| Nedumangad AE |
| Date: 17/04/2026 |
Work has been completed | 100% Completed
completed
| Nedumangad AE |
| Date: 10/04/2026 |
Work in progress | 10% Completed
Work started.
| Nedumangad AE |
| Date: 31/01/2026 |
Work in progress | 10% Completed
Work started.
| Nedumangad AE |
| Date: 09/01/2026 |
Work in progress | 10% Completed
Work started.
| Nedumangad AE |
| Date: 20/12/2025 |
Work in progress | 10% Completed
Work started.
| Nedumangad AE |
| Date: 11/12/2025 |
Work in progress | 10% Completed
Work started.
| Nedumangad AE |
| Date: 03/12/2025 |
Work in progress | 10% Completed
Work started.
| Nedumangad AE |
| Date: 25/11/2025 |
Work in progress | 10% Completed
Work started.
| Nedumangad AE |
| Date: 10/11/2025 |
Work in progress | 10% Completed
Work started.
| Nedumangad AE |
| Date: 06/11/2025 |
Work in progress | 10% Completed
Work started.
| Nedumangad AE |
| Date: 30/10/2025 |
Work in progress | 10% Completed
work started
| Nedumangad AE |
| Date: 27/10/2025 |
Work in progress | 10% Completed
work started
| Nedumangad AE |
| Date: 21/10/2025 |
Work in progress | 0% Completed
work order issued
| Nedumangad AE |
| Date: 10/10/2025 |
Work in progress | 0% Completed
work order issued
| Nedumangad AE |
| Date: 25/09/2025 |
Work in progress | 0% Completed
work order issued
| Nedumangad AE |
| Date: 20/09/2025 |
Work in progress | 0% Completed
work order issued
| Nedumangad AE |
| Date: 09/09/2025 |
Work in progress | 0% Completed
work order issued
| Nedumangad AE |
| Date: 01/09/2025 |
Work in progress | 0% Completed
work order issued
| Nedumangad AE |
| Date: 20/08/2025 |
Work in progress | 0% Completed
work order issued
| Nedumangad AE |
| Date: 12/08/2025 |
Work in progress | 0% Completed
work order issued
| Nedumangad AE |
| Date: 04/08/2025 |
Work in progress | 0% Completed
work order issued
| Aruvikkara HW Dn EE |
| Date: 02/08/2025 |
Work has started | 0% Completed
Deposit -UWSS -to Nedumangad Municipality Enhancement of water supply in SUT Hospital area Venkode by using booster pump -pipeline work