Kozhikode Project Dn AE5
Date: 23/11/2021

Work has been completed | 100% Completed

Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges.

Kozhikode Project Dn AE5
Date: 27/10/2021

Work has been completed | 100% Completed

Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges.

Kozhikode Project Dn AE5
Date: 15/08/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE5
Date: 08/08/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project Dn AE5
Date: 02/08/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project Dn AE5
Date: 26/07/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project Dn AE5
Date: 23/07/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project Dn AE5
Date: 22/07/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project Dn AE5
Date: 19/07/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project AEE 2
Date: 16/07/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project AEE 2
Date: 11/07/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project AEE 2
Date: 07/07/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project AEE 2
Date: 05/07/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project AEE 2
Date: 27/06/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project AEE 2
Date: 25/06/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project AEE 2
Date: 24/06/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project AEE 2
Date: 21/06/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project AEE 2
Date: 18/06/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project AEE 2
Date: 13/06/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project AEE 2
Date: 11/06/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project AEE 2
Date: 03/06/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project AEE 2
Date: 02/06/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project AEE 2
Date: 01/06/2021

Work has been completed | 100% Completed

work completed, Final bill submitted

Kozhikode Project AEE 2
Date: 31/05/2021

Work has been completed | 100% Completed

final bill submitted

Kozhikode Project AEE 2
Date: 23/05/2021

Work has been completed | 100% Completed

final bill submitted

Kozhikode Project AEE 2
Date: 22/05/2021

Work has been completed | 100% Completed

final bill submitted

Kozhikode Project AEE 2
Date: 16/05/2021

Work has been completed | 100% Completed

final bill submitted

Kozhikode Project AEE 2
Date: 14/05/2021

Work has been completed | 100% Completed

final bill submitted

Kozhikode Project AEE 2
Date: 13/05/2021

Work has been completed | 100% Completed

final bill submitted

Kozhikode Project AEE 2
Date: 11/05/2021

Work in progress | 98% Completed

Trial run in progress

Kozhikode Project AEE 2
Date: 09/05/2021

Work in progress | 98% Completed

Trial run in progress

Kozhikode Project AEE 2
Date: 08/05/2021

Work in progress | 98% Completed

Trial run in progress

Kozhikode Project AEE 2
Date: 05/05/2021

Work in progress | 98% Completed

Trial run in progress

Kozhikode Project AEE 2
Date: 03/05/2021

Work in progress | 98% Completed

Trial run in progress

Kozhikode Project AEE 2
Date: 02/05/2021

Work in progress | 98% Completed

Trial run in progress

Kozhikode Project AEE 2
Date: 01/05/2021

Work in progress | 98% Completed

Trial run in progress

Kozhikode Project AEE 2
Date: 30/04/2021

Work in progress | 98% Completed

Trial run in progress

Kozhikode Project AEE 2
Date: 28/04/2021

Work in progress | 98% Completed

Trial run in progress

Kozhikode Project AEE 2
Date: 26/04/2021

Work in progress | 98% Completed

Trial run in progress

Kozhikode Project AEE 2
Date: 23/04/2021

Work in progress | 98% Completed

Trial run in progress

Kozhikode Project AEE 2
Date: 21/04/2021

Work in progress | 98% Completed

Trial run in progress

Kozhikode Project AEE 2
Date: 19/04/2021

Work in progress | 98% Completed

Trial run in progress

Kozhikode Project AEE 2
Date: 17/04/2021

Work in progress | 98% Completed

Trial run in progress

Kozhikode Project AEE 2
Date: 15/04/2021

Work in progress | 98% Completed

Trial run in progress

Kozhikode Project AEE 2
Date: 13/04/2021

Work in progress | 95% Completed

Pipe line work completed, Trial Run in Progress

Kozhikode Project AEE 2
Date: 12/04/2021

Work in progress | 95% Completed

Pipe line work completed, Trial Run in Progress

Kozhikode Project AEE 2
Date: 08/04/2021

Work in progress | 95% Completed

Pipe line work completed, Trial Run in Progress

Kozhikode Project AEE 2
Date: 07/04/2021

Work in progress | 95% Completed

Pipe line work completed, Trial Run in Progress

Kozhikode Project AEE 2
Date: 05/04/2021

Work in progress | 95% Completed

Pipe line work completed, Trial Run in Progress

Kozhikode Project AEE 2
Date: 03/04/2021

Work in progress | 95% Completed

Pipe line work completed, Trial Run in Progress

Kozhikode Project AEE 2
Date: 30/03/2021

Work in progress | 95% Completed

Pipe line work completed, Trial Run in Progress

Kozhikode Project AEE 2
Date: 29/03/2021

Work in progress | 95% Completed

Pipe line work completed, Trial Run in Progress

Kozhikode Project AEE 2
Date: 27/03/2021

Work in progress | 95% Completed

Pipe line work completed, Trial Run in Progress

Kozhikode Project AEE 2
Date: 24/03/2021

Work in progress | 95% Completed

Pipe line work completed, Trial Run in Progress

Kozhikode Project AEE 2
Date: 22/03/2021

Work in progress | 95% Completed

Pipe line work completed, Trial Run in Progress

Kozhikode Project AEE 2
Date: 19/03/2021

Work in progress | 95% Completed

Pipe line work completed, Trial Run in Progress

Kozhikode Project AEE 2
Date: 15/03/2021

Work in progress | 95% Completed

Pipe line work completed, Trial Run in Progress

Kozhikode Project AEE 2
Date: 08/03/2021

Work in progress | 94% Completed

Pipe line work in progress and nearing completion

Kozhikode Project AEE 2
Date: 02/03/2021

Work in progress | 93% Completed

Pipe line work in progress and nearing completion

Kozhikode Project AEE 2
Date: 22/02/2021

Work in progress | 93% Completed

Pipe line work in progress and nearing completion

Kozhikode Project AEE 2
Date: 12/02/2021

Work in progress | 92% Completed

Pipe line work in progress and nearing completion

Kozhikode Project AEE 2
Date: 05/02/2021

Work in progress | 91% Completed

Pipe line work in progress and nearing completion

Attached images

img img

Kozhikode Project AEE 2
Date: 26/01/2021

Work in progress | 90% Completed

transmission main laying work started Iringath narakode PWD (Under DLP)

Kozhikode Project AEE 2
Date: 31/12/2020

Work in progress | 89% Completed

Out of 10335 m transmission main 6457 m pipes laid and construction of 7.5 LL OHSR completed. Due to delay in getting permission from PWD for road cutting on Iringath Narakode road, alternate proposal for laying HDPE pipe by HDD method was submitted to KIIFB , the same was returned by KIIFB with queries. meanwhile discussion made with PWD and online application submitted to PWD on 13.10 2020 and PWD intimated the reformation charge of Rs.10618497.00 and a DLP amount of Rs 41,75,025.00 on PWD 25.11.2020.KIIFB rejected the fund request and directed to meet the DLP amount for road from the centage charge of SPV. Fund request submitted to head office .

Kozhikode Project AEE 2
Date: 27/11/2020

Work in progress | 88% Completed

Out of 10335 m transmission main 6457 m pipes laid and construction of 7.5 LL OHSR completed. Due to delay in getting permission from PWD for road cutting on Iringath Narakode road, alternate proposal for laying HDPE pipe by HDD method was submitted to KIIFB , the same was returned by KIIFB with queries. meanwhile discussion made with PWD and online application submitted to PWD on 13.10 2020 and reformation charge of Rs.10618497.00 and a DLP amount of Rs 41,75,025.00 on square meter rate is intimated by PWD 25.11.2020. Requested PWD to provide detailed estimate for the road work for uploading in KIIFB portal.

Kozhikode Project AEE 2
Date: 10/11/2020

Work in progress | 87% Completed

87%completed

Kozhikode Project AEE 2
Date: 09/09/2020

Work in progress | 86% Completed

Work in progress

Attached images

img

Kozhikode Project AEE 2
Date: 18/08/2020

Work in progress | 85% Completed

All works in this packages were completed except the laying work in Narakkod- Iringath road due to PWD DLP for a length of 1700m. An extra item of laying HDPE pipe by HDD method is required as per actual site condition.The estimate with TS committee recommendation uploaded in KIIFB PFMS portal

Kozhikode Project AEE 2
Date: 01/07/2020

Work in progress | 83% Completed

On going