| Thiruvananthapuram - Med col - AE |
| Date: 21/10/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 18/10/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 16/10/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 13/10/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 11/10/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 08/10/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 01/10/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 28/09/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 24/09/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 22/09/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 20/09/2021 |
Work has been completed | 100% Completed
Work has been completed
| Thiruvananthapuram - Med col - AE |
| Date: 17/09/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 15/09/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 13/09/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 09/09/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 07/09/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 04/09/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 02/09/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 31/08/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 27/08/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 26/08/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 22/08/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 18/08/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 16/08/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 14/08/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 13/08/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 11/08/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 09/08/2021 |
Work has been completed | 100% Completed
Work completed
| Thiruvananthapuram - Med col - AE |
| Date: 05/08/2021 |
Work has been completed | 100% Completed
Work Completed
| Thiruvananthapuram - Med col - AE |
| Date: 02/08/2021 |
Work in progress | 99% Completed
cover slab casting going on
| Thiruvananthapuram - Med col - AE |
| Date: 29/07/2021 |
Work in progress | 98% Completed
cover slab casting going on
| Thiruvananthapuram - Med col - AE |
| Date: 26/07/2021 |
Work in progress | 98% Completed
cover slab casting going on
| Thiruvananthapuram - Med col - AE |
| Date: 23/07/2021 |
Work in progress | 97% Completed
cover slab casting going on
| Thiruvananthapuram - Med col - AE |
| Date: 20/07/2021 |
Work in progress | 92% Completed
Restoration completed
| Pattoor Sewerage Dn |
| Date: 16/07/2021 |
Work in progress | 84% Completed
Restoration going on
| Pattoor Sewerage Dn |
| Date: 14/07/2021 |
Work in progress | 82% Completed
Restoration work going on.
| Pattoor Sewerage Dn |
| Date: 12/07/2021 |
Work in progress | 81% Completed
Fifteen Manhole Constructed. 250 mm SW pipe-233 m, 200 mm SW pipe-24.15 m , 110 mm PVC Pipe-20 m has been laid. Junction pit-3 Nos, Silt pit- 4 nos were constructed.Removed Interlock tiles replaced.
| Pattoor Sewerage Dn |
| Date: 09/07/2021 |
Work in progress | 81% Completed
Fifteen Manhole Constructed. 250 mm SW pipe-233 m, 200 mm SW pipe-24.15 m , 110 mm PVC Pipe-20 m has been laid. Junction pit-3 Nos, Silt pit- 4 nos were constructed.Removed Interlock tiles replaced.
| Pattoor Sewerage Dn |
| Date: 05/07/2021 |
Work in progress | 79% Completed
Fifteen Manhole Constructed. 250 mm SW pipe-208 m, 200 mm SW pipe-24.15 m , 110 mm PVC Pipe-20 m has been laid. Junction pit-3 Nos, Silt pit- 4 nos were constructed.
| Pattoor Sewerage Dn |
| Date: 02/07/2021 |
Work in progress | 77% Completed
Thirteen Manhole Constructed. 250 mm SW pipe-163 m, 200 mm SW pipe-24.15 m , 110 mm PVC Pipe-20 m has been laid. Junction pit-3 Nos, Sit pit- 4 nos were also constructed.
| Pattoor Sewerage Dn |
| Date: 30/06/2021 |
Work in progress | 75% Completed
Thirteen Manhole Constructed. 250 mm SW pipe-143.10 m, 200 mm SW pipe-24.15 m , 110 mm PVC Pipe-20 m has been laid. Junction pit-3 Nos, Sit pit- 4 nos were also constructed.
| Pattoor Sewerage Dn |
| Date: 25/06/2021 |
Work in progress | 67% Completed
Thirteen Manhole Constructed. 250 mm SW pipe-143.10 m, 200 mm SW pipe-24.15 m , 110 mm PVC Pipe-20 m has been laid. Junction pit-3 Nos, Sit pit- 4 nos were also constructed.
| Pattoor Sewerage Dn |
| Date: 21/06/2021 |
Work in progress | 65% Completed
Thirteen Manhole Constructed. 165 meter Sewer Line Pipe laid.
| Pattoor Sewerage Dn |
| Date: 17/06/2021 |
Work in progress | 61% Completed
Nine Manhole Constructed. 140 meter Sewer Line Pipe laid.
| Pattoor Sewerage Dn |
| Date: 14/06/2021 |
Work in progress | 61% Completed
Nine Manhole Constructed. 140 meter Sewer Line Pipe laid.
| Pattoor Sewerage Dn |
| Date: 10/06/2021 |
Work in progress | 61% Completed
Nine Manhole Constructed. 140 meter Sewer Line Pipe laid
| Pattoor Sewerage Dn |
| Date: 06/06/2021 |
Work in progress | 58% Completed
Seven Manhole Constructed. 100 meter Sewer Line Pipe laid
| Pattoor Sewerage Dn |
| Date: 02/06/2021 |
Work in progress | 55% Completed
Work Restarted after Lockdown. Seven Manhole Constructed. 100 meter Sewer Line Pipe laid
| Pattoor Sewerage Dn |
| Date: 31/05/2021 |
Work in progress | 47% Completed
Work stopped due to Unavailability of Materials/ Workmen due to lockdown
| Pattoor Sewerage Dn |
| Date: 28/05/2021 |
Work in progress | 47% Completed
Work stopped due to lock down/unavailability of materials
| Pattoor Sewerage Dn |
| Date: 24/05/2021 |
Work in progress | 47% Completed
Work stopped due to lock down/unavailability of materials
| Pattoor Sewerage Dn |
| Date: 20/05/2021 |
Work in progress | 47% Completed
Work stopped due to Triple lock down.
| Pattoor Sewerage Dn |
| Date: 04/05/2021 |
Work in progress | 45% Completed
Work in Progress. Seven Manhole Constructed. 85 meter Sewer Line Pipe Laying Excavation Competed
| Pattoor Sewerage Dn |
| Date: 30/04/2021 |
Work in progress | 40% Completed
Work in Progress. Seven Manhole Constructed. 75 meter Sewer Line Pipe Laying Excavation Competed
| Pattoor Sewerage Dn |
| Date: 26/04/2021 |
Work in progress | 35% Completed
Work in Progress. Six Manhole Constructed. 65 meter Sewer Line Pipe Laying Excavation Competed
| Pattoor Sewerage Dn |
| Date: 21/04/2021 |
Work in progress | 30% Completed
Work in Progress. Four Manhole Constructed. 40 meter Sewer Line Pipe Laying Excavation Competed.
| Pattoor Sewerage Dn |
| Date: 16/04/2021 |
Work in progress | 21% Completed
Work in Progress. Four Manhole Constructed. 35 meter Sewer Line Pipe Laying Excavation Competed.
| Pattoor Sewerage Dn |
| Date: 12/04/2021 |
Work in progress | 19% Completed
Work in Progress. Three Manhole Constructed. 35 meter Sewer Line Pipe Laying Excavation Competed. Fourth manhole construction in progress.
| Pattoor Sewerage Dn |
| Date: 07/04/2021 |
Work in progress | 17% Completed
Work in Progress. Three Manhole Constructed. 30 meter Sewer Line Pipe Laying Excavation Competed
| Pattoor Sewerage Dn |
| Date: 31/03/2021 |
Work in progress | 15% Completed
Work in Progress. Three Manhole Constructed. 20 meter Sewer Line Pipe Laying Excavation Competed
| Pattoor Sewerage Dn |
| Date: 27/03/2021 |
Work in progress | 11% Completed
Work in Progress.. Two Manhole Constructed. Pipi Laying Excavation work in progress
| Pattoor Sewerage Dn |
| Date: 23/03/2021 |
Work in progress | 10% Completed
Work in Progress.. Two Manhole Constructed. Pipi Laying Excavation work in progress
| Pattoor Sewerage Dn |
| Date: 16/03/2021 |
Work in progress | 7% Completed
Work in Progress.. Two Manhole Constructed
| Pattoor Sewerage Dn |
| Date: 05/03/2021 |
Work in progress | 3% Completed
Work in Progress
| Pattoor Sewerage Dn |
| Date: 17/02/2021 |
Work in progress | 2% Completed
Work Started on 17.02.2021
| Pattoor Sewerage Dn |
| Date: 16/02/2021 |
Work has started | 0% Completed
WO issued
| Pattoor Sewerage Dn |
| Date: 09/02/2021 |
Work has started | 0% Completed
WO issued
| Pattoor Sewerage Dn |
| Date: 03/02/2021 |
Work in progress | 0% Completed
Tender opened on 02/02/2021
| Pattoor Sewerage Dn |
| Date: 27/01/2021 |
Work has started | 0% Completed
tendered