| Kozhikode Dist 1 Sn 2 - AE |
| Date: 16/01/2025 |
Work has been completed | 100% Completed
Completed
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 07/12/2024 |
Work in progress | 96% Completed
Laying and temporary restoration completed. FHTC'S and one more interconnection pending
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 19/11/2024 |
Work in progress | 95% Completed
Laying and temporary restoration completed. FHTC'S and one more interconnection pending.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 06/11/2024 |
Work in progress | 95% Completed
Laying and temporary restoration completed. FHTC'S and one more interconnection pending.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 23/10/2024 |
Work in progress | 95% Completed
Laying and temporary restoration completed. FHTC'S and one more interconnection pending.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 21/08/2024 |
Work in progress | 90% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 21/04/2024 |
Work in progress | 23% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 21% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 18% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 15% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 13% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 12/01/2024 |
Work in progress | 9% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work in progress | 8% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 29/11/2023 |
Work in progress | 5% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 31/10/2023 |
Work in progress | 2% Completed
Pipe Supplied