Kozhikode Dist 1 Sn 2 - AE
Date: 24/09/2024

Work has been completed | 100% Completed

Work completed.Final bill submitted.

Kozhikode Dist 1 Sn 2 - AE
Date: 11/09/2024

Work has been completed | 100% Completed

RE approved. Final bill under process.

Kozhikode Dist 1 Sn 2 - AE
Date: 21/08/2024

Work has been completed | 100% Completed

Work completed.Final bill pending.RE submitted

Kozhikode PH Dn EE
Date: 21/04/2024

Work in progress | 75% Completed

Work in progress

Kozhikode PH Dn EE
Date: 04/04/2024

Work in progress | 59% Completed

Work in progress

Kozhikode PH Dn EE
Date: 12/03/2024

Work in progress | 55% Completed

WORK IN PROGRESS

Kozhikode PH Dn EE
Date: 14/02/2024

Work in progress | 50% Completed

WORK IN PROGRESS

Kozhikode PH Dn EE
Date: 27/01/2024

Work has started | 0% Completed

Work Not Yet Started

Kozhikode PH Dn EE
Date: 12/01/2024

Work has started | 0% Completed

Work Not Yet Started

Kozhikode PH Dn EE
Date: 11/12/2023

Work has started | 0% Completed

Work Not Yet Started

Kozhikode PH Dn EE
Date: 29/11/2023

Work has started | 0% Completed

Waiting for road cutting permission

Kozhikode PH Dn EE
Date: 31/10/2023

Work has started | 0% Completed

Agreement Executed