| Painavu PH Section AE |
| Date: 13/04/2023 |
Work has been completed | 100% Completed
Completed
| Painavu PH Section AE |
| Date: 10/04/2023 |
Work in progress | 90% Completed
Pipe Laying Completed. Line Charges. Since all houses around the pipe line is having consumer connections, we could not able to find new connection as mentioned in the work. Work can be marked as completed with since pipe laying is completed
| Painavu PH Section AE |
| Date: 23/03/2023 |
Work in progress | 80% Completed
Line Charging work in progress
| Painavu PH Section AE |
| Date: 18/03/2023 |
Work in progress | 80% Completed
Pipe Laying Works completed
| Painavu PH Section AE |
| Date: 13/03/2023 |
Work in progress | 80% Completed
Pipe Laying Works completed
| Painavu PH Section AE |
| Date: 08/03/2023 |
Work in progress | 45% Completed
Pipe Laying Works going on
| Painavu PH Section AE |
| Date: 27/02/2023 |
Work in progress | 43% Completed
Pipe Laying works in progress
| Painavu PH Section AE |
| Date: 21/02/2023 |
Work in progress | 40% Completed
Pipe Laying Works going on
| Painavu PH Section AE |
| Date: 14/02/2023 |
Work in progress | 35% Completed
Pipe Laying Works going on
| Painavu PH Section AE |
| Date: 06/02/2023 |
Work in progress | 25% Completed
Pipe Laying started
| Painavu PH Section AE |
| Date: 27/01/2023 |
Work in progress | 25% Completed
Pipe Laying will start soon
| Painavu PH Section AE |
| Date: 20/01/2023 |
Work in progress | 24% Completed
Pipe Laying will start soon
| Painavu PH Section AE |
| Date: 10/01/2023 |
Work in progress | 24% Completed
Pipe laying will start next week
| Painavu PH Section AE |
| Date: 04/01/2023 |
Work in progress | 24% Completed
Pipe laying will begin soon
| Painavu PH Section AE |
| Date: 26/12/2022 |
Work in progress | 24% Completed
Pipe Laying is not Started
| Painavu PH Section AE |
| Date: 17/12/2022 |
Work in progress | 24% Completed
Pipe Laying not started because the work is going on at another site
| Painavu PH Section AE |
| Date: 13/12/2022 |
Work in progress | 24% Completed
Pipe Laying not started yet due to ongoing works in other areas
| Painavu PH Section AE |
| Date: 08/12/2022 |
Work in progress | 24% Completed
Pipe supply done
| Painavu PH Section AE |
| Date: 03/12/2022 |
Work in progress | 23% Completed
Work in progress
| Painavu PH Section AE |
| Date: 29/11/2022 |
Work in progress | 23% Completed
Work on going
| Painavu PH Section AE |
| Date: 24/11/2022 |
Work in progress | 22% Completed
Work on going
| Painavu PH Section AE |
| Date: 16/11/2022 |
Work in progress | 20% Completed
Pipe supply done, work started
| Painavu PH Sub Dn AEE |
| Date: 06/11/2022 |
Work in progress | 2% Completed
work in progress
| Painavu PH Sub Dn AEE |
| Date: 15/10/2022 |
Work has started | 0% Completed
pipe tested on 14.10.22
| Painavu PH Section AE |
| Date: 03/10/2022 |
Work in progress | 0% Completed
Agreement executed, pipe supply not done
| Painavu PH Sub Dn AEE |
| Date: 02/10/2022 |
Work has started | 0% Completed
pipe supply order placed in the firm
| Painavu PH Sub Dn AEE |
| Date: 20/09/2022 |
Work has started | 0% Completed
Agreement executed
| Painavu PH Section AE |
| Date: 13/09/2022 |
Work has started | 0% Completed
work order issued
| Painavu PH Section AE |
| Date: 01/09/2022 |
Work has started | 0% Completed
work order issued
| Thodupuzha PH Dn EE |
| Date: 27/08/2022 |
Work has started | 0% Completed
Work Order Issued