| Oachira AE |
| Date: 19/05/2025 |
| Oachira AE |
| Date: 16/05/2025 |
Work in progress | 75% Completed
Pipe laying and interconnection work completed. Providing water connection and re concrete to be completed.
| Oachira AE |
| Date: 12/05/2025 |
Work in progress | 75% Completed
Pipe laying and interconnection work completed. Providing water connection and re concrete to be completed.
| Oachira AE |
| Date: 08/05/2025 |
Work in progress | 75% Completed
Pipe laying and interconnection work completed. Providing water connection and re concrete to be completed.
| Oachira AE |
| Date: 05/05/2025 |
Work in progress | 75% Completed
Pipe laying and interconnection work completed. Providing water connection and re concrete to be completed.
| Oachira AE |
| Date: 02/05/2025 |
Work in progress | 75% Completed
Pipe laying and interconnection work completed. Providing water connection and re concrete to be completed.
| Oachira AE |
| Date: 29/04/2025 |
Work in progress | 75% Completed
Pipe laying and interconnection work completed. Providing water connection and re concrete to be completed.
| Oachira AE |
| Date: 24/04/2025 |
Work in progress | 75% Completed
Pipe laying of 63 mm PVC 6 kg/cm2 and interconnection work completed
| Oachira AE |
| Date: 22/04/2025 |
Work in progress | 50% Completed
Work started on 21-04-2025
| Oachira AE |
| Date: 15/04/2025 |
Work in progress | 0% Completed
Agreement executed on 06/03/2023, Site hand over on 19/03/2023
| Oachira AE |
| Date: 10/04/2025 |
Work in progress | 0% Completed
Agreement executed on 06/03/2023, Site hand over on 19/03/2023
| Oachira AE |
| Date: 05/04/2025 |
Work in progress | 0% Completed
Agreement executed on 06/03/2023, Site hand over on 19/03/2023
| Oachira AE |
| Date: 01/04/2025 |
Work in progress | 0% Completed
Agreement executed on 06/03/2023, Site hand over on 19/03/2023
| Oachira AE |
| Date: 29/03/2025 |
Work has started | 0% Completed
Agreement executed on 06/03/2023, Site hand over on 19/03/2023