Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Painavu PH Section AE
Date: 13/04/2023

Work has been completed | 100% Completed

Completed

Painavu PH Section AE
Date: 10/04/2023

Work in progress | 90% Completed

Pipe Laying Completed. Line Charges. Since all houses around the pipe line is having consumer connections, we could not able to find new connection as mentioned in the work. Work can be marked as completed with since pipe laying is completed

Painavu PH Section AE
Date: 23/03/2023

Work in progress | 80% Completed

Line Charging work in progress

Painavu PH Section AE
Date: 18/03/2023

Work in progress | 80% Completed

Pipe Laying Works completed

Painavu PH Section AE
Date: 13/03/2023

Work in progress | 80% Completed

Pipe Laying Works completed

Painavu PH Section AE
Date: 08/03/2023

Work in progress | 45% Completed

Pipe Laying Works going on

Painavu PH Section AE
Date: 27/02/2023

Work in progress | 43% Completed

Pipe Laying works in progress

Painavu PH Section AE
Date: 21/02/2023

Work in progress | 40% Completed

Pipe Laying Works going on

Painavu PH Section AE
Date: 14/02/2023

Work in progress | 35% Completed

Pipe Laying Works going on

Painavu PH Section AE
Date: 06/02/2023

Work in progress | 25% Completed

Pipe Laying started

Painavu PH Section AE
Date: 27/01/2023

Work in progress | 25% Completed

Pipe Laying will start soon

Painavu PH Section AE
Date: 20/01/2023

Work in progress | 24% Completed

Pipe Laying will start soon

Painavu PH Section AE
Date: 10/01/2023

Work in progress | 24% Completed

Pipe laying will start next week

Painavu PH Section AE
Date: 04/01/2023

Work in progress | 24% Completed

Pipe laying will begin soon

Painavu PH Section AE
Date: 26/12/2022

Work in progress | 24% Completed

Pipe Laying is not Started

Painavu PH Section AE
Date: 17/12/2022

Work in progress | 24% Completed

Pipe Laying not started because the work is going on at another site

Painavu PH Section AE
Date: 13/12/2022

Work in progress | 24% Completed

Pipe Laying not started yet due to ongoing works in other areas

Painavu PH Section AE
Date: 08/12/2022

Work in progress | 24% Completed

Pipe supply done

Painavu PH Section AE
Date: 03/12/2022

Work in progress | 23% Completed

Work in progress

Painavu PH Section AE
Date: 29/11/2022

Work in progress | 23% Completed

Work on going

Painavu PH Section AE
Date: 24/11/2022

Work in progress | 22% Completed

Work on going

Painavu PH Section AE
Date: 16/11/2022

Work in progress | 20% Completed

Pipe supply done, work started

Painavu PH Sub Dn AEE
Date: 06/11/2022

Work in progress | 2% Completed

work in progress

Painavu PH Sub Dn AEE
Date: 15/10/2022

Work has started | 0% Completed

pipe tested on 14.10.22

Painavu PH Section AE
Date: 03/10/2022

Work in progress | 0% Completed

Agreement executed, pipe supply not done

Painavu PH Sub Dn AEE
Date: 02/10/2022

Work has started | 0% Completed

pipe supply order placed in the firm

Painavu PH Sub Dn AEE
Date: 20/09/2022

Work has started | 0% Completed

Agreement executed

Painavu PH Section AE
Date: 13/09/2022

Work has started | 0% Completed

work order issued

Painavu PH Section AE
Date: 01/09/2022

Work has started | 0% Completed

work order issued

Thodupuzha PH Dn EE
Date: 27/08/2022

Work has started | 0% Completed

Work Order Issued