| Kollam WS Sn 2 - AE |
| Date: 12/06/2023 |
Work has been completed | 100% Completed
Work has been completed
| Kollam WS Sn 2 - AE |
| Date: 09/06/2023 |
Work has been completed | 100% Completed
Bill under preparation
| Kollam WS Sn 2 - AE |
| Date: 06/06/2023 |
Work has been completed | 100% Completed
Work started on 6/6/2023 and completed satisfactrily ( 80 m - 63 mm PVC )
| Kollam WS Sn 2 - AE |
| Date: 05/06/2023 |
Work in progress | 0% Completed
Site handed over and work will start tomorrow.
| Kollam WS Sn 2 - AE |
| Date: 01/06/2023 |
Work in progress | 0% Completed
Tested pipe not received
| Kollam WS Sn 2 - AE |
| Date: 24/05/2023 |
Work in progress | 0% Completed
Tested pipe not received
| Kollam WS Sn 2 - AE |
| Date: 22/05/2023 |
Work has started | 0% Completed
Tested pipe not received
| Kollam WS Sn 2 - AE |
| Date: 19/05/2023 |
Work has started | 0% Completed
Waiting for tested pipe
| Kollam WS Sn 2 - AE |
| Date: 15/05/2023 |
Work has started | 0% Completed
Waiting for tested pipe
| Kollam WS Sn 2 - AE |
| Date: 11/05/2023 |
Work has started | 0% Completed
LOA prepared and send to the contractor