2023

Work in progress | 30% Completed

143Nos FHTCS provided .Pipe supply, 686 km laying and 42 nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 10/07/2023

Work in progress | 30% Completed

143Nos FHTCS provided .Pipe supply, 0.626 km laying and 42 nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 04/07/2023

Work in progress | 30% Completed

137Nos FHTCS provided .Pipe supply, 0.626 km laying and 42 nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 30/06/2023

Work in progress | 30% Completed

111Nos FHTCS provided .Pipe supply, 0.626 km laying and 42 nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 24/06/2023

Work in progress | 30% Completed

94Nos FHTCS provided .Pipe supply, 0.626 km laying and 42 nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 19/06/2023

Work in progress | 26% Completed

80Nos FHTCS provided .Pipe supply, 0.626 km laying and 42 nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 16/06/2023

Work in progress | 26% Completed

78 Nos FHTCS provided .Pipe supply, 0.626 km laying and 42 nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 08/06/2023

Work in progress | 26% Completed

64Nos FHTC provided, Nos HTC provided

Perlassery Sn 2 AE
Date: 01/06/2023

Work in progress | 26% Completed

46Nos FHTC provided,84Nos HTC provided

Attached images

img

Perlassery Sn 2 AE
Date: 24/05/2023

Work in progress | 25% Completed

41Nos FHTC provided,65Nos HTC provided

Perlassery Sn 2 AE
Date: 18/05/2023

Work in progress | 25% Completed

41Nos FHTC provided,65Nos HTC provided

Perlassery Sn 2 AE
Date: 15/05/2023

Work in progress | 25% Completed

41Nos FHTC provided,65Nos HTC provided

Perlassery Sn 2 AE
Date: 10/05/2023

Work in progress | 25% Completed

41Nos FHTC provided,59Nos HTC provided

Perlassery Sn 2 AE
Date: 04/05/2023

Work in progress | 25% Completed

41Nos FHTC provided,59Nos HTC provided

Perlassery Sn 2 AE
Date: 26/04/2023

Work in progress | 25% Completed

37Nos FHTC provided,92Nos HTC provided

Perlassery Sn 2 AE
Date: 19/04/2023

Work in progress | 24% Completed

34Nos FHTC provided,92Nos HTC provided

Perlassery Sn 2 AE
Date: 13/04/2023

Work in progress | 22% Completed

34Nos FHTC provided, 72Nos HTC provided

Perlassery Sn 2 AE
Date: 09/04/2023

Work in progress | 22% Completed

34Nos FHTC provided, 28 Nos HTC provided

Perlassery Sn 2 AE
Date: 03/04/2023

Work in progress | 22% Completed

23 Nos FHTC provided, 37 Nos HTC provided

Perlassery Sn 2 AE
Date: 29/03/2023

Work in progress | 20% Completed

23 Nos FHTC provided, 33 Nos HTC provided

Perlassery Sn 2 AE
Date: 22/03/2023

Work in progress | 20% Completed

56 Nos HTC provided. Pipe supplied

Perlassery Sn 2 AE
Date: 18/03/2023

Work in progress | 20% Completed

54 Nos HTC provided. Pipe supplied

Perlassery Sn 2 AE
Date: 14/03/2023

Work in progress | 15% Completed

work in progress

Perlassery Sn 2 AE
Date: 09/03/2023

Work in progress | 15% Completed

Pipe supplied ,550m pipe laid &laying in progress

Perlassery Sn 2 AE
Date: 04/03/2023

Work in progress | 15% Completed

10% WORK COMPLETED

Perlassery Sn 2 AE
Date: 27/02/2023

Work in progress | 5% Completed

work in progress

Perlassery Sn 2 AE
Date: 21/02/2023

Work in progress | 3% Completed

ongoing

Kannur PH Dn EE
Date: 27/01/2023

Work has started | 0% Completed

AGREEMENT EXECUTED ON 27.01.2023

Kannur PH Dn EE
Date: 18/01/2023

Work has started | 0% Completed

WORK ORDER ISSUED ON 18.01.2023

Kannur PH Dn EE
Date: 09/12/2022

Work in progress | 1% Completed

TS Issued for the balance work.