Thiruvananthapuram - Med col - AE
Date: 21/10/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 18/10/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 16/10/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 13/10/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 11/10/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 08/10/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 01/10/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 28/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 24/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 22/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 20/09/2021

Work has been completed | 100% Completed

Work has been completed

Thiruvananthapuram - Med col - AE
Date: 17/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 15/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 13/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 09/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 07/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 04/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 02/09/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 31/08/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 27/08/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 26/08/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 22/08/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 18/08/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 16/08/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 14/08/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 13/08/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 11/08/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 09/08/2021

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 05/08/2021

Work has been completed | 100% Completed

Work Completed

Thiruvananthapuram - Med col - AE
Date: 02/08/2021

Work in progress | 99% Completed

cover slab casting going on

Thiruvananthapuram - Med col - AE
Date: 29/07/2021

Work in progress | 98% Completed

cover slab casting going on

Thiruvananthapuram - Med col - AE
Date: 26/07/2021

Work in progress | 98% Completed

cover slab casting going on

Thiruvananthapuram - Med col - AE
Date: 23/07/2021

Work in progress | 97% Completed

cover slab casting going on

Thiruvananthapuram - Med col - AE
Date: 20/07/2021

Work in progress | 92% Completed

Restoration completed

Pattoor Sewerage Dn
Date: 16/07/2021

Work in progress | 84% Completed

Restoration going on

Pattoor Sewerage Dn
Date: 14/07/2021

Work in progress | 82% Completed

Restoration work going on.

Pattoor Sewerage Dn
Date: 12/07/2021

Work in progress | 81% Completed

Fifteen Manhole Constructed. 250 mm SW pipe-233 m, 200 mm SW pipe-24.15 m , 110 mm PVC Pipe-20 m has been laid. Junction pit-3 Nos, Silt pit- 4 nos were constructed.Removed Interlock tiles replaced.

Pattoor Sewerage Dn
Date: 09/07/2021

Work in progress | 81% Completed

Fifteen Manhole Constructed. 250 mm SW pipe-233 m, 200 mm SW pipe-24.15 m , 110 mm PVC Pipe-20 m has been laid. Junction pit-3 Nos, Silt pit- 4 nos were constructed.Removed Interlock tiles replaced.

Pattoor Sewerage Dn
Date: 05/07/2021

Work in progress | 79% Completed

Fifteen Manhole Constructed. 250 mm SW pipe-208 m, 200 mm SW pipe-24.15 m , 110 mm PVC Pipe-20 m has been laid. Junction pit-3 Nos, Silt pit- 4 nos were constructed.

Pattoor Sewerage Dn
Date: 02/07/2021

Work in progress | 77% Completed

Thirteen Manhole Constructed. 250 mm SW pipe-163 m, 200 mm SW pipe-24.15 m , 110 mm PVC Pipe-20 m has been laid. Junction pit-3 Nos, Sit pit- 4 nos were also constructed.

Pattoor Sewerage Dn
Date: 30/06/2021

Work in progress | 75% Completed

Thirteen Manhole Constructed. 250 mm SW pipe-143.10 m, 200 mm SW pipe-24.15 m , 110 mm PVC Pipe-20 m has been laid. Junction pit-3 Nos, Sit pit- 4 nos were also constructed.

Pattoor Sewerage Dn
Date: 25/06/2021

Work in progress | 67% Completed

Thirteen Manhole Constructed. 250 mm SW pipe-143.10 m, 200 mm SW pipe-24.15 m , 110 mm PVC Pipe-20 m has been laid. Junction pit-3 Nos, Sit pit- 4 nos were also constructed.

Pattoor Sewerage Dn
Date: 21/06/2021

Work in progress | 65% Completed

Thirteen Manhole Constructed. 165 meter Sewer Line Pipe laid.

Pattoor Sewerage Dn
Date: 17/06/2021

Work in progress | 61% Completed

Nine Manhole Constructed. 140 meter Sewer Line Pipe laid.

Pattoor Sewerage Dn
Date: 14/06/2021

Work in progress | 61% Completed

Nine Manhole Constructed. 140 meter Sewer Line Pipe laid.

Pattoor Sewerage Dn
Date: 10/06/2021

Work in progress | 61% Completed

Nine Manhole Constructed. 140 meter Sewer Line Pipe laid

Pattoor Sewerage Dn
Date: 06/06/2021

Work in progress | 58% Completed

Seven Manhole Constructed. 100 meter Sewer Line Pipe laid

Pattoor Sewerage Dn
Date: 02/06/2021

Work in progress | 55% Completed

Work Restarted after Lockdown. Seven Manhole Constructed. 100 meter Sewer Line Pipe laid

Pattoor Sewerage Dn
Date: 31/05/2021

Work in progress | 47% Completed

Work stopped due to Unavailability of Materials/ Workmen due to lockdown

Pattoor Sewerage Dn
Date: 28/05/2021

Work in progress | 47% Completed

Work stopped due to lock down/unavailability of materials

Pattoor Sewerage Dn
Date: 24/05/2021

Work in progress | 47% Completed

Work stopped due to lock down/unavailability of materials

Pattoor Sewerage Dn
Date: 20/05/2021

Work in progress | 47% Completed

Work stopped due to Triple lock down.

Pattoor Sewerage Dn
Date: 04/05/2021

Work in progress | 45% Completed

Work in Progress. Seven Manhole Constructed. 85 meter Sewer Line Pipe Laying Excavation Competed

Pattoor Sewerage Dn
Date: 30/04/2021

Work in progress | 40% Completed

Work in Progress. Seven Manhole Constructed. 75 meter Sewer Line Pipe Laying Excavation Competed

Pattoor Sewerage Dn
Date: 26/04/2021

Work in progress | 35% Completed

Work in Progress. Six Manhole Constructed. 65 meter Sewer Line Pipe Laying Excavation Competed

Pattoor Sewerage Dn
Date: 21/04/2021

Work in progress | 30% Completed

Work in Progress. Four Manhole Constructed. 40 meter Sewer Line Pipe Laying Excavation Competed.

Pattoor Sewerage Dn
Date: 16/04/2021

Work in progress | 21% Completed

Work in Progress. Four Manhole Constructed. 35 meter Sewer Line Pipe Laying Excavation Competed.

Pattoor Sewerage Dn
Date: 12/04/2021

Work in progress | 19% Completed

Work in Progress. Three Manhole Constructed. 35 meter Sewer Line Pipe Laying Excavation Competed. Fourth manhole construction in progress.

Pattoor Sewerage Dn
Date: 07/04/2021

Work in progress | 17% Completed

Work in Progress. Three Manhole Constructed. 30 meter Sewer Line Pipe Laying Excavation Competed

Pattoor Sewerage Dn
Date: 31/03/2021

Work in progress | 15% Completed

Work in Progress. Three Manhole Constructed. 20 meter Sewer Line Pipe Laying Excavation Competed

Pattoor Sewerage Dn
Date: 27/03/2021

Work in progress | 11% Completed

Work in Progress.. Two Manhole Constructed. Pipi Laying Excavation work in progress

Pattoor Sewerage Dn
Date: 23/03/2021

Work in progress | 10% Completed

Work in Progress.. Two Manhole Constructed. Pipi Laying Excavation work in progress

Pattoor Sewerage Dn
Date: 16/03/2021

Work in progress | 7% Completed

Work in Progress.. Two Manhole Constructed

Pattoor Sewerage Dn
Date: 05/03/2021

Work in progress | 3% Completed

Work in Progress

Pattoor Sewerage Dn
Date: 17/02/2021

Work in progress | 2% Completed

Work Started on 17.02.2021

Pattoor Sewerage Dn
Date: 16/02/2021

Work has started | 0% Completed

WO issued

Pattoor Sewerage Dn
Date: 09/02/2021

Work has started | 0% Completed

WO issued

Pattoor Sewerage Dn
Date: 03/02/2021

Work in progress | 0% Completed

Tender opened on 02/02/2021

Pattoor Sewerage Dn
Date: 27/01/2021

Work has started | 0% Completed

tendered