Piravam Project Sub Dn AE 2 |
Date: 27/06/2024 |
Work in progress | 1% Completed
Site clearance completed at WTP site at Palamattom for providing production components.WTP structural design under progress.Retaining wall work started.
Piravam Project Sub Dn AE 2 |
Date: 26/06/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 24/06/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 21/06/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 13/06/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 03/06/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 21/05/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 17/05/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 14/05/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 08/05/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 06/05/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 27/04/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 20/04/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 15/04/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 06/04/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 27/03/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 19/03/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 12/03/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 01/03/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 26/02/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 20/02/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 14/02/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 13/02/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 07/02/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 03/02/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 29/01/2024 |
Work in progress | 1% Completed
Site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 22/01/2024 |
Work in progress | 1% Completed
site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 16/01/2024 |
Work in progress | 1% Completed
site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 09/01/2024 |
Work in progress | 1% Completed
site clearance work progressing at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 04/01/2024 |
Work in progress | 1% Completed
site clearence work started at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 18/12/2023 |
Work in progress | 1% Completed
site clearence work started at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 11/12/2023 |
Work in progress | 1% Completed
site clearence work started at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 06/12/2023 |
Work in progress | 1% Completed
site clearence work started at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 30/11/2023 |
Work in progress | 1% Completed
site clearence work started at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 27/11/2023 |
Work in progress | 1% Completed
site clearence work started at WTP site at Palamattom for providing production components.
Piravam Project Sub Dn AE 2 |
Date: 23/11/2023 |
Work in progress | 1% Completed
site clearence work started at WTP site at Palamattom for providing production components.