| Kollam WS Sn 2 - AE |
| Date: 12/06/2023 |
Work has been completed | 100% Completed
work completed
| Kollam WS Sn 2 - AE |
| Date: 09/06/2023 |
Work in progress | 99% Completed
Pipe laying work completed on 7/6/23, restoration of concrete work to be done
| Kollam WS Sn 2 - AE |
| Date: 05/06/2023 |
Work in progress | 2% Completed
Work started and in progress
| Kollam WS Sn 2 - AE |
| Date: 01/06/2023 |
Work in progress | 0% Completed
Tested pipe not received
| Kollam WS Sn 2 - AE |
| Date: 29/05/2023 |
Work in progress | 0% Completed
Tested pipe not received
| Kollam WS Sn 2 - AE |
| Date: 24/05/2023 |
Work has started | 0% Completed
Tested pipe not received
| Kollam WS Sn 2 - AE |
| Date: 22/05/2023 |
Work has started | 0% Completed
Tested pipe not received
| Kollam WS Sn 2 - AE |
| Date: 19/05/2023 |
Work has started | 0% Completed
Waiting for tested pipe
| Kollam WS Sn 2 - AE |
| Date: 15/05/2023 |
Work has started | 0% Completed
Waiting for tested pipe
| Kollam WS Sn 2 - AE |
| Date: 11/05/2023 |
Work has started | 0% Completed
LoA prepared and send to the contractor, Site inspection conducted
| Kollam WS Sn 2 - AE |
| Date: 08/05/2023 |
Work has started | 0% Completed
LoA prepared and send to the contractor