Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Kozhikode PH Dn EE
Date: 20/03/2025

Work has been completed | 100% Completed

Final bill submitted.

Kozhikode PH Dn EE
Date: 11/02/2025

Work has been completed | 100% Completed

Final bill submitted.

Kozhikode PH Dn EE
Date: 22/01/2025

Work has been completed | 100% Completed

Final bill submitted.

Kozhikode PH Dn EE
Date: 10/01/2025

Work has been completed | 100% Completed

Work completed.

Kozhikode PH Dn EE
Date: 03/01/2025

Work has been completed | 100% Completed

Work completed.

Kozhikode PH Dn EE
Date: 11/12/2024

Work has been completed | 100% Completed

Work completed.

Kozhikode PH Dn EE
Date: 07/12/2024

Work has been completed | 100% Completed

Work completed.

Kozhikode PH Dn EE
Date: 02/12/2024

Work has been completed | 100% Completed

Work completed.

Kozhikode PH Dn EE
Date: 27/11/2024

Work has been completed | 100% Completed

Work completed.

Kozhikode PH Dn EE
Date: 22/11/2024

Work has been completed | 100% Completed

Work completed.

Kozhikode PH Dn EE
Date: 19/11/2024

Work has been completed | 100% Completed

Work completed

Kozhikode PH Dn EE
Date: 13/11/2024

Work has been completed | 100% Completed

Work completed

Kozhikode PH Dn EE
Date: 11/11/2024

Work has been completed | 100% Completed

Work completed

Kozhikode PH Dn EE
Date: 29/10/2024

Work has been completed | 100% Completed

Work completed

Kozhikode PH Dn EE
Date: 19/10/2024

Work has been completed | 100% Completed

Work completed

Kozhikode PH Dn EE
Date: 28/09/2024

Work in progress | 98% Completed

Road restoration works are pending

Kozhikode PH Dn EE
Date: 19/09/2024

Work in progress | 98% Completed

Road restoration works are pending

Kozhikode PH Dn EE
Date: 10/09/2024

Work in progress | 98% Completed

road restoration works are pending

Kozhikode PH Dn EE
Date: 21/08/2024

Work in progress | 98% Completed

Only road restoration works are pending

Kozhikode PH Dn EE
Date: 27/06/2024

Work in progress | 95% Completed

on going

Kozhikode PH Dn EE
Date: 20/04/2024

Work in progress | 40% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 04/04/2024

Work in progress | 24% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 12/03/2024

Work in progress | 20% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 14/02/2024

Work in progress | 15% Completed

Work started

Kozhikode PH Dn EE
Date: 27/01/2024

Work has started | 0% Completed

Site Handed Over

Kozhikode PH Dn EE
Date: 11/01/2024

Work has started | 0% Completed

Site Handed Over

Kozhikode PH Dn EE
Date: 11/12/2023

Work has started | 0% Completed

Site Handed Over

Kozhikode PH Dn EE
Date: 29/11/2023

Work has started | 0% Completed

Site Handed Over

Kozhikode PH Dn EE
Date: 28/10/2023

Work has started | 0% Completed

Site Handed Over