All updates

Thiruvananthapuram - Med col - AE
Date: 27/04/2022

Work has been completed | 100% Completed

Work has been completed

Thiruvananthapuram - Med col - AE
Date: 25/04/2022

Work has been completed | 100% Completed

Work has been completed

Thiruvananthapuram - Med col - AE
Date: 22/04/2022

Work has been completed | 100% Completed

Work has been completed

Thiruvananthapuram - Med col - AE
Date: 20/04/2022

Work has been completed | 100% Completed

Work has been completed

Thiruvananthapuram - Med col - AE
Date: 18/04/2022

Work has been completed | 100% Completed

Work has been completed

Thiruvananthapuram - Med col - AE
Date: 13/04/2022

Work has been completed | 100% Completed

Work has been completed

Thiruvananthapuram - Med col - AE
Date: 11/04/2022

Work has been completed | 100% Completed

Work has been completed

Thiruvananthapuram - Med col - AE
Date: 04/04/2022

Work has been completed | 100% Completed

Work has been completed

Thiruvananthapuram - Med col - AE
Date: 01/04/2022

Work has been completed | 100% Completed

Work has been completed

Thiruvananthapuram - Med col - AE
Date: 30/03/2022

Work has been completed | 100% Completed

Work has been completed

Thiruvananthapuram - Med col - AE
Date: 24/03/2022

Work has been completed | 100% Completed

Work has been completed

Thiruvananthapuram - Med col - AE
Date: 22/03/2022

Work has been completed | 100% Completed

Work has been completed

Thiruvananthapuram - Med col - AE
Date: 19/03/2022

Work has been completed | 100% Completed

Work has been completed

Thiruvananthapuram - Med col - AE
Date: 18/03/2022

Work has been completed | 100% Completed

Work has been completed

Thiruvananthapuram - Med col - AE
Date: 16/03/2022

Work has been completed | 100% Completed

Work has been completed

Pattoor Sewerage Dn
Date: 14/03/2022

Work has been completed | 100% Completed

Work completed

Thiruvananthapuram - Med col - AE
Date: 10/03/2022

Work in progress | 97% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 08/03/2022

Work in progress | 95% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 04/03/2022

Work in progress | 95% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 02/03/2022

Work in progress | 95% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 28/02/2022

Work in progress | 95% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 27/02/2022

Work in progress | 95% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 25/02/2022

Work in progress | 94% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 23/02/2022

Work in progress | 93% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 21/02/2022

Work in progress | 93% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 18/02/2022

Work in progress | 93% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 16/02/2022

Work in progress | 93% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 14/02/2022

Work in progress | 92% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 09/02/2022

Work in progress | 92% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 07/02/2022

Work in progress | 92% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 04/02/2022

Work in progress | 90% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 02/02/2022

Work in progress | 90% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 27/01/2022

Work in progress | 83% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 25/01/2022

Work in progress | 83% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 21/01/2022

Work in progress | 82% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 18/01/2022

Work in progress | 82% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 13/01/2022

Work in progress | 81% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 12/01/2022

Work in progress | 81% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 10/01/2022

Work in progress | 81% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 06/01/2022

Work in progress | 81% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 03/01/2022

Work in progress | 81% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 31/12/2021

Work in progress | 81% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 29/12/2021

Work in progress | 81% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 27/12/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 24/12/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 21/12/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 18/12/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 14/12/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 10/12/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 07/12/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 03/12/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 30/11/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 27/11/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 24/11/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 22/11/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 18/11/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 16/11/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 12/11/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 10/11/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 08/11/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 06/11/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 01/11/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 29/10/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 27/10/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 25/10/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 21/10/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 18/10/2021

Work in progress | 80% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 16/10/2021

Work in progress | 79% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 13/10/2021

Work in progress | 78% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 11/10/2021

Work in progress | 77% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 08/10/2021

Work in progress | 76% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 01/10/2021

Work in progress | 74% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 28/09/2021

Work in progress | 73% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 24/09/2021

Work in progress | 72% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 22/09/2021

Work in progress | 71% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 20/09/2021

Work in progress | 70% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 17/09/2021

Work in progress | 69% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 15/09/2021

Work in progress | 68% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 13/09/2021

Work in progress | 67% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 09/09/2021

Work in progress | 66% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 07/09/2021

Work in progress | 65% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 04/09/2021

Work in progress | 64% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 02/09/2021

Work in progress | 64% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 31/08/2021

Work in progress | 63% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 28/08/2021

Work in progress | 62% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 27/08/2021

Work in progress | 61% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 26/08/2021

Work in progress | 61% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 24/08/2021

Work in progress | 60% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 22/08/2021

Work in progress | 59% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 18/08/2021

Work in progress | 58% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 16/08/2021

Work in progress | 57% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 14/08/2021

Work in progress | 56% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 13/08/2021

Work in progress | 55% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 11/08/2021

Work in progress | 54% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 09/08/2021

Work in progress | 53% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 05/08/2021

Work in progress | 52% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 02/08/2021

Work in progress | 51% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 29/07/2021

Work in progress | 50% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 26/07/2021

Work in progress | 49% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 23/07/2021

Work in progress | 48% Completed

Running Contract works in Progress

Thiruvananthapuram - Med col - AE
Date: 20/07/2021

Work in progress | 47% Completed

Running Contract works in Progress

Pattoor Sewerage Dn
Date: 16/07/2021

Work in progress | 46% Completed

Running Contract works in Progress

Pattoor Sewerage Dn
Date: 14/07/2021

Work in progress | 45% Completed

Running Contract works in Progress

Pattoor Sewerage Dn
Date: 12/07/2021

Work in progress | 44% Completed

Running Contract works in Progress

Pattoor Sewerage Dn
Date: 09/07/2021

Work in progress | 43% Completed

Running Contract works in Progress

Pattoor Sewerage Dn
Date: 05/07/2021

Work in progress | 42% Completed

Running Contract works in Progress

Pattoor Sewerage Dn
Date: 02/07/2021

Work in progress | 41% Completed

Running Contract works in Progress

Pattoor Sewerage Dn
Date: 30/06/2021

Work in progress | 40% Completed

Running Contract works in Progress

Pattoor Sewerage Dn
Date: 25/06/2021

Work in progress | 38% Completed

Running Contract works in Progress

Pattoor Sewerage Dn
Date: 21/06/2021

Work in progress | 37% Completed

Running Contract works in Progress

Pattoor Sewerage Dn
Date: 17/06/2021

Work in progress | 36% Completed

Running Contract works in Progress

Pattoor Sewerage Dn
Date: 14/06/2021

Work in progress | 35% Completed

Running Contract works in Progress

Pattoor Sewerage Dn
Date: 10/06/2021

Work in progress | 34% Completed

Running Contract works in Progress

Pattoor Sewerage Dn
Date: 06/06/2021

Work in progress | 33% Completed

Running Contract works in Progress

Pattoor Sewerage Dn
Date: 02/06/2021

Work in progress | 32% Completed

Running Contract works in Progress

Pattoor Sewerage Dn
Date: 31/05/2021

Work in progress | 30% Completed

RC Work Ongoing

Pattoor Sewerage Dn
Date: 28/05/2021

Work in progress | 27% Completed

RC Work Ongoing

Pattoor Sewerage Dn
Date: 24/05/2021

Work in progress | 26% Completed

RC Work Ongoing

Pattoor Sewerage Dn
Date: 20/05/2021

Work in progress | 25% Completed

RC Work Ongoing

Pattoor Sewerage Dn
Date: 17/05/2021

Work in progress | 24% Completed

RC Work Ongoing

Pattoor Sewerage Dn
Date: 14/05/2021

Work in progress | 24% Completed

RC Work Ongoing

Pattoor Sewerage Dn
Date: 04/05/2021

Work in progress | 23% Completed

RC Work Ongoing

Pattoor Sewerage Dn
Date: 30/04/2021

Work in progress | 20% Completed

RC Work Ongoing

Pattoor Sewerage Dn
Date: 26/04/2021

Work in progress | 19% Completed

RC Work Ongoing

Pattoor Sewerage Dn
Date: 21/04/2021

Work in progress | 18% Completed

RC Work Ongoing

Pattoor Sewerage Dn
Date: 16/04/2021

Work in progress | 16% Completed

RC Work Ongoing

Pattoor Sewerage Dn
Date: 12/04/2021

Work in progress | 15% Completed

RC Work Ongoing

Pattoor Sewerage Dn
Date: 07/04/2021

Work in progress | 14% Completed

RC Work Ongoing

Pattoor Sewerage Dn
Date: 31/03/2021

Work in progress | 12% Completed

RC Work Ongoing

Pattoor Sewerage Dn
Date: 27/03/2021

Work in progress | 11% Completed

RC Work Ongoing

Pattoor Sewerage Dn
Date: 23/03/2021

Work in progress | 10% Completed

RC Work Ongoing

Pattoor Sewerage Dn
Date: 16/03/2021

Work in progress | 8% Completed

RC Work On going

Pattoor Sewerage Dn
Date: 05/03/2021

Work in progress | 5% Completed

RC Work On going

Pattoor Sewerage Dn
Date: 16/02/2021

Work in progress | 1% Completed

RC Work On going

Pattoor Sewerage Dn
Date: 09/02/2021

Work in progress | 1% Completed

RC Work On Started

Pattoor Sewerage Dn
Date: 08/02/2021

Work has started | 0% Completed

Work Order Issued

Pattoor Sewerage Dn
Date: 03/02/2021

Work in progress | 0% Completed

Tender opened on 02/02/2021

Pattoor Sewerage Dn
Date: 27/01/2021

Work has started | 0% Completed

tendered