| Muvattupuzha PH Dn EE |
| Date: 16/04/2022 |
Work has been completed | 100% Completed
completed
| Muvattupuzha PH Dn EE |
| Date: 11/04/2022 |
Work has been completed | 100% Completed
completed
| Muvattupuzha PH Dn EE |
| Date: 06/03/2022 |
Work has been completed | 100% Completed
completed
| Muvattupuzha PH Dn EE |
| Date: 27/02/2022 |
Work has been completed | 100% Completed
completed
| Muvattupuzha PH Dn EE |
| Date: 18/02/2022 |
Work in progress | 98% Completed
98%completed
| Muvattupuzha PH Dn EE |
| Date: 02/02/2022 |
Work in progress | 92% Completed
FHTC in progress
| Muvattupuzha PH Dn EE |
| Date: 26/01/2022 |
Work in progress | 92% Completed
fhtc work in progress
| Muvattupuzha PH Dn EE |
| Date: 20/01/2022 |
Work in progress | 92% Completed
2036 connections given
| Muvattupuzha PH Dn EE |
| Date: 11/01/2022 |
Work in progress | 82% Completed
FHTC work in progress
| Muvattupuzha PH Dn EE |
| Date: 04/01/2022 |
Work in progress | 82% Completed
82% completed
| Muvattupuzha PH Dn EE |
| Date: 28/12/2021 |
Work in progress | 81% Completed
FHTC in progress
| Muvattupuzha PH Dn EE |
| Date: 21/12/2021 |
Work in progress | 81% Completed
Pipe line extension in progress
| Muvattupuzha PH Dn EE |
| Date: 15/12/2021 |
Work in progress | 80% Completed
pipe laying in progress
| Muvattupuzha PH Dn EE |
| Date: 07/12/2021 |
Work in progress | 78% Completed
work in progress
| Muvattupuzha PH Dn EE |
| Date: 29/11/2021 |
Work in progress | 78% Completed
Pipe laying and connection in progress
| Muvattupuzha PH Dn EE |
| Date: 15/11/2021 |
Work in progress | 77% Completed
1696 connections given
| Muvattupuzha PH Dn EE |
| Date: 08/11/2021 |
Work in progress | 64% Completed
1422 connections given
| Muvattupuzha PH Dn EE |
| Date: 26/10/2021 |
Work in progress | 55% Completed
1220 connections given
| Muvattupuzha PH Dn EE |
| Date: 11/10/2021 |
Work in progress | 50% Completed
1130 connections given
| Muvattupuzha PH Dn EE |
| Date: 01/10/2021 |
Work in progress | 50% Completed
1100 connections out of 2200 connections given ,60 % pipe line extension and replacement completed
| Muvattupuzha PH Dn EE |
| Date: 28/09/2021 |
Work in progress | 50% Completed
1090 connections given
| Muvattupuzha PH Dn EE |
| Date: 12/09/2021 |
Work in progress | 47% Completed
work in progress
| Muvattupuzha PH Dn EE |
| Date: 05/09/2021 |
Work in progress | 47% Completed
1038 connections given
| Muvattupuzha PH Dn EE |
| Date: 31/08/2021 |
Work in progress | 46% Completed
1020 connections given
| Muvattupuzha PH Dn EE |
| Date: 24/08/2021 |
Work in progress | 46% Completed
Bill for 1014 connections submitted
| Muvattupuzha PH Dn EE |
| Date: 16/08/2021 |
Work in progress | 46% Completed
1014 connections given
| Muvattupuzha PH Dn EE |
| Date: 09/08/2021 |
Work in progress | 43% Completed
960 connections given
| Muvattupuzha PH Dn EE |
| Date: 03/08/2021 |
Work in progress | 41% Completed
920 connections given
| Muvattupuzha PH Dn EE |
| Date: 29/07/2021 |
Work in progress | 41% Completed
903 connections given
| Muvattupuzha PH Dn EE |
| Date: 23/07/2021 |
Work in progress | 38% Completed
855 connections given
| Muvattupuzha PH Dn EE |
| Date: 17/07/2021 |
Work in progress | 38% Completed
844 connections given
| Muvattupuzha PH Dn EE |
| Date: 10/07/2021 |
Work in progress | 38% Completed
834 connections given
| Muvattupuzha PH Dn EE |
| Date: 03/07/2021 |
Work in progress | 28% Completed
line extension and replacement is in progress
| Muvattupuzha PH Dn EE |
| Date: 27/06/2021 |
Work in progress | 28% Completed
line extension and replacement is in progress
| Muvattupuzha PH Dn EE |
| Date: 21/06/2021 |
Work in progress | 28% Completed
line extension and replacement is in progress
| Muvattupuzha PH Dn EE |
| Date: 15/06/2021 |
Work in progress | 28% Completed
606 connections given. line extn in progress
| Muvattupuzha PH Dn EE |
| Date: 09/06/2021 |
Work in progress | 28% Completed
line extension and replacement work in progress
| Muvattupuzha PH Dn EE |
| Date: 04/06/2021 |
Work in progress | 28% Completed
out of 15 km 5 km pipe line laid .out of 2200 connections 606 connections given
| Muvattupuzha PH Dn EE |
| Date: 03/06/2021 |
Work in progress | 28% Completed
total 606 connections given and 504 connections bill submitted and balance under preparation
| Muvattupuzha PH Dn EE |
| Date: 31/05/2021 |
Work in progress | 21% Completed
line extn work in progress
| Muvattupuzha PH Dn EE |
| Date: 25/05/2021 |
Work in progress | 21% Completed
line extension and replacement work in progress
| Muvattupuzha PH Dn EE |
| Date: 17/05/2021 |
Work in progress | 21% Completed
line extension and replacement work in progress
| Muvattupuzha PH Dn EE |
| Date: 14/05/2021 |
Work in progress | 21% Completed
line extension and replacement work in progress
| Muvattupuzha PH Dn EE |
| Date: 10/05/2021 |
Work in progress | 21% Completed
line extension and replacement work in progress
| Muvattupuzha PH Dn EE |
| Date: 03/05/2021 |
Work in progress | 21% Completed
line extension is in progress
| Muvattupuzha PH Dn EE |
| Date: 27/04/2021 |
Work in progress | 21% Completed
464 connections given
| Muvattupuzha PH Dn EE |
| Date: 12/04/2021 |
Work in progress | 13% Completed
336 connections given
| Muvattupuzha PH Dn EE |
| Date: 07/04/2021 |
Work in progress | 13% Completed
pipeline extension is in progress
| Muvattupuzha PH Dn EE |
| Date: 29/03/2021 |
Work in progress | 13% Completed
bill submitted for 298 connections Total
| Muvattupuzha PH Dn EE |
| Date: 22/03/2021 |
Work in progress | 13% Completed
300 connections given
| Muvattupuzha PH Dn EE |
| Date: 16/03/2021 |
Work in progress | 12% Completed
line extension going on
| Muvattupuzha PH Dn EE |
| Date: 11/03/2021 |
Work in progress | 12% Completed
275 connections given
| Muvattupuzha PH Dn EE |
| Date: 05/03/2021 |
Work in progress | 11% Completed
245 connections given
| Muvattupuzha PH Dn EE |
| Date: 01/03/2021 |
Work in progress | 10% Completed
228 connections given
| Muvattupuzha PH Dn EE |
| Date: 26/02/2021 |
Work in progress | 10% Completed
211 connections given
| Muvattupuzha PH Dn EE |
| Date: 22/02/2021 |
Work in progress | 7% Completed
170connections given
| Muvattupuzha PH Dn EE |
| Date: 15/02/2021 |
Work in progress | 6% Completed
128 connections given
| Muvattupuzha PH Dn EE |
| Date: 09/02/2021 |
Work in progress | 5% Completed
107 connections given
| Muvattupuzha PH Dn EE |
| Date: 03/02/2021 |
Work in progress | 4% Completed
84 connections given
| Muvattupuzha PH Dn EE |
| Date: 27/01/2021 |
Work in progress | 2% Completed
52 connections given