| Sasthamcotta WS Sn 1 - AE |
| Date: 16/10/2023 |
Work has been completed | 100% Completed
Deposit Work of RWSS To Kunnathoor - Disconnection of public tap in Kunnathoor Grama Panchayath - 100 % of work completed
| Sasthamcotta WS Sn 1 - AE |
| Date: 11/10/2023 |
| Sasthamcotta WS Sn 1 - AE |
| Date: 07/10/2023 |
Work in progress | 90% Completed
Out of 369 / 369 nos public tap disconnection completed. Concrete work (dismantling and demolishing portion) in progress
| Sasthamcotta WS Sn 1 - AE |
| Date: 27/09/2023 |
| Sasthamcotta WS Sn 1 - AE |
| Date: 24/09/2023 |
Work in progress | 85% Completed
Out of 369 / 356 nos public tap disconnection completed
| Sasthamcotta WS Sn 1 - AE |
| Date: 21/09/2023 |
Work in progress | 80% Completed
Out of 369 / 330 nos public tap disconnection completed
| Sasthamcotta WS Sn 1 - AE |
| Date: 19/09/2023 |
Work in progress | 75% Completed
Out of 369 / 310 nos public tap disconnection completed
| Sasthamcotta WS Sn 1 - AE |
| Date: 16/09/2023 |
Work in progress | 72% Completed
Out of 369 / 290 nos public tap disconnection completed
| Sasthamcotta WS Sn 1 - AE |
| Date: 13/09/2023 |
Work in progress | 70% Completed
270 nos disconnection completed
| Sasthamcotta WS Sn 1 - AE |
| Date: 10/09/2023 |
Work in progress | 65% Completed
250 nos disconnection completed
| Sasthamcotta WS Sn 1 - AE |
| Date: 06/09/2023 |
Work in progress | 60% Completed
220 nos disconnection completed
| Sasthamcotta WS Sn 1 - AE |
| Date: 03/09/2023 |
Work in progress | 50% Completed
200 nos disconnection completed
| Sasthamcotta WS Sn 1 - AE |
| Date: 02/09/2023 |
Work in progress | 45% Completed
Work in progress- 180 nos disconnection completed
| Sasthamcotta WS Sn 1 - AE |
| Date: 01/09/2023 |
Work in progress | 35% Completed
Work in progress
| Sasthamcotta WS Sn 1 - AE |
| Date: 30/08/2023 |
Work in progress | 20% Completed
Work on progress
| Sasthamcotta WS Sn 1 - AE |
| Date: 23/08/2023 |
Work in progress | 10% Completed
Work on progress