Kozhikode WestHill Distribution Sn - 1/1 - AE
Date: 28/12/2024

Work has been completed | 100% Completed

WORK COMPLETED

Kozhikode WestHill Distribution Sn - 1/1 - AE
Date: 07/12/2024

Work in progress | 95% Completed

on going

Kozhikode WestHill Distribution Sn - 1/1 - AE
Date: 03/12/2024

Work in progress | 95% Completed

on going

Kozhikode WestHill Distribution Sn - 1/1 - AE
Date: 22/11/2024

Work in progress | 94% Completed

ongoing

Kozhikode WestHill Distribution Sn - 1/1 - AE
Date: 06/11/2024

Work in progress | 94% Completed

on going

Kozhikode WestHill Distribution Sn - 1/1 - AE
Date: 26/10/2024

Work in progress | 94% Completed

on going

Kozhikode WestHill Distribution Sn - 1/1 - AE
Date: 23/10/2024

Work in progress | 94% Completed

on going

Kozhikode WestHill Distribution Sn - 1/1 - AE
Date: 05/10/2024

Work in progress | 94% Completed

work in progress

Kozhikode WestHill Distribution Sn - 1/1 - AE
Date: 24/09/2024

Work in progress | 93% Completed

on going

Kozhikode WestHill Distribution Sn - 1/1 - AE
Date: 11/09/2024

Work in progress | 91% Completed

on going

Kozhikode WestHill Distribution Sn - 1/1 - AE
Date: 21/08/2024

Work in progress | 90% Completed

2 interconnetion work pending

Kozhikode PH Dn EE
Date: 20/04/2024

Work in progress | 40% Completed

Work in progress

Kozhikode PH Dn EE
Date: 04/04/2024

Work in progress | 35% Completed

Work in progress

Kozhikode PH Dn EE
Date: 12/03/2024

Work in progress | 30% Completed

Work in progress

Kozhikode PH Dn EE
Date: 14/02/2024

Work in progress | 20% Completed

Work started

Kozhikode PH Dn EE
Date: 27/01/2024

Work in progress | 16% Completed

Pipe Supplied

Kozhikode PH Dn EE
Date: 12/01/2024

Work in progress | 14% Completed

Pipe Supplied

Kozhikode PH Dn EE
Date: 11/12/2023

Work in progress | 13% Completed

Pipe Supplied

Kozhikode PH Dn EE
Date: 29/11/2023

Work in progress | 10% Completed

Pipe Supplied

Kozhikode PH Dn EE
Date: 30/10/2023

Work in progress | 3% Completed

Pipe Supplied