| Mattannur WS Sn |
| Date: 04/06/2026 |
Work in progress | 47% Completed
valiyannur nayattupara road restoration work is in progress
| Mattannur WS Sn |
| Date: 21/04/2026 |
Work in progress | 16% Completed
Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor.
| Mattannur WS Sn |
| Date: 13/04/2026 |
Work in progress | 16% Completed
Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor.
| Mattannur WS Sn |
| Date: 04/04/2026 |
Work in progress | 16% Completed
Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor.
| Mattannur WS Sn |
| Date: 31/03/2026 |
Work in progress | 16% Completed
Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor.
| Mattannur WS Sn |
| Date: 18/03/2026 |
Work in progress | 16% Completed
Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor.
| Mattannur WS Sn |
| Date: 09/03/2026 |
Work in progress | 16% Completed
Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor.
| Mattannur WS Sn |
| Date: 27/02/2026 |
Work in progress | 16% Completed
Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor.
| Mattannur WS Sn |
| Date: 17/02/2026 |
Work in progress | 16% Completed
Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor.
| Mattannur WS Sn |
| Date: 04/02/2026 |
Work in progress | 16% Completed
Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor.
| Mattannur WS Sn |
| Date: 27/01/2026 |
Work in progress | 16% Completed
Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor.
| Mattannur WS Sn |
| Date: 16/01/2026 |
Work in progress | 16% Completed
Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor.
| Mattannur WS Sn |
| Date: 08/01/2026 |
Work in progress | 16% Completed
Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor.
| Mattannur WS Sn |
| Date: 06/01/2026 |
Work in progress | 16% Completed
Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor.
| Mattannur WS Sn |
| Date: 30/12/2025 |
Work in progress | 16% Completed
Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor.
| Mattannur WS Sn |
| Date: 29/12/2025 |
Work in progress | 16% Completed
Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor.
| Mattannur WS Sn |
| Date: 27/12/2025 |
Work in progress | 16% Completed
Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor.
| Mattannur WS Sn |
| Date: 26/12/2025 |
Work in progress | 16% Completed
Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor.
| Mattannur WS Sn |
| Date: 23/12/2025 |
Work in progress | 16% Completed
Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor.
| Mattannur WS Sn |
| Date: 22/12/2025 |
Work in progress | 6% Completed
Work delayed due to heavy rain,not restarted yet
| Mattannur WS Sn |
| Date: 04/12/2025 |
Work in progress | 6% Completed
Work delayed due to heavy rain,not restarted yet
| Mattannur WS Sn |
| Date: 25/11/2025 |
Work in progress | 6% Completed
Work delayed due to heavy rain,not restarted yet
| Mattannur WS Sn |
| Date: 18/11/2025 |
Work in progress | 6% Completed
Work delayed due to heavy rain,not restarted yet
| Mattannur WS Sn |
| Date: 14/11/2025 |
Work in progress | 6% Completed
Work delayed due to heavy rain,not restarted yet
| Mattannur WS Sn |
| Date: 05/11/2025 |
Work in progress | 6% Completed
Work delayed due to heavy rain, not restarted yet
| Mattannur WS Sn |
| Date: 15/10/2025 |
Work in progress | 6% Completed
Work delayed due to heavy rain,not restarted yet
| Mattannur WS Sn |
| Date: 03/10/2025 |
Work in progress | 6% Completed
Work delayed due to heavy rain, not restarted yet
| Mattannur WS Sn |
| Date: 22/09/2025 |
Work in progress | 6% Completed
Work delayed due to heavy rain,not restarted yet
| Mattannur WS Sn |
| Date: 12/09/2025 |
Work in progress | 4% Completed
Work delayed due to heavy rain.Not restarted yet
| Mattannur WS Sn |
| Date: 19/08/2025 |
Work in progress | 4% Completed
work delayed due to heavy rain
| Mattannur WS Sn |
| Date: 31/07/2025 |
Work in progress | 4% Completed
work delayed due to heavy rain
| Mattannur WS Sn |
| Date: 21/07/2025 |
Work in progress | 4% Completed
work delayed due to heavy rain
| Mattannur WS Sn |
| Date: 30/06/2025 |
Work in progress | 4% Completed
work delayed due to heavy rain
| Mattannur WS Sn |
| Date: 18/06/2025 |
Work in progress | 4% Completed
work delayed due to heavy rain
| Mattannur WS Sn |
| Date: 14/05/2025 |
Work in progress | 3% Completed
GSB Spreading work started
| Mattannur WS Sn |
| Date: 16/04/2025 |
Work in progress | 3% Completed
GSB Spreading work started
| Mattannur WS Sn |
| Date: 01/04/2025 |
Work in progress | 3% Completed
GSB Spreading work started
| Mattannur WS Sn |
| Date: 16/03/2025 |
Work in progress | 3% Completed
GSB Spreading work started
| Mattannur WS Sn |
| Date: 07/03/2025 |
Work in progress | 1% Completed
Earth work started in chola- Nidukulam road
| Mattannur WS Sn |
| Date: 25/02/2025 |
Work in progress | 1% Completed
Earth work started in chola- Nidukulam road
| Mattannur WS Sn |
| Date: 11/02/2025 |
Work in progress | 1% Completed
Earth work started in chola- Nidukulam road
| Mattannur WS Sn |
| Date: 28/01/2025 |
Work in progress | 1% Completed
Earth work started in chola- Nidukulam road
| Mattannur WS Sn |
| Date: 20/01/2025 |
Work in progress | 1% Completed
Earth work started in chola- Nidukulam road
| Mattannur WS Sn |
| Date: 12/01/2025 |
Work in progress | 1% Completed
Earth work started in chola- Nidukulam road
| Mattannur WS Sn |
| Date: 06/01/2025 |
Work in progress | 1% Completed
Earth work started in chola- Nidukulam road
| Mattannur WS Sn |
| Date: 01/01/2025 |
Work in progress | 1% Completed
Earth work started in chola- Nidukulam road
| Mattannur WS Sn |
| Date: 26/12/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 18/12/2024 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 12/12/2024 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 03/12/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 25/11/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 18/11/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 11/11/2024 |
Work has started | 0% Completed
work not started -
| Mattannur WS Sn |
| Date: 04/11/2024 |
Work has started | 0% Completed
work not started -
| Mattannur WS Sn |
| Date: 28/10/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 21/10/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 16/10/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 03/10/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 27/09/2024 |
Work has started | 0% Completed
work not started