| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 28/12/2024 |
Work has been completed | 100% Completed
WORK COMPLETED
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 07/12/2024 |
Work in progress | 95% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 03/12/2024 |
Work in progress | 95% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 22/11/2024 |
Work in progress | 94% Completed
ongoing
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 06/11/2024 |
Work in progress | 94% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 26/10/2024 |
Work in progress | 94% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 23/10/2024 |
Work in progress | 94% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 05/10/2024 |
Work in progress | 94% Completed
work in progress
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 24/09/2024 |
Work in progress | 93% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 11/09/2024 |
Work in progress | 91% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 21/08/2024 |
Work in progress | 90% Completed
2 interconnetion work pending
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 40% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 35% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 30% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 20% Completed
Work started
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 16% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 12/01/2024 |
Work in progress | 14% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work in progress | 13% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 29/11/2023 |
Work in progress | 10% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 30/10/2023 |
Work in progress | 3% Completed
Pipe Supplied