| Kozhikode PH Dn EE |
| Date: 11/03/2025 |
Work in progress | 0% Completed
Work Short closed
| Kozhikode PH Dn EE |
| Date: 24/02/2025 |
Work has started | 0% Completed
oad-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval ROW/10109084
| Kozhikode PH Dn EE |
| Date: 11/02/2025 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval ROW/10109084
| Kozhikode PH Dn EE |
| Date: 24/01/2025 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval ROW/10109084
| Kozhikode PH Dn EE |
| Date: 22/01/2025 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval ROW/10109084
| Kozhikode PH Dn EE |
| Date: 21/01/2025 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval ROW/10109084
| Kozhikode PH Dn EE |
| Date: 18/01/2025 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval ROW/10109084
| Kozhikode PH Dn EE |
| Date: 17/01/2025 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval ROW/10109084
| Kozhikode PH Dn EE |
| Date: 15/01/2025 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval ROW/10109084
| Kozhikode PH Dn EE |
| Date: 13/01/2025 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval ROW/10109084
| Kozhikode PH Dn EE |
| Date: 09/01/2025 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval ROW/10109084
| Kozhikode PH Dn EE |
| Date: 04/01/2025 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval ROW/10109084
| Kozhikode PH Dn EE |
| Date: 01/01/2025 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval ROW/10109084
| Kozhikode PH Dn EE |
| Date: 21/12/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval ROW/10109084
| Kozhikode PH Dn EE |
| Date: 16/12/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval ROW/10109084
| Kozhikode PH Dn EE |
| Date: 10/12/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval ROW/10109084
| Kozhikode PH Dn EE |
| Date: 07/12/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval
| Kozhikode PH Dn EE |
| Date: 03/12/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval
| Kozhikode PH Dn EE |
| Date: 27/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval
| Kozhikode PH Dn EE |
| Date: 26/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval
| Kozhikode PH Dn EE |
| Date: 25/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval
| Kozhikode PH Dn EE |
| Date: 22/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval
| Kozhikode PH Dn EE |
| Date: 21/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval
| Kozhikode PH Dn EE |
| Date: 20/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval
| Kozhikode PH Dn EE |
| Date: 19/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval
| Kozhikode PH Dn EE |
| Date: 18/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval
| Kozhikode PH Dn EE |
| Date: 16/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval
| Kozhikode PH Dn EE |
| Date: 15/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval
| Kozhikode PH Dn EE |
| Date: 14/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval
| Kozhikode PH Dn EE |
| Date: 13/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval
| Kozhikode PH Dn EE |
| Date: 12/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval
| Kozhikode PH Dn EE |
| Date: 11/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval
| Kozhikode PH Dn EE |
| Date: 08/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval
| Kozhikode PH Dn EE |
| Date: 07/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval
| Kozhikode PH Dn EE |
| Date: 06/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval.
| Kozhikode PH Dn EE |
| Date: 02/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 01/11/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 30/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 24/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 23/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 22/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 21/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 19/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 18/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 17/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 16/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 15/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 14/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 12/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 11/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 10/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 09/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 08/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 07/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 05/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 04/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 03/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 01/10/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 30/09/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 28/09/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 27/09/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 26/09/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 25/09/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 24/09/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 23/09/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 20/09/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 19/09/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 18/09/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 13/09/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for getting approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 12/09/2024 |
Work has started | 0% Completed
Road cutting permission from PWD NH and PWD is required. Hard copies submitted to Morth for getting approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 11/09/2024 |
Work has started | 0% Completed
Road cutting permission from PWD NH and PWD is required. Hard copies submitted to Morth for getting approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 10/09/2024 |
Work has started | 0% Completed
Road cutting permission from PWD NH and PWD is required. Hard copies submitted to Morth for getting approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 09/09/2024 |
Work has started | 0% Completed
Road-cutting permission from PWD NH and PWD is required. Hard copies were submitted to Morth for getting approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 21/08/2024 |
Work has started | 0% Completed
Road cutting permission from PWD NH and PWD is required. Hard copies submitted to Morth for getting approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 19/08/2024 |
Work has started | 0% Completed
Road cutting permission from PWD NH and PWD is required. Hard copies submitted to Morth for getting approval. New Row-119957
| Kozhikode PH Dn EE |
| Date: 16/08/2024 |
Work has started | 0% Completed
Road cutting permission not recieved from PWD. Road under DLP
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 0% Completed
Supply order placed for pipes
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 0% Completed
Supply order placed for pipes
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work has started | 0% Completed
Supply order placed for pipes
| Kozhikode PH Dn EE |
| Date: 05/03/2024 |
Work has started | 0% Completed
Supply order placed for pipes
| Kozhikode PH Dn EE |
| Date: 04/03/2024 |
Work has started | 0% Completed
Supply order placed for pipes
| Kozhikode PH Dn EE |
| Date: 03/03/2024 |
Work has started | 0% Completed
Supply order placed for pipes
| Kozhikode PH Dn EE |
| Date: 02/03/2024 |
Work has started | 0% Completed
Supply order placed for pipes
| Kozhikode PH Dn EE |
| Date: 01/03/2024 |
Work has started | 0% Completed
Supply order placed for pipes
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work has started | 0% Completed
Work Not Started
| Kozhikode PH Dn EE |
| Date: 30/01/2024 |
Work has started | 0% Completed
Agreement executed
| Kozhikode PH Dn EE |
| Date: 29/01/2024 |
Work has started | 0% Completed
Agreement executed
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work has started | 0% Completed
Work Order Issued
| Kozhikode PH Dn EE |
| Date: 12/01/2024 |
Work has started | 0% Completed
Work Order Issued
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work has started | 0% Completed
Work Order Issued
| Kozhikode PH Dn EE |
| Date: 29/11/2023 |
Work has started | 0% Completed
Work Order Issued
| Kozhikode PH Dn EE |
| Date: 30/10/2023 |
Work has started | 0% Completed
Work Order Issued