| Idukki QCDL - AE |
| Date: 19/07/2022 |
Work has been completed | 100% Completed
Work completed, Final bill under preparation.
| Idukki QCDL - AE |
| Date: 24/06/2022 |
Work has been completed | 100% Completed
work completed final bill under preperation
| Idukki QCDL - AE |
| Date: 25/03/2022 |
Work in progress | 80% Completed
Electrical work in progress. Painting and fabrication work in progress.
| Idukki QCDL - AE |
| Date: 23/03/2022 |
Work in progress | 75% Completed
Flooring work completed .Electrical work in progress. Painting work in progress.
| Idukki QCDL - AE |
| Date: 18/03/2022 |
Work in progress | 65% Completed
Flooring work started .electrical work in progress.
| Idukki QCDL - AE |
| Date: 16/03/2022 |
Work in progress | 62% Completed
electrical work stated.
| Idukki QCDL - AE |
| Date: 14/03/2022 |
Work in progress | 60% Completed
floor p c c work started.
| Idukki QCDL - AE |
| Date: 11/03/2022 |
| Idukki QCDL - AE |
| Date: 10/03/2022 |
| Idukki QCDL - AE |
| Date: 09/03/2022 |
Work in progress | 52% Completed
plastering work in progress.
| Idukki QCDL - AE |
| Date: 07/03/2022 |
| Idukki QCDL - AE |
| Date: 04/03/2022 |
Work in progress | 51% Completed
plastering work in progress
| Idukki QCDL - AE |
| Date: 03/03/2022 |
Work in progress | 50% Completed
plastering work in progress
| Idukki QCDL - AE |
| Date: 25/02/2022 |
Work in progress | 45% Completed
plastering work of out side wall started
| Idukki QCDL - AE |
| Date: 23/02/2022 |
Work in progress | 45% Completed
roof concrete work completed.
| Idukki QCDL - AE |
| Date: 21/02/2022 |
Work in progress | 45% Completed
roof concrete work completed.
| Idukki QCDL - AE |
| Date: 19/02/2022 |
Work in progress | 45% Completed
roof concrete work completed.
| Idukki QCDL - AE |
| Date: 17/02/2022 |
Work in progress | 45% Completed
roof concrete work completed.
| Idukki QCDL - AE |
| Date: 16/02/2022 |
Work in progress | 42% Completed
centering and shuttering for roof slab completed.
| Idukki QCDL - AE |
| Date: 03/02/2022 |
Work in progress | 40% Completed
centering and shuttering for lintel in progress.
| Idukki QCDL - AE |
| Date: 02/02/2022 |
Work in progress | 40% Completed
centering and shuttering for lintel started.
| Idukki QCDL - AE |
| Date: 01/02/2022 |
Work in progress | 39% Completed
brick masonry work completed.
| Idukki QCDL - AE |
| Date: 31/01/2022 |
Work in progress | 38% Completed
brick masonry work in progress.
| Idukki QCDL - AE |
| Date: 29/01/2022 |
Work in progress | 38% Completed
brick masonry work in progress.
| Idukki QCDL - AE |
| Date: 28/01/2022 |
Work in progress | 37% Completed
brick masonry work in progress
| Idukki QCDL - AE |
| Date: 24/01/2022 |
Work in progress | 37% Completed
brick work masonry started
| Idukki QCDL - AE |
| Date: 22/01/2022 |
Work in progress | 35% Completed
plinth beam concrete completed .
| Idukki QCDL - AE |
| Date: 21/01/2022 |
Work in progress | 33% Completed
Plinth bean centering and shuttering work in progress.
| Idukki QCDL - AE |
| Date: 20/01/2022 |
Work in progress | 33% Completed
RR work finished. Plinth beam work started.
| Idukki QCDL - AE |
| Date: 19/01/2022 |
Work in progress | 33% Completed
RR work of building basement in progress.
| Idukki QCDL - AE |
| Date: 18/01/2022 |
Work in progress | 33% Completed
RR work of building basement started.
| Idukki QCDL - AE |
| Date: 17/01/2022 |
Work in progress | 32% Completed
PCC for building basement finished.
| Idukki QCDL - AE |
| Date: 15/01/2022 |
Work in progress | 30% Completed
short Column work -concreting started.
| Idukki QCDL - AE |
| Date: 14/01/2022 |
Work in progress | 30% Completed
RR work of retaining wall completed .Building column footing work completed .
| Idukki QCDL - AE |
| Date: 13/01/2022 |
Work in progress | 27% Completed
RR work of Retaining wall 80% completed .Colum work in progress.
| Idukki QCDL - AE |
| Date: 12/01/2022 |
Work in progress | 26% Completed
6 column footing concrete completed .RR masonry work of retaining wall in progress .
| Idukki QCDL - AE |
| Date: 11/01/2022 |
Work in progress | 25% Completed
RR work of retaining wall in progress .Column footing work in progress.
| Idukki QCDL - AE |
| Date: 10/01/2022 |
Work in progress | 22% Completed
PCC for column footing completed. RR masonry work for retaining wall in progress.
| Idukki QCDL - AE |
| Date: 08/01/2022 |
Work in progress | 22% Completed
PCC for column footing in progress. .RR work of retaining wall in progress.
| Idukki QCDL - AE |
| Date: 07/01/2022 |
| Idukki QCDL - AE |
| Date: 06/01/2022 |
| Idukki QCDL - AE |
| Date: 05/01/2022 |
Work in progress | 16% Completed
Casting of 2nd RCC intermediate belt (15cm) above RR masonry started .
| Idukki QCDL - AE |
| Date: 04/01/2022 |
Work in progress | 15% Completed
1.5 m height Random rubble masonry work for retaining wall above the RCC belt completed
| Idukki QCDL - AE |
| Date: 31/12/2021 |
Work in progress | 10% Completed
Random rubble masonry work for retaining wall above RCC belt going on
| Idukki QCDL - AE |
| Date: 27/12/2021 |
Work in progress | 8% Completed
Casting of intermediate RCC belt for retaining wall started
| Idukki QCDL - AE |
| Date: 23/12/2021 |
Work in progress | 7% Completed
Random rubble masonry work for retaining wall started on 23/12/21
| Idukki QCDL - AE |
| Date: 22/12/2021 |
Work in progress | 5% Completed
PCC work for Retaining wall started.
| Idukki QCDL - AE |
| Date: 20/12/2021 |
Work in progress | 4% Completed
Earth work for retaining wall completed.
| Idukki QCDL - AE |
| Date: 18/12/2021 |
Work in progress | 3% Completed
Earth work excavation for retaining wall going on
| Idukki QCDL - AE |
| Date: 14/12/2021 |
Work in progress | 2% Completed
Earth work excavation for retaining wall started .
| Idukki QCDL - AE |
| Date: 10/12/2021 |
Work in progress | 1% Completed
Site clearing works commenced,building material supply started.