| Kozhikode PH Dn EE |
| Date: 20/03/2025 |
Work has been completed | 100% Completed
Final bill submitted.
| Kozhikode PH Dn EE |
| Date: 22/01/2025 |
Work has been completed | 100% Completed
Final bill submitted.
| Kozhikode PH Dn EE |
| Date: 10/01/2025 |
Work has been completed | 100% Completed
Final bill submitted.
| Kozhikode PH Dn EE |
| Date: 03/01/2025 |
Work has been completed | 100% Completed
Final bill submitted.
| Kozhikode PH Dn EE |
| Date: 12/12/2024 |
Work has been completed | 100% Completed
Final bill submitted.
| Kozhikode PH Dn EE |
| Date: 02/12/2024 |
Work has been completed | 100% Completed
Final bill submitted.
| Kozhikode PH Dn EE |
| Date: 27/11/2024 |
Work has been completed | 100% Completed
Final bill submitted.
| Kozhikode PH Dn EE |
| Date: 22/11/2024 |
Work has been completed | 100% Completed
Final bill submitted.
| Kozhikode PH Dn EE |
| Date: 20/11/2024 |
Work has been completed | 100% Completed
Final bill submitted.
| Kozhikode PH Dn EE |
| Date: 13/11/2024 |
Work has been completed | 100% Completed
Final bill submitted.
| Kozhikode PH Dn EE |
| Date: 11/11/2024 |
Work has been completed | 100% Completed
Final bill submitted.
| Kozhikode PH Dn EE |
| Date: 29/10/2024 |
Work has been completed | 100% Completed
Final bill submitted.
| Kozhikode PH Dn EE |
| Date: 19/10/2024 |
Work has been completed | 100% Completed
Final bill submitted.
| Kozhikode PH Dn EE |
| Date: 28/09/2024 |
Work has been completed | 100% Completed
Final bill submitted.
| Kozhikode PH Dn EE |
| Date: 19/09/2024 |
Work has been completed | 100% Completed
Final bill submitted
| Kozhikode PH Dn EE |
| Date: 10/09/2024 |
Work has been completed | 100% Completed
Final bill submitted
| Kozhikode PH Dn EE |
| Date: 21/08/2024 |
Work has been completed | 100% Completed
Final bill submitted.
| Kozhikode PH Dn EE |
| Date: 27/06/2024 |
Work in progress | 95% Completed
on going
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 50% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 22% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 15% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 12% Completed
Work started
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 9% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 11/01/2024 |
Work in progress | 8% Completed
Pipe Supplyed
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work in progress | 6% Completed
Pipe Supplyed
| Kozhikode PH Dn EE |
| Date: 29/11/2023 |
Work in progress | 5% Completed
Pipe Supplyed
| Kozhikode PH Dn EE |
| Date: 28/10/2023 |
Work has started | 0% Completed
Site Handed Over