| Kozhikode Dist 1 Sn 2 - AE |
| Date: 20/06/2025 |
Work in progress | 81% Completed
1500 M laying completed
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 28/04/2025 |
Work in progress | 81% Completed
1500 M laying completed.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 18/03/2025 |
Work in progress | 80% Completed
1500 M laying completed.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 12/02/2025 |
Work in progress | 75% Completed
1500 M laying completed.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 24/01/2025 |
Work in progress | 71% Completed
1500 M laying completed.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 16/01/2025 |
Work in progress | 70% Completed
1500 M laying completed.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 07/12/2024 |
Work in progress | 45% Completed
Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 19/11/2024 |
Work in progress | 44% Completed
Permission granted but site not handed over. PWD informed that work should be started only after getting the AS for maintance.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 06/11/2024 |
Work in progress | 44% Completed
Road cutting permission received
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 26/10/2024 |
Work in progress | 44% Completed
Road cutting permission pending.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 22/10/2024 |
Work in progress | 44% Completed
Road cutting permission pending.
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 44% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 42% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 35% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 01/03/2024 |
Work in progress | 33% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 30% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 27% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 11/01/2024 |
Work in progress | 25% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work has started | 0% Completed
Work not started
| Kozhikode PH Dn EE |
| Date: 28/11/2023 |
Work has started | 0% Completed
Work not started
| Kozhikode PH Dn EE |
| Date: 09/11/2023 |
Work has started | 0% Completed
Work not started
| Kozhikode PH Dn EE |
| Date: 27/10/2023 |
Work has started | 0% Completed
Work not started
| Kozhikode PH Dn EE |
| Date: 17/10/2023 |
Work in progress | 0% Completed
Work not started
| Kozhikode PH Dn EE |
| Date: 14/09/2023 |
Work has started | 0% Completed
Work not started
| Kozhikode PH Dn EE |
| Date: 05/09/2023 |
Work has started | 0% Completed
Work not started
| Kozhikode PH Dn EE |
| Date: 16/08/2023 |
Work has started | 0% Completed
Site Handed Over
| Kozhikode PH Dn EE |
| Date: 07/08/2023 |
Work has started | 0% Completed
Site Handed Over
| Kozhikode PH Dn EE |
| Date: 24/07/2023 |
Work has started | 0% Completed
Site Handed Over
| Kozhikode PH Dn EE |
| Date: 12/07/2023 |
Work has started | 0% Completed
Tender Accepted
| Kozhikode PH Dn EE |
| Date: 30/06/2023 |
Work has started | 0% Completed
Tender Accepted
| Kozhikode PH Dn EE |
| Date: 20/06/2023 |
Work has started | 0% Completed
Tender Accepted
| Kozhikode PH Dn EE |
| Date: 13/06/2023 |
Work has started | 0% Completed
Tender Accepted
| Kozhikode PH Dn EE |
| Date: 05/06/2023 |
Work in progress | 1% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 01/06/2023 |
Work in progress | 1% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 26/05/2023 |
Work in progress | 1% Completed
Agreement Executed