| Kattappana Project Dn EE |
| Date: 01/06/2021 |
Work in progress | 70% Completed
The various components - Intake structure ,Treatment plant, RWPM ,CWPM's and Pump sets ,Service Reservoirs ,Distribution networks for Zones 1,2,3,4,5,8,9, etc are completed under ARP-NRDWP. The balance works such as RW Pump set, Transformer at RW Pump house ,Power Connection works ,Charging of Pumping mains and Dist. networks & FHTC's etc are ongoing under state plan and JJM .
| Kattappana Project Dn EE |
| Date: 25/05/2021 |
Work in progress | 70% Completed
The various components - Intake structure ,Treatment plant, RWPM ,CWPM's and Pump sets ,Service Reservoirs ,Distribution networks for Zones 1,2,3,4,5,8,9, etc are completed under ARP-NRDWP. The balance works such as RW Pump set, Transformer at RW Pump house ,Power Connection works ,Charging of Pumping mains and Dist. networks & FHTC's etc are ongoing under state plan and JJM .
| Kattappana Project Dn EE |
| Date: 14/05/2021 |
Work in progress | 70% Completed
The various components - Intake structure ,Treatment plant, RWPM ,CWPM's and Pump sets ,Service Reservoirs ,Distribution networks for Zones 1,2,3,4,5,8,9, etc are completed under ARP-NRDWP. The balance works such as RW Pump set, Transformer at RW Pump house ,Power Connection works ,Charging of Pumping mains and Dist. networks & FHTC's etc are ongoing under state plan and JJM .
| Kattappana Project Dn EE |
| Date: 26/04/2021 |
Work in progress | 70% Completed
The Raw water motor supplied. Power connection works are in progress
| Kattappana Project Dn EE |
| Date: 10/02/2021 |
Work in progress | 65% Completed
Power Line Extension - amount required is remitted in KSEB
| Kattappana Project Dn EE |
| Date: 09/02/2021 |
Work in progress | 65% Completed
Factory Inspection Completed for Transformer at RWPH
| Kattappana Project Dn EE |
| Date: 03/02/2021 |
Work in progress | 65% Completed
Factory Inspection Completed for Transformer at RWPH
| Kattappana Project Dn EE |
| Date: 21/11/2020 |
Work in progress | 60% Completed
Supply and erection of Raw Water And Clear Water Transformers and electrification ongoing