| Nedumkandam Sn AE |
| Date: 21/06/2025 |
Work has been completed | 100% Completed
Work completed
| Nedumkandam Sn AE |
| Date: 28/01/2025 |
Work in progress | 55% Completed
100mm GI Pumping Main Laying Works On Going
| Nedumkandam Sn AE |
| Date: 13/01/2025 |
Work in progress | 50% Completed
150mm GI pumping main laying works continues . (317 nos of 100mm GI laid)