Sasthamcotta WS Sn 1 - AE
Date: 14/12/2022

Work has been completed | 100% Completed

100% work completed and final bill submitted

Sasthamcotta WS Sn 1 - AE
Date: 13/12/2022

Work has been completed | 100% Completed

xtension of distribution line with 63 mm PVC CL3 pipe at various places of ward no.12 in Kunnathoor Grama Panchayath - work 100 % completed

Sasthamcotta WS Sn 1 - AE
Date: 06/12/2022

Work in progress | 92% Completed

63 mm PVC pipe line laying work in various wards - work on progress. Out of 750 m laying work 750 m work completed. Balance work is on progress

Sasthamcotta WS Sn 1 - AE
Date: 30/11/2022

Work in progress | 92% Completed

63 mm PVC pipe line laying work in various wards - work on progress. Out of 750 m laying work 670 m work completed. Balance work is on progress

Sasthamcotta WS Sn 1 - AE
Date: 28/11/2022

Work in progress | 92% Completed

63 mm PVC pipe line laying work in various wards - work on progress. Out of 750 m laying work 670 m work completed. Balance work is on progress

Sasthamcotta WS Sn 1 - AE
Date: 26/11/2022

Work in progress | 92% Completed

63 mm PVC pipe line laying work in various wards - work on progress. Out of 750 m laying work 670 m work completed. Balance work is on progress

Sasthamcotta WS Sn 1 - AE
Date: 24/11/2022

Work in progress | 90% Completed

63 mm PVC pipe line laying work in various wards - work on progress. Out of 750 m laying work 670 m work completed. Balance work is on progress.

Sasthamcotta WS Sn 1 - AE
Date: 21/11/2022

Work in progress | 90% Completed

63 mm PVC pipe line laying work in various wards - work on progress. Out of 750 m laying work 670 m work completed

Sasthamcotta WS Sn 1 - AE
Date: 16/11/2022

Work in progress | 85% Completed

63 mm PVC pipe line laying work in various wards - work on progress. Out of 750 m laying work 650 m work completed

Sasthamcotta WS Sn 1 - AE
Date: 14/11/2022

Work in progress | 80% Completed

63 mm PVC pipe line laying work in various wards - work on progress. Out of 750 m laying work 550 m work completed.

Sasthamcotta WS Sn 1 - AE
Date: 12/11/2022

Work in progress | 50% Completed

63 mm PVC pipe line laying work in various wards - work on progress. Out of 750 m laying work 250 m work completed.

Sasthamcotta WS Sn 1 - AE
Date: 10/11/2022

Work in progress | 10% Completed

63 mm PVC pipe line laying work started.60 m laying work completed

Attached images

img img

Sasthamcotta WS Sn 1 - AE
Date: 09/11/2022

Work in progress | 10% Completed

63 mm PVC pipe line laying work started.60 m laying work completed

Sasthamcotta WS Sn 1 - AE
Date: 08/11/2022

Work in progress | 1% Completed

Agreement executed, steps has been taken for pipe testing

Sasthamcotta WS Sn 1 - AE
Date: 02/11/2022

Work in progress | 1% Completed

Agreement executed, steps has been taken for pipe testing

Sasthamcotta WS Sn 1 - AE
Date: 30/10/2022

Work in progress | 1% Completed

Agreement executed, steps has been taken for pipe testing

Sasthamcotta WS Sn 1 - AE
Date: 24/10/2022

Work in progress | 1% Completed

Agreement executed, steps has been taken for pipe testing

Sasthamcotta WS Sn 1 - AE
Date: 19/10/2022

Work has started | 0% Completed

Agreement executed, steps has been taken for pipe testing

Sasthamcotta WS Sn 1 - AE
Date: 14/10/2022

Work has started | 0% Completed

Agreement executed, Work not started

Sasthamcotta WS Sn 1 - AE
Date: 13/10/2022

Work has started | 0% Completed

Agreement executed, Work not started