Kottayam Proj Dn AE4 |
Date: 01/07/2024 |
Work in progress | 60% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 30/06/2024 |
Work in progress | 60% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 29/06/2024 |
Work in progress | 60% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 28/06/2024 |
Work in progress | 60% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 27/06/2024 |
Work in progress | 60% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 26/06/2024 |
Work in progress | 60% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 25/06/2024 |
Work in progress | 60% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 24/06/2024 |
Work in progress | 60% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 23/06/2024 |
Work in progress | 60% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 22/06/2024 |
Work in progress | 60% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 21/06/2024 |
Work in progress | 60% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 20/06/2024 |
Work in progress | 60% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 19/06/2024 |
Work in progress | 60% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 18/06/2024 |
Work in progress | 60% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 17/06/2024 |
Work in progress | 60% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 16/06/2024 |
Work in progress | 60% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 15/06/2024 |
Work in progress | 58% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 14/06/2024 |
Work in progress | 58% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 13/06/2024 |
Work in progress | 57% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 12/06/2024 |
Work in progress | 54% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 11/06/2024 |
Work in progress | 54% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 10/06/2024 |
Work in progress | 53% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 09/06/2024 |
Work in progress | 51% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 08/06/2024 |
Work in progress | 51% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 07/06/2024 |
Work in progress | 50% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 06/06/2024 |
Work in progress | 49% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 05/06/2024 |
Work in progress | 48% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 04/06/2024 |
Work in progress | 46% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 03/06/2024 |
Work in progress | 44% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 02/06/2024 |
Work in progress | 40% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 01/06/2024 |
Work in progress | 39% Completed
350 mm DI K9-1950 m supplied and billed. Work in progress. Need permission for Ayarkunnam Mattakava PWD road. (550m). Road restoration work in progress.
Kottayam Proj Dn AE4 |
Date: 31/05/2024 |
Work in progress | 38% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 30/05/2024 |
Work in progress | 33% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 29/05/2024 |
Work in progress | 33% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 28/05/2024 |
Work in progress | 30% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 27/05/2024 |
Work in progress | 27% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 26/05/2024 |
Work in progress | 23% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 25/05/2024 |
Work in progress | 20% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 24/05/2024 |
Work in progress | 18% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 23/05/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 22/05/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 21/05/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 20/05/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 19/05/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 18/05/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 17/05/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 16/05/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 15/05/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 14/05/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 13/05/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 12/05/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 11/05/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 10/05/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 09/05/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 08/05/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 07/05/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 06/05/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 05/04/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 04/04/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 03/04/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 02/04/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 01/04/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 31/03/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 30/03/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 29/03/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 28/03/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 27/03/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 26/03/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 25/03/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 24/03/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 23/03/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 22/03/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 21/03/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 20/03/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 19/03/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 18/03/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 17/03/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 16/03/2024 |
Work in progress | 14% Completed
pipe line work
Kottayam Proj Dn AE4 |
Date: 15/03/2024 |
Work in progress | 14% Completed
pipe line work