| Kollam WS Sn 1 - AE |
| Date: 16/08/2024 |
Work has been completed | 100% Completed
100 % COMPLETED, Final Bill submitted
| Kollam WS Sn 1 - AE |
| Date: 12/08/2024 |
Work in progress | 79% Completed
79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 09/08/2024 |
Work in progress | 79% Completed
79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 07/08/2024 |
Work in progress | 79% Completed
79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 05/08/2024 |
Work in progress | 79% Completed
79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 01/08/2024 |
| Kollam WS Sn 1 - AE |
| Date: 29/07/2024 |
Work in progress | 79% Completed
79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 25/07/2024 |
Work in progress | 79% Completed
79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 22/07/2024 |
Work in progress | 79% Completed
79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 18/07/2024 |
Work in progress | 60% Completed
60 % COMPLETED, 200 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 15/07/2024 |
Work in progress | 60% Completed
60 % COMPLETED, 200 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 09/07/2024 |
Work in progress | 60% Completed
60 % COMPLETED, 200 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 06/07/2024 |
Work in progress | 60% Completed
60 % COMPLETED, 200 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 02/07/2024 |
Work in progress | 60% Completed
60 % COMPLETED, 200 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 27/06/2024 |
Work in progress | 60% Completed
60 % COMPLETED, 200 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 24/06/2024 |
Work in progress | 60% Completed
60 % COMPLETED, 200 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 21/06/2024 |
Work in progress | 60% Completed
60 % COMPLETED, 200 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 18/06/2024 |
Work in progress | 60% Completed
60 % COMPLETED, 200 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 13/06/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 10/06/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 07/06/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 04/06/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 31/05/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 27/05/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 24/05/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 20/05/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 16/05/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 13/05/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 10/05/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 06/05/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 03/05/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 29/04/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 25/04/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 22/04/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 19/04/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 15/04/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 11/04/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 08/04/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 05/04/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 02/04/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 30/03/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 27/03/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 25/03/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 21/03/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 18/03/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 15/03/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 11/03/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 07/03/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 04/03/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 01/03/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 27/02/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED
| Kollam WS Sn 1 - AE |
| Date: 24/02/2024 |
Work in progress | 40% Completed
40 % COMPLETED, 170 NOS. OF TAP DISCONNECTED.
| Kollam WS Sn 1 - AE |
| Date: 20/02/2024 |
Work in progress | 30% Completed
30 % COMPLETED, 140 NOS. OF TAP DISCONNECTED.
| Kollam WS Sn 1 - AE |
| Date: 17/02/2024 |
Work in progress | 30% Completed
30 % COMPLETED, 140 NOS. OF TAP DISCONNECTED.
| Kollam WS Sn 1 - AE |
| Date: 14/02/2024 |
Work in progress | 20% Completed
work started on 01/02/2024.Total 120 public tap disconnected
| Kollam WS Sn 1 - AE |
| Date: 12/02/2024 |
Work in progress | 10% Completed
work started on 01/02/2024.Total 110 public tap disconnected
| Kollam WS Sn 1 - AE |
| Date: 05/02/2024 |
Work in progress | 4% Completed
work started on 01/02/2024
| Kollam WS Sn 1 - AE |
| Date: 01/02/2024 |
Work in progress | 1% Completed
work started on 01/02/2024
| Kollam WS Sn 1 - AE |
| Date: 29/01/2024 |
Work in progress | 1% Completed
Agreement executed on 12/01/2024
| Kollam WS Sn 1 - AE |
| Date: 25/01/2024 |
Work in progress | 1% Completed
Agreement executed on 12/01/2024
| Kollam WS Sn 1 - AE |
| Date: 22/01/2024 |
Work in progress | 1% Completed
Agreement executed on 12/01/2024