Thrissur WW Sn - AE 1 |
Date: 28/06/2024 |
Work has started | 0% Completed
Hydraulic design and design drawings in progress. Site handover completed. work not started design to be submitted by contractor
Thrissur WW Sn - AE 1 |
Date: 24/06/2024 |
Work has started | 0% Completed
Hydraulic design and design drawings in progress. Site handover completed. work not started design to be submitted by contractor
Thrissur WW Sn - AE 1 |
Date: 21/06/2024 |
Work has started | 0% Completed
Hydraulic design and design drawings in progress. Site handover completed. work not started design to be submitted by contractor
Thrissur WW Sn - AE 1 |
Date: 18/06/2024 |
Work has started | 0% Completed
Hydraulic design and design drawings in progress. Site handover completed. work not started design to be submitted by contractor
Thrissur WW Sn - AE 1 |
Date: 14/06/2024 |
Work has started | 0% Completed
Hydraulic design and design drawings in progress. Site handover completed. work not started design to be submitted by contractor
Thrissur WW Sn - AE 1 |
Date: 10/06/2024 |
Work has started | 0% Completed
Hydraulic design and design drawings in progress. Site handover completed. work not started design to be submitted by contractor
Thrissur WW Sn - AE 1 |
Date: 05/06/2024 |
Work in progress | 0% Completed
Hydraulic design and design drawings in progress. Site handover completed. work not started design to be submitted by contractor
Thrissur WW Sn - AE 1 |
Date: 03/06/2024 |
Work has started | 0% Completed
Hydraulic design and design drawings in progress. Site handover completed. work not started design to be submitted by contractor
Thrissur PH Dn EE |
Date: 30/05/2024 |
Work has started | 0% Completed
Hydraulic design and design drawings in progress. Site handover completed. work not started design to be submitted by contractor
Thrissur WW Sn - AE 1 |
Date: 27/05/2024 |
Work has started | 0% Completed
Hydraulic design and design drawings in progress.
Thrissur WW Sn - AE 1 |
Date: 23/05/2024 |
Work in progress | 0% Completed
Hydraulic design and design drawings in progress.
Thrissur WW Sn - AE 1 |
Date: 18/05/2024 |
Work has started | 0% Completed
Hydraulic design and design drawings in progress.
Thrissur WW Sn - AE 1 |
Date: 14/05/2024 |
Work has started | 0% Completed
Hydraulic design and design drawings in progress.
Thrissur WW Sn - AE 1 |
Date: 10/05/2024 |
Work has started | 0% Completed
Hydraulic design and design drawings in progress.
Thrissur WW Sn - AE 1 |
Date: 06/05/2024 |
Work has started | 0% Completed
Hydraulic design and design drawings in progress.
Thrissur PH Dn EE |
Date: 02/05/2024 |
Work has started | 0% Completed
Hydraulic design and design drawings in progress.
Thrissur WW Sn - AE 1 |
Date: 30/04/2024 |
Work has started | 0% Completed
Hydraulic design and design drawings in progress.
Thrissur PH Dn EE |
Date: 29/04/2024 |
Work has started | 0% Completed
Hydraulic design and design drawings in progress.
Thrissur PH Dn EE |
Date: 27/04/2024 |
Work has started | 0% Completed
Hydraulic design and design drawings in progress.
Thrissur WW Sn - AE 1 |
Date: 23/04/2024 |
Work has started | 0% Completed
Hydraulic design and design drawings in progress.
Thrissur PH Dn EE |
Date: 19/04/2024 |
Work has started | 0% Completed
We have letter for testing the materials
Thrissur WW Sn - AE 1 |
Date: 16/04/2024 |
Work has started | 0% Completed
We have letter for testing the materials
Thrissur WW Sn - AE 1 |
Date: 15/04/2024 |
Work has started | 0% Completed
We have letter for testing the materials
Thrissur PH Dn EE |
Date: 12/04/2024 |
Work has started | 0% Completed
We have letter for testing the materials.
Thrissur WW Sn - AE 1 |
Date: 08/04/2024 |
Work has started | 0% Completed
We have letter for testing the materials.
Thrissur PH Dn EE |
Date: 06/04/2024 |
Work has started | 0% Completed
We have letter for testing the materials.
Thrissur PH Dn EE |
Date: 02/04/2024 |
Work has started | 0% Completed
We have letter for testing the materials.
Thrissur WW Sn - AE 1 |
Date: 30/03/2024 |
Work has started | 0% Completed
We have letter for testing the materials.
Thrissur PH Dn EE |
Date: 26/03/2024 |
Work has started | 0% Completed
We have letter for testing the materials.
Thrissur PH Dn EE |
Date: 22/03/2024 |
Work has started | 0% Completed
We have letter for testing the materials.
Thrissur PH Dn EE |
Date: 18/03/2024 |
Work has started | 0% Completed
We have letter for testing the materials.
Thrissur PH Dn EE |
Date: 14/03/2024 |
Work has started | 0% Completed
We have letter for testing the materials.
Thrissur WW Sn - AE 1 |
Date: 13/03/2024 |
Work has started | 0% Completed
We have letter for testing the materials.
Thrissur PH Dn EE |
Date: 09/03/2024 |
Work has started | 0% Completed
We have letter for testing the materials.
Thrissur WW Sn - AE 1 |
Date: 05/03/2024 |
Work has started | 0% Completed
We have letter for testing the materials.
Thrissur PH Dn EE |
Date: 02/03/2024 |
Work has started | 0% Completed
We have letter for testing the materials.
Thrissur WW Sn - AE 1 |
Date: 29/02/2024 |
Work has started | 0% Completed
We have letter for testing the materials
Thrissur WW Sn - AE 1 |
Date: 26/02/2024 |
Work has started | 0% Completed
We have letter for testing the materials
Thrissur WW Sn - AE 1 |
Date: 23/02/2024 |
Work has started | 0% Completed
We have letter for testing the materials
Thrissur WW Sn - AE 1 |
Date: 19/02/2024 |
Work has started | 0% Completed
We have letter for testing the materials
Thrissur WW Sn - AE 1 |
Date: 15/02/2024 |
Work has started | 0% Completed
We have letter for testing the materials
Thrissur WW Sn - AE 1 |
Date: 12/02/2024 |
Work has started | 0% Completed
We have letter for testing the materials
Thrissur WW Sn - AE 1 |
Date: 08/02/2024 |
Work has started | 0% Completed
We have letter for testing the materials
Thrissur WW Sn - AE 1 |
Date: 06/02/2024 |
Work has started | 0% Completed
We have letter for testing the materials
Thrissur WW Sn - AE 1 |
Date: 02/02/2024 |
Work has started | 0% Completed
We have letter for testing the materials
Thrissur WW Sn - AE 1 |
Date: 29/01/2024 |
Work has started | 0% Completed
Site Handover
Thrissur WW Sn - AE 1 |
Date: 25/01/2024 |
Work has started | 0% Completed
Site Handover
Thrissur WW Sn - AE 1 |
Date: 22/01/2024 |
Work has started | 0% Completed
Site Handover
Thrissur WW Sn - AE 1 |
Date: 18/01/2024 |
Work has started | 0% Completed
Site Handover
Thrissur WW Sn - AE 1 |
Date: 16/01/2024 |
Work has started | 0% Completed
Site Handover
Thrissur WW Sn - AE 1 |
Date: 11/01/2024 |
Work has started | 0% Completed
Work order issued on 21/09/2023. Agreement executed on 13/11/2023
Thrissur WW Sn - AE 1 |
Date: 08/01/2024 |
Work has started | 0% Completed
Work order issued on 21/09/2023. Agreement executed on 13/11/2023
Thrissur WW Sn - AE 1 |
Date: 03/01/2024 |
Work has started | 0% Completed
Work order issued on 21/09/2023. Agreement executed on 13/11/2023
Thrissur WW Sn - AE 1 |
Date: 01/01/2024 |
Work has started | 0% Completed
Work order issued on 21/09/2023. Agreement executed on 13/11/2023
Thrissur WW Sn - AE 1 |
Date: 28/12/2023 |
Work has started | 0% Completed
Work order issued on 21/09/2023. Agreement executed on 13/11/2023
Thrissur WW Sn - AE 1 |
Date: 26/12/2023 |
Work has started | 0% Completed
Work order issued on 21/09/2023. Agreement executed on 13/11/2023
Thrissur PH Dn EE |
Date: 22/12/2023 |
Work has started | 0% Completed
Work order issued on 21/09/2023. Agreement executed on 13/11/2023
Thrissur WW Sn - AE 1 |
Date: 21/12/2023 |
Work has started | 0% Completed
Work order issued on 21/09/2023. Agreement executed on 13/11/2023
Thrissur WW Sn - AE 1 |
Date: 18/12/2023 |
Work has started | 0% Completed
Work order issued on 21/09/2023. Agreement executed on 13/11/2023
Thrissur PH Dn EE |
Date: 16/12/2023 |
Work has started | 0% Completed
Work order issued on 21/09/2023. Agreement executed on 13/11/2023
Thrissur WW Sn - AE 1 |
Date: 14/12/2023 |
Work has started | 0% Completed
Work order issued on 21/09/2023. Agreement executed on 13/11/2023
Thrissur WW Sn - AE 1 |
Date: 11/12/2023 |
Work has started | 0% Completed
Work order issued on 21/09/2023. Agreement executed on 13/11/2023
Thrissur PH Dn EE |
Date: 08/12/2023 |
Work has started | 0% Completed
Work order issued on 21/09/2023. Agreement executed on 13/11/2023.
Thrissur PH Dn EE |
Date: 05/12/2023 |
Work has started | 0% Completed
Work order issued on 21/09/2023. Agreement executed on 13/11/2023.