Kollam WS Sn 2 - AE
Date: 12/06/2023

Work has been completed | 100% Completed

Work has been completed

Kollam WS Sn 2 - AE
Date: 09/06/2023

Work has been completed | 100% Completed

Bill under preparation

Kollam WS Sn 2 - AE
Date: 06/06/2023

Work has been completed | 100% Completed

Work started on 6/6/2023 and completed satisfactrily ( 80 m - 63 mm PVC )

Kollam WS Sn 2 - AE
Date: 05/06/2023

Work in progress | 0% Completed

Site handed over and work will start tomorrow.

Kollam WS Sn 2 - AE
Date: 01/06/2023

Work in progress | 0% Completed

Tested pipe not received

Kollam WS Sn 2 - AE
Date: 24/05/2023

Work in progress | 0% Completed

Tested pipe not received

Kollam WS Sn 2 - AE
Date: 22/05/2023

Work has started | 0% Completed

Tested pipe not received

Kollam WS Sn 2 - AE
Date: 19/05/2023

Work has started | 0% Completed

Waiting for tested pipe

Kollam WS Sn 2 - AE
Date: 15/05/2023

Work has started | 0% Completed

Waiting for tested pipe

Kollam WS Sn 2 - AE
Date: 11/05/2023

Work has started | 0% Completed

LOA prepared and send to the contractor