| Keezhallur PH Sn AE |
| Date: 20/07/2026 |
Work in progress | 95% Completed
Revised Estimate submitted
| Keezhallur PH Sn AE |
| Date: 13/07/2026 |
Work in progress | 92% Completed
COP submitted
| Keezhallur PH Sn AE |
| Date: 06/07/2026 |
Work in progress | 91% Completed
Demand notice issued - COP submitted
| Keezhallur PH Sn AE |
| Date: 26/06/2026 |
Work in progress | 90% Completed
Road restoration work pending
| Keezhallur PH Sn AE |
| Date: 17/06/2026 |
Work in progress | 90% Completed
Road restoration work pending
| Keezhallur PH Sn AE |
| Date: 11/06/2026 |
Work in progress | 90% Completed
Pipe line laying work completed,Part bill submitted, road restoration work pending
| Keezhallur PH Sn AE |
| Date: 02/06/2026 |
Work in progress | 90% Completed
Pipe line laying work completed,Part bill submitted, road restoration work pending
| Keezhallur PH Sn AE |
| Date: 22/05/2026 |
Work in progress | 90% Completed
Pipe line laying work completed,Part bill submitted.
| Keezhallur PH Sn AE |
| Date: 12/05/2026 |
Work in progress | 90% Completed
Pipe line laying work completed,Part bill submitted.
| Keezhallur PH Sn AE |
| Date: 02/05/2026 |
Work in progress | 90% Completed
Part bill submitted
| Keezhallur PH Sn AE |
| Date: 25/04/2026 |
Work in progress | 90% Completed
Part bill submitted
| Keezhallur PH Sn AE |
| Date: 17/04/2026 |
Work in progress | 90% Completed
Revised estimate and Part bill submitted
| Keezhallur PH Sn AE |
| Date: 08/04/2026 |
Work in progress | 90% Completed
Revised estimate and Part bill submitted
| Keezhallur PH Sn AE |
| Date: 30/03/2026 |
Work in progress | 90% Completed
Revised estimate and Part bill submitted
| Keezhallur PH Sn AE |
| Date: 26/03/2026 |
Work in progress | 90% Completed
Revised estimate and Part bill submitted
| Keezhallur PH Sn AE |
| Date: 16/03/2026 |
Work in progress | 90% Completed
Pipe laying work completed.
| Keezhallur PH Sn AE |
| Date: 06/03/2026 |
Work in progress | 90% Completed
Pipe line laying work completed, Revised Estimate under Preperation
| Keezhallur PH Sn AE |
| Date: 27/02/2026 |
Work in progress | 90% Completed
Pipe laying completed
| Keezhallur PH Sn AE |
| Date: 18/02/2026 |
Work in progress | 90% Completed
PIPE LAYING WORK COMPLETED
| Keezhallur PH Sn AE |
| Date: 09/02/2026 |
Work in progress | 90% Completed
pipe laying completed
| Keezhallur PH Sn AE |
| Date: 28/01/2026 |
Work in progress | 90% Completed
pipe line laying completed
| Keezhallur PH Sn AE |
| Date: 19/01/2026 |
Work in progress | 85% Completed
ROAD CROSSING WORKS COMPLETED
| Keezhallur PH Sn AE |
| Date: 12/01/2026 |
Work in progress | 82% Completed
GI FABRICATING WORK PROGRESSING
| Keezhallur PH Sn AE |
| Date: 05/01/2026 |
Work in progress | 82% Completed
Pipe line laying work progressing
| Keezhallur PH Sn AE |
| Date: 29/12/2025 |
Work in progress | 82% Completed
5 Km of pipeline laid
| Keezhallur PH Sn AE |
| Date: 22/12/2025 |
Work in progress | 79% Completed
Work Restarted
| Keezhallur PH Sn AE |
| Date: 12/12/2025 |
Work in progress | 79% Completed
The work was temporarily stopped, due to election
| Keezhallur PH Sn AE |
| Date: 05/12/2025 |
Work in progress | 79% Completed
The work was temporarily stopped, due to election declaration
| Keezhallur PH Sn AE |
| Date: 28/11/2025 |
Work in progress | 79% Completed
The work was temporarily stopped, due to election declaration
| Keezhallur PH Sn AE |
| Date: 21/11/2025 |
Work in progress | 79% Completed
PWD Road cutting work progressing
| Keezhallur PH Sn AE |
| Date: 14/11/2025 |
| Keezhallur PH Sn AE |
| Date: 06/11/2025 |
Work in progress | 78% Completed
Out of 3 PWD road cutting permissions, 2 road cutting permission received and COP submitted for the remaining one permission.
| Keezhallur PH Sn AE |
| Date: 23/10/2025 |
Work in progress | 78% Completed
COP Submitted for road cutting permission.
| Keezhallur PH Sn AE |
| Date: 15/10/2025 |
Work in progress | 78% Completed
Out of 3 PWD road cutting permissions, 2 road cutting permission received and COP submitted for the remaining one permission.
| Keezhallur PH Sn AE |
| Date: 10/10/2025 |
Work in progress | 78% Completed
3.1 Km of pipeline laid .PWD road crossing waiting for permission
| Keezhallur PH Sn AE |
| Date: 03/10/2025 |
Work in progress | 78% Completed
3.1 Km of pipeline laid .PWD road crossing waiting for permission
| Keezhallur PH Sn AE |
| Date: 27/09/2025 |
Work in progress | 78% Completed
3.1 Km of pipeline laid .PWD road crossing waiting for permission
| Keezhallur PH Sn AE |
| Date: 24/09/2025 |
Work in progress | 78% Completed
3.1 Km of pipeline laid .PWD road crossing waiting for permission
| Keezhallur PH Sn AE |
| Date: 20/09/2025 |
Work in progress | 78% Completed
3.1 Km of pipeline laid .PWD road crossing waiting for permission
| Keezhallur PH Sn AE |
| Date: 25/08/2025 |
Work in progress | 78% Completed
3.1 Km of pipeline laid .PWD road crossing waiting for permission
| Keezhallur PH Sn AE |
| Date: 16/08/2025 |
Work in progress | 78% Completed
3.1 km pipe line laid
| Keezhallur PH Sn AE |
| Date: 06/08/2025 |
Work in progress | 78% Completed
3 Km of pipeline laid .Work stopped due to monsoon.
| Keezhallur PH Sn AE |
| Date: 28/07/2025 |
Work in progress | 78% Completed
3 Km of pipeline laid .Work stopped due to monsoon.
| Keezhallur PH Sn AE |
| Date: 14/07/2025 |
Work in progress | 78% Completed
3 Km of pipeline laid .Work stopped due to monsoon.
| Keezhallur PH Sn AE |
| Date: 27/06/2025 |
Work in progress | 78% Completed
3 Km of pipeline laid .Work stopped due to monsoon.
| Keezhallur PH Sn AE |
| Date: 17/06/2025 |
Work in progress | 78% Completed
3 Km of pipeline laid .Work stopped due to monsoon.
| Keezhallur PH Sn AE |
| Date: 31/05/2025 |
Work in progress | 78% Completed
3 Km of pipeline completed. Work stopped due to monsoon rains.
| Keezhallur PH Sn AE |
| Date: 22/04/2025 |
Work in progress | 10% Completed
PWD demand notice waiting.
| Keezhallur PH Sn AE |
| Date: 08/04/2025 |
Work in progress | 10% Completed
PWD demand notice waiting.
| Keezhallur PH Sn AE |
| Date: 01/04/2025 |
Work in progress | 10% Completed
PWD demand notice waiting.
| Keezhallur PH Sn AE |
| Date: 27/03/2025 |
Work in progress | 10% Completed
PWD demand notice waiting.
| Keezhallur PH Sn AE |
| Date: 19/03/2025 |
Work in progress | 10% Completed
PWD demand notice waiting.
| Keezhallur PH Sn AE |
| Date: 05/03/2025 |
Work in progress | 1% Completed
LOA issued and Agreement executed on 12-11-2024.Pipe supplied.PWD demand notice waiting.
| Keezhallur PH Sn AE |
| Date: 18/02/2025 |
Work in progress | 1% Completed
LOA issued and Agreement executed on 12-11-2024.Pipe supplied.PWD demand notice waiting.
| Keezhallur PH Sn AE |
| Date: 10/02/2025 |
Work in progress | 1% Completed
LOA issued and Agreement executed on 12-11-2024.Pipe supplied.PWD demand notice waiting.
| Keezhallur PH Sn AE |
| Date: 31/01/2025 |
Work in progress | 1% Completed
LOA issued and Agreement executed on 12-11-2024.Pipe supplied.PWD demand notice waiting.
| Keezhallur PH Sn AE |
| Date: 03/01/2025 |
Work in progress | 0% Completed
LOA issued and Agreement executed on 12-11-2024
| Keezhallur PH Sn AE |
| Date: 16/12/2024 |
Work in progress | 0% Completed
LOA issued and Agreement executed on 12-11-2024
| Keezhallur PH Sn AE |
| Date: 05/12/2024 |
Work has started | 0% Completed
LOA issued and Agreement executed on 12-11-2024
| Kannur PH Dn EE |
| Date: 18/11/2024 |
Work has started | 0% Completed
LOA issued and Agreement executed on 12-11-2024.
| Keezhallur PH Sn AE |
| Date: 13/11/2024 |
Work in progress | 0% Completed
Tender under scrutiny.
| Keezhallur PH Sn AE |
| Date: 02/11/2024 |
Work has started | 0% Completed
Tender under scrutiny.
| Keezhallur PH Sn AE |
| Date: 26/10/2024 |
Work has started | 0% Completed
Tender under scrutiny.
| Keezhallur PH Sn AE |
| Date: 24/10/2024 |
Work has started | 0% Completed
Tender under scrutiny.
| Kannur PH Dn EE |
| Date: 21/10/2024 |
Work has started | 0% Completed
Tender under scrutiny
| Kannur PH Dn EE |
| Date: 14/10/2024 |
Work has started | 0% Completed
Work retendered with due date 15-10-2024.
| Kannur PH Dn EE |
| Date: 27/09/2024 |
Work has started | 0% Completed
TS issued & work tendered.
| Keezhallur PH Sn AE |
| Date: 26/09/2024 |
Work has started | 0% Completed
Work to be tendered.
| Keezhallur PH Sn AE |
| Date: 18/09/2024 |
Work has started | 0% Completed
To be tendered.
| Keezhallur PH Sn AE |
| Date: 10/09/2024 |
Work has started | 0% Completed
AS Accorded on 23/07/2024, work to be tendered.
| Keezhallur PH Sn AE |
| Date: 03/09/2024 |
Work has started | 0% Completed
AS Accorded on 23/07/2024, work to be tendered.
| Kannur PH Dn EE |
| Date: 14/08/2024 |
Work has started | 0% Completed
AS Accorded on 23/07/2024, work to be tendered.