Kattapana Project Dn AE4 |
Date: 17/08/2021 |
Work has been completed | 100% Completed
Work has been completed
Kattapana Project Dn AE4 |
Date: 11/08/2021 |
Work has been completed | 100% Completed
Work has been completed
Kattapana Project Dn AE4 |
Date: 29/07/2021 |
Work has been completed | 100% Completed
Work has been completed
Kattapana Project Dn AE4 |
Date: 28/07/2021 |
Work has been completed | 100% Completed
Work has been completed
Kattapana Project Dn AE4 |
Date: 25/07/2021 |
Work has been completed | 100% Completed
Work has been completed
Kattapana Project Dn AE4 |
Date: 22/07/2021 |
Work has been completed | 100% Completed
Work has been completed
Kattapana Project Dn AE4 |
Date: 19/07/2021 |
Work has been completed | 100% Completed
Work has been completed
Kattapana Project Dn AE4 |
Date: 08/07/2021 |
Work has been completed | 100% Completed
Work completed
Kattapana Project Dn AE4 |
Date: 07/07/2021 |
Work in progress | 96% Completed
FHTC Provided - 800 Shifting connection works are in progress
Kattapana Project Dn AE4 |
Date: 05/07/2021 |
Work in progress | 96% Completed
FHTC Provided - 800 Shifting connection works are in progress
Kattapana Project Dn AE4 |
Date: 03/07/2021 |
Work in progress | 96% Completed
Work is in progress.
Kattapana Project Dn AE4 |
Date: 23/06/2021 |
Work in progress | 96% Completed
Work in progress
Kattapana Project Dn AE4 |
Date: 21/06/2021 |
Work in progress | 96% Completed
Work in progress
Kattapana Project Dn AE4 |
Date: 14/06/2021 |
Work in progress | 96% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 10/06/2021 |
Work in progress | 96% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 07/06/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 05/06/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 03/06/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 01/06/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 25/05/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 21/05/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 18/05/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 15/05/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 11/05/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 08/05/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 05/05/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 04/05/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 03/05/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 29/04/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 27/04/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 26/04/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 21/04/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 19/04/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 15/04/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 11/04/2021 |
Work in progress | 95% Completed
Total FHTCs as per Agreement - 800 nos FHTCs Given - 800 nos FHTSs Billed - 800 nos The works of shifting water connection under progress
Kattapana Project Dn AE4 |
Date: 07/04/2021 |
Work in progress | 95% Completed
Work in progress | 95% Completed | 30/03/2021
Kattapana Project Dn AE4 |
Date: 30/03/2021 |
Work in progress | 94% Completed
Par Bill submitted.
Kattapana Project Dn AE4 |
Date: 27/03/2021 |
Work in progress | 94% Completed
Total FHTC to be given - 800nos FHTC given - 800nos FHTC Billed - 800nos. Other connected works are in Work in progress.
Kattapana Project Dn AE4 |
Date: 26/03/2021 |
Work in progress | 94% Completed
otal FHTC to be given - 800nos FHTC given - 800nos FHTC Billed - 800nos. Other connected works are in Work in progress.
Kattapana Project Dn AE4 |
Date: 25/03/2021 |
Work in progress | 94% Completed
Total FHTC to be given - 800nos FHTC given - 800nos FHTC Billed - 800nos. Other connected works are in Work in progress.
Kattapana Project Dn AE4 |
Date: 24/03/2021 |
Work in progress | 94% Completed
Work in progress | 94% Completed
Kattapana Project Dn AE4 |
Date: 21/03/2021 |
Work in progress | 94% Completed
Total No. of FHTC as per agreement - 800 nos Total FHTC Given - 800 Bill submitted - 798 The work of shifting chocked old connections is progressing
Kattapana Project Dn AE4 |
Date: 19/03/2021 |
Work in progress | 94% Completed
The work of shifting chocked old connections is progressing
Kattapana Project Dn AE4 |
Date: 17/03/2021 |
Work in progress | 94% Completed
The work of shifting chocked old connections is progressing
Kattapana Project Dn AE4 |
Date: 15/03/2021 |
Work in progress | 93% Completed
Total FHTC - 800nos FHTC given- 798 FHTC Billed - 798 Repairing the choked connections and line repairing is under progress.
Kattapana Project Dn AE4 |
Date: 11/03/2021 |
Work in progress | 93% Completed
The work in progress.
Kattapana Project Dn AE4 |
Date: 08/03/2021 |
Work in progress | 93% Completed
Work in progress
Kattapana Project Dn AE4 |
Date: 05/03/2021 |
Work in progress | 93% Completed
work under progress
Kattapana Project Dn AE4 |
Date: 01/03/2021 |
Work in progress | 92% Completed
Bill for 598 nos of FHTCs under scrutiny
Kattapana Project Dn AE4 |
Date: 25/02/2021 |
Work in progress | 90% Completed
Bill under preparation
Kattapana Project Dn AE4 |
Date: 21/02/2021 |
Work in progress | 86% Completed
740/800 FHTCs completed.Bill under preparation.
Kattapana Project Dn AE4 |
Date: 15/02/2021 |
Work in progress | 81% Completed
Work in progress. 650/800 FHTCs are providied.
Kattapana Project Dn AE4 |
Date: 08/02/2021 |
Work in progress | 75% Completed
597/800 FHTCs billed.
Kattapana Project Dn AE4 |
Date: 31/01/2021 |
Work in progress | 75% Completed
2nd and Part Bill for 597 FHTCs submitted
Kattapana Project Dn AE4 |
Date: 31/12/2020 |
Kattapana Project Dn AE4 |
Date: 21/11/2020 |
Work in progress | 18% Completed
50 nos of FHTC Completed, Pipe Supply Completed