| Mattannur WS Sn |
| Date: 01/06/2026 |
Work has been completed | 100% Completed
work completed and final bill submitted
| Mattannur WS Sn |
| Date: 21/04/2026 |
Work in progress | 25% Completed
road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on )
| Mattannur WS Sn |
| Date: 13/04/2026 |
Work in progress | 25% Completed
road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on )
| Mattannur WS Sn |
| Date: 04/04/2026 |
Work in progress | 25% Completed
road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on )
| Mattannur WS Sn |
| Date: 26/03/2026 |
Work in progress | 25% Completed
road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on )
| Mattannur WS Sn |
| Date: 18/03/2026 |
Work in progress | 25% Completed
road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on )
| Mattannur WS Sn |
| Date: 09/03/2026 |
Work in progress | 25% Completed
road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on )
| Mattannur WS Sn |
| Date: 27/02/2026 |
Work in progress | 25% Completed
road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on )
| Mattannur WS Sn |
| Date: 17/02/2026 |
Work in progress | 25% Completed
road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on )
| Mattannur WS Sn |
| Date: 04/02/2026 |
Work in progress | 25% Completed
road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on )
| Mattannur WS Sn |
| Date: 27/01/2026 |
Work in progress | 25% Completed
road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on )
| Mattannur WS Sn |
| Date: 16/01/2026 |
Work in progress | 25% Completed
road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on )
| Mattannur WS Sn |
| Date: 09/01/2026 |
Work in progress | 25% Completed
road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on )
| Mattannur WS Sn |
| Date: 06/01/2026 |
Work in progress | 25% Completed
road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on )
| Mattannur WS Sn |
| Date: 29/12/2025 |
Work in progress | 25% Completed
road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on )
| Mattannur WS Sn |
| Date: 20/12/2025 |
Work in progress | 25% Completed
road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on )
| Mattannur WS Sn |
| Date: 04/12/2025 |
Work in progress | 20% Completed
Work not restarted
| Mattannur WS Sn |
| Date: 25/11/2025 |
Work in progress | 20% Completed
Work not restarted
| Mattannur WS Sn |
| Date: 14/11/2025 |
Work in progress | 20% Completed
WORK HELD UP DUE TO HEAVY RAIN
| Mattannur WS Sn |
| Date: 05/11/2025 |
Work in progress | 20% Completed
WORK HELD UP DUE TO HEAVY RAIN
| Mattannur WS Sn |
| Date: 15/10/2025 |
Work in progress | 20% Completed
WORK HELD UP DUE TO HEAVY RAIN
| Mattannur WS Sn |
| Date: 03/10/2025 |
Work in progress | 20% Completed
WORK HELD UP DUE TO HEAVY RAIN
| Mattannur WS Sn |
| Date: 22/09/2025 |
Work in progress | 20% Completed
WORK HELD UP DUE TO HEAVY RAIN
| Mattannur WS Sn |
| Date: 19/08/2025 |
Work in progress | 20% Completed
800mtr road restoration work completed
| Mattannur WS Sn |
| Date: 31/07/2025 |
Work in progress | 20% Completed
800mtr road restoration work completed,
| Mattannur WS Sn |
| Date: 21/07/2025 |
Work in progress | 20% Completed
800mtr road restoration work completed
| Mattannur WS Sn |
| Date: 30/06/2025 |
Work in progress | 20% Completed
800mtr road restoration work completed
| Mattannur WS Sn |
| Date: 18/06/2025 |
Work in progress | 20% Completed
800mtr road restoration work completed
| Mattannur WS Sn |
| Date: 16/06/2025 |
Work in progress | 20% Completed
800m road restoration work ongoing.
| Mattannur WS Sn |
| Date: 14/05/2025 |
Work in progress | 20% Completed
800m road restoration work ongoing.
| Mattannur WS Sn |
| Date: 30/04/2025 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 16/04/2025 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 01/04/2025 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 16/03/2025 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 07/03/2025 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 25/02/2025 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 11/02/2025 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 28/01/2025 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 20/01/2025 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 12/01/2025 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 06/01/2025 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 01/01/2025 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 26/12/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 18/12/2024 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 12/12/2024 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 03/12/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 25/11/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 18/11/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 11/11/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 04/11/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 28/10/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 21/10/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 16/10/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 03/10/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 27/09/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 17/09/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 05/09/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 28/08/2024 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 21/08/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 12/08/2024 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 06/08/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 31/07/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 22/07/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 17/07/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 10/07/2024 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 25/06/2024 |
Work has started | 0% Completed
Agreement executed on 16.03.2024 and site handed over on 21.03.2024.
| Mattannur WS Sn |
| Date: 18/06/2024 |
Work has started | 0% Completed
Agreement executed on 16.03.2024 and site handed over on 21.03.2024.
| Kannur PH Dn EE |
| Date: 04/06/2024 |
Work in progress | 0% Completed
Agreement executed on 16.03.2024 and site handed over on 21.03.2024.
| Kannur PH Dn EE |
| Date: 25/05/2024 |
Work in progress | 0% Completed
Agreement executed on 16.03.2024 and site handed over on 21.03.2024.
| Kannur PH Dn EE |
| Date: 17/05/2024 |
Work in progress | 0% Completed
Agreement executed on 16.03.2024 and site handed over on 21.03.2024.
| Kannur PH Dn EE |
| Date: 03/05/2024 |
Work has started | 0% Completed
Agreement executed on 16.03.2024 and site handed over on 21.03.2024.
| Kannur PH Dn EE |
| Date: 23/04/2024 |
Work in progress | 0% Completed
Agreement executed on 16.03.2024 and site handed over on 21.03.2024.
| Kannur PH Dn EE |
| Date: 15/04/2024 |
Work in progress | 0% Completed
Agreement executed on 16.03.2024 and site handed over on 21.03.2024.
| Kannur PH Dn EE |
| Date: 03/04/2024 |
Work in progress | 0% Completed
Agreement executed on 16.03.2024 and site handed over on 21.03.2024.
| Kannur PH Dn EE |
| Date: 26/03/2024 |
Work has started | 0% Completed
Agreement executed on 16.03.2024 and site handed over on 21.03.2024.