Sasthamcotta WS Sn 1 - AE
Date: 25/01/2023

Work has been completed | 100% Completed

Supply of 10 HPM (2 Nos) Tube well submersible spare pump set - Work 100 % completed

Sasthamcotta WS Sn 1 - AE
Date: 24/01/2023

Work in progress | 5% Completed

Work on progress.

Sasthamcotta WS Sn 1 - AE
Date: 21/01/2023

Work in progress | 5% Completed

Agreement executed on 18/01/2023. Work on progress

Sasthamcotta WS Sn 1 - AE
Date: 18/01/2023

Work in progress | 5% Completed

Agreement executed on 18/01/2023

Sasthamcotta WS Sn 1 - AE
Date: 09/01/2023

Work in progress | 0% Completed

Work order issued.

Sasthamcotta WS Sn 1 - AE
Date: 03/01/2023

Work in progress | 0% Completed

Work tendered.

Sasthamcotta WS Sub-Dn - AEE
Date: 21/12/2022

Work has started | 0% Completed

Tendered