Oachira AE
Date: 19/05/2025

Work has been completed | 100% Completed

Work completed on 17-05-2025.

Attached images

img img

Oachira AE
Date: 16/05/2025

Work in progress | 75% Completed

Pipe laying and interconnection work completed. Providing water connection and re concrete to be completed.

Oachira AE
Date: 12/05/2025

Work in progress | 75% Completed

Pipe laying and interconnection work completed. Providing water connection and re concrete to be completed.

Oachira AE
Date: 08/05/2025

Work in progress | 75% Completed

Pipe laying and interconnection work completed. Providing water connection and re concrete to be completed.

Oachira AE
Date: 05/05/2025

Work in progress | 75% Completed

Pipe laying and interconnection work completed. Providing water connection and re concrete to be completed.

Oachira AE
Date: 02/05/2025

Work in progress | 75% Completed

Pipe laying and interconnection work completed. Providing water connection and re concrete to be completed.

Oachira AE
Date: 29/04/2025

Work in progress | 75% Completed

Pipe laying and interconnection work completed. Providing water connection and re concrete to be completed.

Oachira AE
Date: 24/04/2025

Work in progress | 75% Completed

Pipe laying of 63 mm PVC 6 kg/cm2 and interconnection work completed

Oachira AE
Date: 22/04/2025

Work in progress | 50% Completed

Work started on 21-04-2025

Oachira AE
Date: 15/04/2025

Work in progress | 0% Completed

Agreement executed on 06/03/2023, Site hand over on 19/03/2023

Oachira AE
Date: 10/04/2025

Work in progress | 0% Completed

Agreement executed on 06/03/2023, Site hand over on 19/03/2023

Oachira AE
Date: 05/04/2025

Work in progress | 0% Completed

Agreement executed on 06/03/2023, Site hand over on 19/03/2023

Oachira AE
Date: 01/04/2025

Work in progress | 0% Completed

Agreement executed on 06/03/2023, Site hand over on 19/03/2023

Oachira AE
Date: 29/03/2025

Work has started | 0% Completed

Agreement executed on 06/03/2023, Site hand over on 19/03/2023