| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 21/08/2024 |
Work has been completed | 100% Completed
completed
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 96% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 95% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 92% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 90% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work has started | 0% Completed
Work Not Yet Started
| Kozhikode PH Dn EE |
| Date: 11/01/2024 |
Work has started | 0% Completed
Work Not Yet Started
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work has started | 0% Completed
Work Not Yet Started
| Kozhikode PH Dn EE |
| Date: 29/11/2023 |
Work has started | 0% Completed
For Join Inspection
| Kozhikode PH Dn EE |
| Date: 30/10/2023 |
Work has started | 0% Completed
Site Handed Over