Kozhikode Project Dn AE5 |
Date: 23/11/2021 |
Work has been completed | 100% Completed
Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges.
Kozhikode Project Dn AE5 |
Date: 27/10/2021 |
Work has been completed | 100% Completed
Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges.
Kozhikode Project Dn AE5 |
Date: 15/08/2021 |
Work has been completed | 100% Completed
work completed
Kozhikode Project Dn AE5 |
Date: 08/08/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project Dn AE5 |
Date: 02/08/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project Dn AE5 |
Date: 26/07/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project Dn AE5 |
Date: 23/07/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project Dn AE5 |
Date: 22/07/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project Dn AE5 |
Date: 19/07/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project AEE 2 |
Date: 16/07/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project AEE 2 |
Date: 11/07/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project AEE 2 |
Date: 07/07/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project AEE 2 |
Date: 05/07/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project AEE 2 |
Date: 27/06/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project AEE 2 |
Date: 25/06/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project AEE 2 |
Date: 24/06/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project AEE 2 |
Date: 21/06/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project AEE 2 |
Date: 18/06/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project AEE 2 |
Date: 13/06/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project AEE 2 |
Date: 11/06/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project AEE 2 |
Date: 03/06/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project AEE 2 |
Date: 02/06/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project AEE 2 |
Date: 01/06/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project AEE 2 |
Date: 31/05/2021 |
Work has been completed | 100% Completed
final bill submitted
Kozhikode Project AEE 2 |
Date: 23/05/2021 |
Work has been completed | 100% Completed
final bill submitted
Kozhikode Project AEE 2 |
Date: 22/05/2021 |
Work has been completed | 100% Completed
final bill submitted
Kozhikode Project AEE 2 |
Date: 16/05/2021 |
Work has been completed | 100% Completed
final bill submitted
Kozhikode Project AEE 2 |
Date: 14/05/2021 |
Work has been completed | 100% Completed
final bill submitted
Kozhikode Project AEE 2 |
Date: 13/05/2021 |
Work has been completed | 100% Completed
final bill submitted
Kozhikode Project AEE 2 |
Date: 11/05/2021 |
Work in progress | 98% Completed
Trial run in progress
Kozhikode Project AEE 2 |
Date: 09/05/2021 |
Work in progress | 98% Completed
Trial run in progress
Kozhikode Project AEE 2 |
Date: 08/05/2021 |
Work in progress | 98% Completed
Trial run in progress
Kozhikode Project AEE 2 |
Date: 05/05/2021 |
Work in progress | 98% Completed
Trial run in progress
Kozhikode Project AEE 2 |
Date: 03/05/2021 |
Work in progress | 98% Completed
Trial run in progress
Kozhikode Project AEE 2 |
Date: 02/05/2021 |
Work in progress | 98% Completed
Trial run in progress
Kozhikode Project AEE 2 |
Date: 01/05/2021 |
Work in progress | 98% Completed
Trial run in progress
Kozhikode Project AEE 2 |
Date: 30/04/2021 |
Work in progress | 98% Completed
Trial run in progress
Kozhikode Project AEE 2 |
Date: 28/04/2021 |
Work in progress | 98% Completed
Trial run in progress
Kozhikode Project AEE 2 |
Date: 26/04/2021 |
Work in progress | 98% Completed
Trial run in progress
Kozhikode Project AEE 2 |
Date: 23/04/2021 |
Work in progress | 98% Completed
Trial run in progress
Kozhikode Project AEE 2 |
Date: 21/04/2021 |
Work in progress | 98% Completed
Trial run in progress
Kozhikode Project AEE 2 |
Date: 19/04/2021 |
Work in progress | 98% Completed
Trial run in progress
Kozhikode Project AEE 2 |
Date: 17/04/2021 |
Work in progress | 98% Completed
Trial run in progress
Kozhikode Project AEE 2 |
Date: 15/04/2021 |
Work in progress | 98% Completed
Trial run in progress
Kozhikode Project AEE 2 |
Date: 13/04/2021 |
Work in progress | 95% Completed
Pipe line work completed, Trial Run in Progress
Kozhikode Project AEE 2 |
Date: 12/04/2021 |
Work in progress | 95% Completed
Pipe line work completed, Trial Run in Progress
Kozhikode Project AEE 2 |
Date: 08/04/2021 |
Work in progress | 95% Completed
Pipe line work completed, Trial Run in Progress
Kozhikode Project AEE 2 |
Date: 07/04/2021 |
Work in progress | 95% Completed
Pipe line work completed, Trial Run in Progress
Kozhikode Project AEE 2 |
Date: 05/04/2021 |
Work in progress | 95% Completed
Pipe line work completed, Trial Run in Progress
Kozhikode Project AEE 2 |
Date: 03/04/2021 |
Work in progress | 95% Completed
Pipe line work completed, Trial Run in Progress
Kozhikode Project AEE 2 |
Date: 30/03/2021 |
Work in progress | 95% Completed
Pipe line work completed, Trial Run in Progress
Kozhikode Project AEE 2 |
Date: 29/03/2021 |
Work in progress | 95% Completed
Pipe line work completed, Trial Run in Progress
Kozhikode Project AEE 2 |
Date: 27/03/2021 |
Work in progress | 95% Completed
Pipe line work completed, Trial Run in Progress
Kozhikode Project AEE 2 |
Date: 24/03/2021 |
Work in progress | 95% Completed
Pipe line work completed, Trial Run in Progress
Kozhikode Project AEE 2 |
Date: 22/03/2021 |
Work in progress | 95% Completed
Pipe line work completed, Trial Run in Progress
Kozhikode Project AEE 2 |
Date: 19/03/2021 |
Work in progress | 95% Completed
Pipe line work completed, Trial Run in Progress
Kozhikode Project AEE 2 |
Date: 15/03/2021 |
Work in progress | 95% Completed
Pipe line work completed, Trial Run in Progress
Kozhikode Project AEE 2 |
Date: 08/03/2021 |
Work in progress | 94% Completed
Pipe line work in progress and nearing completion
Kozhikode Project AEE 2 |
Date: 02/03/2021 |
Work in progress | 93% Completed
Pipe line work in progress and nearing completion
Kozhikode Project AEE 2 |
Date: 22/02/2021 |
Work in progress | 93% Completed
Pipe line work in progress and nearing completion
Kozhikode Project AEE 2 |
Date: 12/02/2021 |
Work in progress | 92% Completed
Pipe line work in progress and nearing completion
Kozhikode Project AEE 2 |
Date: 05/02/2021 |
Kozhikode Project AEE 2 |
Date: 26/01/2021 |
Work in progress | 90% Completed
transmission main laying work started Iringath narakode PWD (Under DLP)
Kozhikode Project AEE 2 |
Date: 31/12/2020 |
Work in progress | 89% Completed
Out of 10335 m transmission main 6457 m pipes laid and construction of 7.5 LL OHSR completed. Due to delay in getting permission from PWD for road cutting on Iringath Narakode road, alternate proposal for laying HDPE pipe by HDD method was submitted to KIIFB , the same was returned by KIIFB with queries. meanwhile discussion made with PWD and online application submitted to PWD on 13.10 2020 and PWD intimated the reformation charge of Rs.10618497.00 and a DLP amount of Rs 41,75,025.00 on PWD 25.11.2020.KIIFB rejected the fund request and directed to meet the DLP amount for road from the centage charge of SPV. Fund request submitted to head office .
Kozhikode Project AEE 2 |
Date: 27/11/2020 |
Work in progress | 88% Completed
Out of 10335 m transmission main 6457 m pipes laid and construction of 7.5 LL OHSR completed. Due to delay in getting permission from PWD for road cutting on Iringath Narakode road, alternate proposal for laying HDPE pipe by HDD method was submitted to KIIFB , the same was returned by KIIFB with queries. meanwhile discussion made with PWD and online application submitted to PWD on 13.10 2020 and reformation charge of Rs.10618497.00 and a DLP amount of Rs 41,75,025.00 on square meter rate is intimated by PWD 25.11.2020. Requested PWD to provide detailed estimate for the road work for uploading in KIIFB portal.
Kozhikode Project AEE 2 |
Date: 10/11/2020 |
Work in progress | 87% Completed
87%completed
Kozhikode Project AEE 2 |
Date: 09/09/2020 |
Kozhikode Project AEE 2 |
Date: 18/08/2020 |
Work in progress | 85% Completed
All works in this packages were completed except the laying work in Narakkod- Iringath road due to PWD DLP for a length of 1700m. An extra item of laying HDPE pipe by HDD method is required as per actual site condition.The estimate with TS committee recommendation uploaded in KIIFB PFMS portal
Kozhikode Project AEE 2 |
Date: 01/07/2020 |
Work in progress | 83% Completed
On going