| Kannur PH Sn 3 AE |
| Date: 04/10/2025 |
Work has been completed | 100% Completed
Work completed, 6km pipe laid, 549 FHTC given
| Kannur PH Sn 3 AE |
| Date: 10/09/2025 |
Work has been completed | 100% Completed
Work completed, 6km pipe laid, 549 FHTC given
| Kannur PH Sn 3 AE |
| Date: 30/08/2025 |
Work has been completed | 100% Completed
Work completed, 6km pipe laid, 549 FHTC given
| Kannur PH Sn 3 AE |
| Date: 08/08/2025 |
Work has been completed | 100% Completed
Work has been completed
| Kannur PH Sn 3 AE |
| Date: 31/07/2025 |
Work has been completed | 100% Completed
Work has been completed
| Kannur PH Sn 3 AE |
| Date: 19/07/2025 |
Work has been completed | 100% Completed
Work has been completed
| Kannur PH Sn 3 AE |
| Date: 14/07/2025 |
Work has been completed | 100% Completed
Work has been completed
| Kannur PH Sn 3 AE |
| Date: 30/06/2025 |
Work has been completed | 100% Completed
Work completed
| Kannur PH Sn 3 AE |
| Date: 27/06/2025 |
Work has been completed | 100% Completed
Work completed
| Kannur PH Sn 3 AE |
| Date: 23/06/2025 |
Work in progress | 80% Completed
6 KM pipe laid 550 nos FHTC given. road restoration-3.3km
| Kannur PH Sn 3 AE |
| Date: 17/06/2025 |
Work in progress | 80% Completed
6 KM pipe laid 550 nos FHTC given. road restoration-3.3km
| Kannur PH Sn 3 AE |
| Date: 29/05/2025 |
Work in progress | 78% Completed
6 KM pipe laid 550 nos FHTC given. road restoration-3.3km
| Kannur PH Sn 3 AE |
| Date: 19/05/2025 |
Work in progress | 78% Completed
6 KM pipe laid 550 nos FHTC given.Road restortion-3.3km
| Kannur PH Sn 3 AE |
| Date: 03/05/2025 |
Work in progress | 75% Completed
6 KM pipe laid 550 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 05/04/2025 |
Work in progress | 75% Completed
6 KM pipe laid 550 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 29/03/2025 |
Work in progress | 75% Completed
6 KM pipe laid 550 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 27/03/2025 |
Work in progress | 75% Completed
6 KM pipe laid 600 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 03/03/2025 |
Work in progress | 75% Completed
6 KM pipe laid 600 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 22/02/2025 |
Work in progress | 75% Completed
6 KM pipe laid 600 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 12/02/2025 |
Work in progress | 75% Completed
6 KM pipe laid 600 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 07/02/2025 |
Work in progress | 75% Completed
6 KM pipe laid 600 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 01/02/2025 |
Work in progress | 75% Completed
6 KM pipe laid 600 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 29/01/2025 |
Work in progress | 75% Completed
6 KM pipe laid 600 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 24/01/2025 |
Work in progress | 75% Completed
6 KM pipe laid 600 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 22/01/2025 |
Work in progress | 75% Completed
6 KM pipe laid 600 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 18/01/2025 |
Work in progress | 75% Completed
6 KM pipe laid 560 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 16/01/2025 |
Work in progress | 75% Completed
5.9 KM pipe laid 560 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 10/01/2025 |
Work in progress | 75% Completed
5.9 KM pipe laid 560 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 04/01/2025 |
Work in progress | 75% Completed
5.9 KM pipe laid 560 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 31/12/2024 |
Work in progress | 44% Completed
5.3 KM pipe laid 550 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 24/12/2024 |
Work in progress | 44% Completed
5.3 KM pipe laid 550 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 21/12/2024 |
Work in progress | 44% Completed
5.3 KM pipe laid 550 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 20/12/2024 |
Work in progress | 44% Completed
5.3 KM pipe laid 550 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 17/12/2024 |
Work in progress | 44% Completed
5.3 KM pipe laid 550 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 16/12/2024 |
Work in progress | 44% Completed
5.3 KM pipe laid 550 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 10/12/2024 |
Work in progress | 44% Completed
5.3 KM pipe laid 550 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 07/12/2024 |
Work in progress | 44% Completed
5.3 KM pipe laid 550 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 05/12/2024 |
Work in progress | 44% Completed
5.3 KM pipe laid 550 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 02/12/2024 |
Work in progress | 44% Completed
5.3 KM pipe laid 550 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 29/11/2024 |
Work in progress | 44% Completed
5.3 KM pipe laid 550 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 26/11/2024 |
Work in progress | 44% Completed
5.3 KM pipe laid 530 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 22/11/2024 |
Work in progress | 44% Completed
5.3 KM pipe laid 530 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 19/11/2024 |
Work in progress | 44% Completed
5.3 KM pipe laid 530 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 16/11/2024 |
Work in progress | 44% Completed
5.3 KM pipe laid 530 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 12/11/2024 |
Work in progress | 43% Completed
5.2 KM pipe laid 510 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 08/11/2024 |
Work in progress | 43% Completed
5.2 KM pipe laid 510 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 07/11/2024 |
Work in progress | 43% Completed
5.2 KM pipe laid 510 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 04/11/2024 |
Work in progress | 43% Completed
5.2 KM pipe laid 510 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 02/11/2024 |
Work in progress | 43% Completed
5.1 KM pipe laid 510 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 01/11/2024 |
Work in progress | 43% Completed
5.1 KM pipe laid 510 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 30/10/2024 |
Work in progress | 43% Completed
5.1 KM pipe laid 510 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 28/10/2024 |
Work in progress | 43% Completed
5.1 KM pipe laid 510 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 26/10/2024 |
Work in progress | 43% Completed
5.1 KM pipe laid 510 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 25/10/2024 |
Work in progress | 43% Completed
5.1 KM pipe laid 510 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 24/10/2024 |
Work in progress | 43% Completed
5.1 KM pipe laid 510 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 22/10/2024 |
Work in progress | 42% Completed
4.9 KM pipe laid 510 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 21/10/2024 |
Work in progress | 40% Completed
4.9 KM pipe laid 420 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 18/10/2024 |
Work in progress | 40% Completed
4.9 KM pipe laid 400 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 16/10/2024 |
Work in progress | 40% Completed
4.9 KM pipe laid 400 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 14/10/2024 |
Work in progress | 40% Completed
4.9 KM pipe laid 380 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 10/10/2024 |
Work in progress | 40% Completed
4.9 KM pipe laid 360 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 07/10/2024 |
Work in progress | 40% Completed
4.8 KM pipe laid 340 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 04/10/2024 |
Work in progress | 40% Completed
4.5 KM pipe laid 300 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 01/10/2024 |
Work in progress | 40% Completed
4.5 KM pipe laid 300 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 28/09/2024 |
Work in progress | 40% Completed
4.5 KM pipe laid 300 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 26/09/2024 |
Work in progress | 40% Completed
4.5 KM pipe laid 300 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 23/09/2024 |
Work in progress | 40% Completed
4.5 KM pipe laid 280 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 20/09/2024 |
Work in progress | 40% Completed
4.5 KM pipe laid 280 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 18/09/2024 |
Work in progress | 39% Completed
2.9 KM pipe laid 150 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 12/09/2024 |
Work in progress | 39% Completed
2.9 KM pipe laid 150 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 09/09/2024 |
Work in progress | 39% Completed
2.9 KM pipe laid 150 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 06/09/2024 |
Work in progress | 39% Completed
2.9 KM pipe laid 150 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 03/09/2024 |
Work in progress | 39% Completed
2.9 KM pipe laid 150 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 30/08/2024 |
Work in progress | 39% Completed
2.9 KM pipe laid 150 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 27/08/2024 |
Work in progress | 39% Completed
2.9 KM pipe laid 150 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 24/08/2024 |
Work in progress | 39% Completed
2.9 KM pipe laid 150 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 22/08/2024 |
Work in progress | 39% Completed
2.9 KM pipe laid 150 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 19/08/2024 |
Work in progress | 39% Completed
2.9 KM pipe laid 150 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 16/08/2024 |
Work in progress | 39% Completed
2.9 KM pipe laid 150 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 12/08/2024 |
Work in progress | 39% Completed
2.9 KM pipe laid 150 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 08/08/2024 |
Work in progress | 39% Completed
2.9 KM pipe laid 150 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 05/08/2024 |
Work in progress | 39% Completed
2.9 KM pipe laid 150 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 02/08/2024 |
Work in progress | 39% Completed
2.9 KM pipe laid 150 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 30/07/2024 |
Work in progress | 39% Completed
2.9 KM pipe laid 150 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 27/07/2024 |
Work in progress | 39% Completed
2.9 KM pipe laid 150 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 23/07/2024 |
Work in progress | 39% Completed
2.9 KM pipe laid 150 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 20/07/2024 |
Work in progress | 36% Completed
2.6 KM pipe laid 120 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 19/07/2024 |
Work in progress | 36% Completed
2.6 KM pipe laid 120 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 17/07/2024 |
Work in progress | 36% Completed
2.6 KM pipe laid 120 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 15/07/2024 |
Work in progress | 36% Completed
2.6 KM pipe laid 120 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 10/07/2024 |
Work in progress | 36% Completed
2.6 KM pipe laid 120 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 06/07/2024 |
Work in progress | 36% Completed
2.6 KM pipe laid 60 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 03/07/2024 |
Work in progress | 36% Completed
2.6 KM pipe laid 60 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 01/07/2024 |
Work in progress | 35% Completed
2.6 KM pipe laid 50 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 27/06/2024 |
Work in progress | 35% Completed
2.6 KM pipe laid 50 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 24/06/2024 |
Work in progress | 35% Completed
2.6 KM pipe laid 50 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 22/06/2024 |
Work in progress | 35% Completed
2.6 KM pipe laid 50 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 18/06/2024 |
Work in progress | 35% Completed
2.6 KM pipe laid 50 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 13/06/2024 |
Work in progress | 35% Completed
2.6 KM pipe laid 50 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 10/06/2024 |
Work in progress | 35% Completed
2.6 KM pipe laid 50 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 05/06/2024 |
Work in progress | 35% Completed
2.6 KM pipe laid 50 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 01/06/2024 |
Work in progress | 35% Completed
2.6 KM pipe laid 50 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 29/05/2024 |
Work in progress | 25% Completed
25% Completed |
| Kannur PH Sn 3 AE |
| Date: 25/05/2024 |
Work in progress | 25% Completed
2 KM pipe laid 32 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 22/05/2024 |
Work in progress | 25% Completed
2 KM pipe laid 32 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 18/05/2024 |
Work in progress | 25% Completed
2 KM pipe laid 32 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 14/05/2024 |
Work in progress | 20% Completed
1150 M pipe laid 32 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 10/05/2024 |
Work in progress | 20% Completed
1150 M pipe laid 32 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 07/05/2024 |
Work in progress | 10% Completed
700 M pipe laid 32 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 02/05/2024 |
Work in progress | 10% Completed
150 M pipe laid 32 nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 27/04/2024 |
Work in progress | 10% Completed
10 % COMPLETED
| Kannur PH Sn 3 AE |
| Date: 24/04/2024 |
Work in progress | 10% Completed
10 % COMPLETED