Kollam WS Sn 3 - AE
Date: 20/09/2024

Work has been completed | 100% Completed

work completed

Kollam WS Sn 3 - AE
Date: 19/09/2024

Work in progress | 78% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 13/09/2024

Work in progress | 78% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 09/09/2024

Work in progress | 78% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 05/09/2024

Work in progress | 78% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 02/09/2024

Work in progress | 78% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 31/08/2024

Work in progress | 77% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 29/08/2024

Work in progress | 77% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 27/08/2024

Work in progress | 77% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 24/08/2024

Work in progress | 77% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 22/08/2024

Work in progress | 77% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 19/08/2024

Work in progress | 77% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 16/08/2024

Work in progress | 77% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 12/08/2024

Work in progress | 77% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 08/08/2024

Work in progress | 77% Completed

Disconnection of public tap work progress is slow

Kollam WS Sn 3 - AE
Date: 05/08/2024

Work in progress | 77% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 02/08/2024

Work in progress | 77% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 01/08/2024

Work in progress | 77% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 29/07/2024

Work in progress | 77% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 22/07/2024

Work in progress | 77% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 18/07/2024

Work in progress | 77% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 15/07/2024

Work in progress | 77% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 12/07/2024

Work in progress | 77% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 09/07/2024

Work in progress | 77% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 05/07/2024

Work in progress | 76% Completed

Disconnection of public tap work is very slow

Kollam WS Sn 3 - AE
Date: 01/07/2024

Work in progress | 76% Completed

Disconnection of public tap work is very slow

Kollam WS Sn 3 - AE
Date: 27/06/2024

Work in progress | 76% Completed

Disconnection of public tap work is very slow

Kollam WS Sn 3 - AE
Date: 24/06/2024

Work in progress | 76% Completed

Disconnection of public tap work is very slow

Kollam WS Sn 3 - AE
Date: 21/06/2024

Work in progress | 76% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 18/06/2024

Work in progress | 75% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 13/06/2024

Work in progress | 70% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 10/06/2024

Work in progress | 50% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 03/06/2024

Work in progress | 30% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 29/05/2024

Work in progress | 15% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 27/05/2024

Work in progress | 10% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 24/05/2024

Work in progress | 9% Completed

Disconnection of public tap work in progress

Kollam WS Sn 3 - AE
Date: 20/05/2024

Work in progress | 8% Completed

Work is very slow 8% Completed

Kollam WS Sn 3 - AE
Date: 17/05/2024

Work in progress | 8% Completed

Work is very slow 8% Completed

Kollam WS Sn 3 - AE
Date: 14/05/2024

Work in progress | 8% Completed

Work is very slow 8% Completed

Kollam WS Sn 3 - AE
Date: 10/05/2024

Work in progress | 8% Completed

Work is very slow 8% Completed

Kollam WS Sn 3 - AE
Date: 08/05/2024

Work in progress | 8% Completed

Work is very slow 8% Completed

Kollam WS Sn 3 - AE
Date: 06/05/2024

Work in progress | 8% Completed

Work is very slow 8% Completed

Kollam WS Sn 3 - AE
Date: 02/05/2024

Work in progress | 8% Completed

Work is very slow 8% Completed

Kollam WS Sn 3 - AE
Date: 29/04/2024

Work in progress | 8% Completed

Work is very slow 8% Completed

Kollam WS Sn 3 - AE
Date: 27/04/2024

Work in progress | 8% Completed

Work is very slow 8% Completed

Kollam WS Sn 3 - AE
Date: 22/04/2024

Work in progress | 8% Completed

Work is very slow 8% Completed

Kollam WS Sn 3 - AE
Date: 18/04/2024

Work in progress | 8% Completed

Work is very slow 8% Completed

Kollam WS Sn 3 - AE
Date: 15/04/2024

Work in progress | 8% Completed

Work is very slow 8% Completed

Kollam WS Sn 3 - AE
Date: 11/04/2024

Work in progress | 8% Completed

Work is very slow 8% Completed

Kollam WS Sn 3 - AE
Date: 08/04/2024

Work in progress | 8% Completed

Work is very slow 8% Completed

Kollam WS Sn 3 - AE
Date: 06/04/2024

Work in progress | 8% Completed

Work is very slow 8% Completed

Kollam WS Sn 3 - AE
Date: 02/04/2024

Work in progress | 8% Completed

Work is very slow 8% Completed

Kollam WS Sn 3 - AE
Date: 30/03/2024

Work in progress | 8% Completed

Work is very slow 8% Completed

Kollam WS Sn 3 - AE
Date: 26/03/2024

Work in progress | 8% Completed

Work is very slow 8% Completed

Kollam WS Sn 3 - AE
Date: 23/03/2024

Work in progress | 8% Completed

Work in progress

Kollam WS Sn 3 - AE
Date: 20/03/2024

Work in progress | 7% Completed

Work in progress

Kollam WS Sn 3 - AE
Date: 18/03/2024

Work in progress | 7% Completed

Work in progress

Kollam WS Sn 3 - AE
Date: 16/03/2024

Work in progress | 7% Completed

Work in progress

Kollam WS Sn 3 - AE
Date: 13/03/2024

Work in progress | 6% Completed

Work in progress

Kollam WS Sn 3 - AE
Date: 11/03/2024

Work in progress | 5% Completed

Work in progress

Kollam WS Sn 3 - AE
Date: 07/03/2024

Work in progress | 4% Completed

Work in progress

Kollam WS Sn 3 - AE
Date: 04/03/2024

Work in progress | 4% Completed

Work in progress

Kollam WS Sn 3 - AE
Date: 29/02/2024

Work in progress | 3% Completed

3% completed

Kollam WS Sn 3 - AE
Date: 26/02/2024

Work in progress | 2% Completed

2% Completed

Kollam WS Sn 3 - AE
Date: 23/02/2024

Work in progress | 1% Completed

site handed over

Kollam WS Sn 3 - AE
Date: 20/02/2024

Work in progress | 1% Completed

site handed over

Kollam WS Sub Dn - AEE
Date: 15/02/2024

Work in progress | 1% Completed

Agreement executed on 12.01.2024 and SITE HANDED OVER