| Nedumangad AE |
| Date: 14/02/2024 |
Work has been completed | 100% Completed
completed
| Nedumangad AE |
| Date: 13/02/2024 |
Work in progress | 65% Completed
pipe laying under progress
| Aruvikkara HW Dn EE |
| Date: 07/02/2024 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 03/02/2024 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 31/01/2024 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 27/01/2024 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 24/01/2024 |
Work in progress | 65% Completed
pipe laying under progress
| Aruvikkara HW Dn EE |
| Date: 20/01/2024 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 15/01/2024 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 09/01/2024 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 05/01/2024 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 03/01/2024 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 30/12/2023 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 28/12/2023 |
Work in progress | 65% Completed
pipe laying under progress
| Aruvikkara HW Dn EE |
| Date: 26/12/2023 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 22/12/2023 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 18/12/2023 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 12/12/2023 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 08/12/2023 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 05/12/2023 |
Work in progress | 65% Completed
pipe laying under progress
| Aruvikkara HW Dn EE |
| Date: 01/12/2023 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 28/11/2023 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 24/11/2023 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 20/11/2023 |
Work in progress | 65% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 18/11/2023 |
Work in progress | 57% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 15/11/2023 |
Work in progress | 57% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 13/11/2023 |
Work in progress | 57% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 09/11/2023 |
Work in progress | 57% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 06/11/2023 |
Work in progress | 55% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 03/11/2023 |
Work in progress | 55% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 30/10/2023 |
Work in progress | 55% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 26/10/2023 |
Work in progress | 55% Completed
pipe laying under progress
| Aruvikkara HW Dn EE |
| Date: 24/10/2023 |
Work in progress | 55% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 20/10/2023 |
Work in progress | 55% Completed
pipe laying under progress
| Aruvikkara HW Dn EE |
| Date: 18/10/2023 |
Work in progress | 55% Completed
pipe laying under progress
| Aruvikkara HW Dn EE |
| Date: 14/10/2023 |
Work in progress | 55% Completed
pipe laying under progress
| Aruvikkara HW Dn EE |
| Date: 08/10/2023 |
Work in progress | 53% Completed
pipe laying under progress
| Aruvikkara HW Dn EE |
| Date: 04/10/2023 |
Work in progress | 53% Completed
pipe laying under progress
| Aruvikkara HW Dn EE |
| Date: 30/09/2023 |
Work in progress | 52% Completed
pipe laying under progress
| Aruvikkara HW Dn EE |
| Date: 26/09/2023 |
Work in progress | 52% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 22/09/2023 |
Work in progress | 52% Completed
pipe laying under progress
| Nedumangad AE |
| Date: 19/09/2023 |
Work in progress | 52% Completed
ongoing
| Aruvikkara HW Dn EE |
| Date: 15/09/2023 |
Work in progress | 50% Completed
UWSS to Nedumanagad-Augmentation enhancing the distribution net works Nedumanangad Municipal area
| Aruvikkara HW Dn EE |
| Date: 11/09/2023 |
Work in progress | 50% Completed
UWSS to Nedumanagad-Augmentation enhancing the distribution net works Nedumanangad Municipal area
| Aruvikkara HW Dn EE |
| Date: 07/09/2023 |
Work in progress | 50% Completed
UWSS to Nedumanagad-Augmentation enhancing the distribution net works Nedumanangad Municipal area