Irinjalakuda AE |
Date: 28/09/2021 |
Work has been completed | 100% Completed
Bill submitted
Irinjalakuda AE |
Date: 24/09/2021 |
Work has been completed | 100% Completed
175 FHTC provided and bill submitted
Irinjalakuda AE |
Date: 22/09/2021 |
Work has been completed | 100% Completed
175 FHTC Provided and bill submitted
Irinjalakuda AE |
Date: 17/09/2021 |
Work in progress | 98% Completed
173 FHTC Provided
Irinjalakuda AE |
Date: 13/09/2021 |
Work in progress | 98% Completed
173 FHTC Provided
Irinjalakuda AE |
Date: 09/09/2021 |
Work in progress | 95% Completed
167 FHTC Provided
Irinjalakuda AE |
Date: 06/09/2021 |
Work in progress | 93% Completed
163 FHTC provided
Irinjalakuda AE |
Date: 04/09/2021 |
Work in progress | 49% Completed
86 FHTC Provided
Irinjalakuda AE |
Date: 02/09/2021 |
Work in progress | 43% Completed
Work in progress
Irinjalakkuda PH Dn EE |
Date: 31/08/2021 |
Work in progress | 42% Completed
73 FHTC PROVIDED
Irinjalakkuda PH Dn EE |
Date: 27/08/2021 |
Work in progress | 42% Completed
Work on progress
Irinjalakuda AE |
Date: 25/08/2021 |
Work in progress | 42% Completed
73 FHTCs provided
Irinjalakuda AE |
Date: 18/08/2021 |
Work in progress | 32% Completed
56 FHTC provided