Keezhallur PH Sn AE
Date: 13/07/2026

Work in progress | 84% Completed

Clear water pipes and air pipe fixing work completed in filter bed 1

Keezhallur PH Sn AE
Date: 06/07/2026

Work in progress | 84% Completed

Clear water pipe and air pipes are fitted in filter bed no.1

Keezhallur PH Sn AE
Date: 26/06/2026

Work in progress | 80% Completed

Tile fixing work completed in filter bed No.1

Keezhallur PH Sn AE
Date: 17/06/2026

Work in progress | 80% Completed

Tile fixing work progressing

Keezhallur PH Sn AE
Date: 11/06/2026

Work in progress | 80% Completed

Plastering work progressing

Keezhallur PH Sn AE
Date: 02/06/2026

Work in progress | 80% Completed

Filter Bed No.1 - Filter sand removing process completed.

Keezhallur PH Sn AE
Date: 22/05/2026

Work in progress | 79% Completed

Filter Bed No.1- Filter sand removing process started

Keezhallur PH Sn AE
Date: 12/05/2026

Work in progress | 79% Completed

Filter bed 3 - packing work completed

Keezhallur PH Sn AE
Date: 02/05/2026

Work in progress | 79% Completed

Filter bed 3 - packing work completed

Keezhallur PH Sn AE
Date: 25/04/2026

Work in progress | 79% Completed

Filter bed 3 - packing work completed

Keezhallur PH Sn AE
Date: 17/04/2026

Work in progress | 79% Completed

Filter bed 3 - packing work completed

Keezhallur PH Sn AE
Date: 08/04/2026

Work in progress | 79% Completed

Filter bed packing work completed

Keezhallur PH Sn AE
Date: 30/03/2026

Work in progress | 78% Completed

Sand shortage supply order given

Keezhallur PH Sn AE
Date: 27/03/2026

Work in progress | 78% Completed

filter bed packing chamber 1 completed

Keezhallur PH Sn AE
Date: 16/03/2026

Work in progress | 78% Completed

filter bed packing progressing

Keezhallur PH Sn AE
Date: 06/03/2026

Work in progress | 78% Completed

Tile fixing work completed in filter bed 3

Keezhallur PH Sn AE
Date: 27/02/2026

Work in progress | 78% Completed

Tile fixing work completed in filter bed 3

Keezhallur PH Sn AE
Date: 18/02/2026

Work in progress | 78% Completed

Tile fixing work progressing in filter bed 3

Keezhallur PH Sn AE
Date: 09/02/2026

Work in progress | 78% Completed

Tile fixing work progressing in filter bed 3

Keezhallur PH Sn AE
Date: 28/01/2026

Work in progress | 78% Completed

Tile fixing work in filter bed 3

Keezhallur PH Sn AE
Date: 19/01/2026

Work in progress | 78% Completed

Clear water pipe and air pipes are fitted filter no.3

Keezhallur PH Sn AE
Date: 14/01/2026

Work in progress | 78% Completed

Clear water pipe and air pipes are fitted filter no.3

Keezhallur PH Sn AE
Date: 08/01/2026

Work in progress | 78% Completed

Clear water pipe and air pipes are fitted

Keezhallur PH Sn AE
Date: 29/12/2025

Work in progress | 78% Completed

Thrust block concrete completed for chamber 1 - Filter bed 3

Keezhallur PH Sn AE
Date: 22/12/2025

Work in progress | 78% Completed

Filter bed no.3- Pipe fitting work

Keezhallur PH Sn AE
Date: 12/12/2025

Work in progress | 78% Completed

Filter bed no.3- New Pipe fitting work

Keezhallur PH Sn AE
Date: 05/12/2025

Work in progress | 78% Completed

Filter Bed No.3- cleaning work

Keezhallur PH Sn AE
Date: 28/11/2025

Work in progress | 78% Completed

Filter Bed No.3 Air pipes changing

Keezhallur PH Sn AE
Date: 21/11/2025

Work in progress | 78% Completed

Filter Bed No.3 - Filter sand removing process completed.

Attached images

img

Keezhallur PH Sn AE
Date: 14/11/2025

Work in progress | 78% Completed

Filter Bed No.3- Filter sand removing process started

Attached images

img img

Keezhallur PH Sn AE
Date: 06/11/2025

Work in progress | 78% Completed

Filter sand not supplied, supply order given

Keezhallur PH Sn AE
Date: 30/10/2025

Work in progress | 78% Completed

Filter sand not supplied, supply order given

Keezhallur PH Sn AE
Date: 23/10/2025

Work in progress | 78% Completed

Filter sand not supplied, supply order given

Keezhallur PH Sn AE
Date: 13/10/2025

Work in progress | 78% Completed

Supply order given filter sand to be supplied

Keezhallur PH Sn AE
Date: 06/10/2025

Work in progress | 78% Completed

Supply order given filter sand to be supplied

Keezhallur PH Sn AE
Date: 29/09/2025

Work in progress | 78% Completed

Supply order given filter sand to be supplied

Keezhallur PH Sn AE
Date: 24/09/2025

Work in progress | 78% Completed

Valve fixing work in progress

Keezhallur PH Sn AE
Date: 20/09/2025

Work in progress | 78% Completed

Valve fixing work in progress.

Keezhallur PH Sn AE
Date: 18/08/2025

Work in progress | 78% Completed

Pebbles supplied

Keezhallur PH Sn AE
Date: 06/08/2025

Work in progress | 78% Completed

Valve fixing work .

Keezhallur PH Sn AE
Date: 28/07/2025

Work in progress | 78% Completed

Valve fixing work in progress.

Keezhallur PH Sn AE
Date: 14/07/2025

Work in progress | 75% Completed

Repairing of compound wall in progress.

Keezhallur PH Sn AE
Date: 27/06/2025

Work in progress | 74% Completed

Repairing of compound wall in progress.

Keezhallur PH Sn AE
Date: 17/06/2025

Work in progress | 73% Completed

Repairing of compound wall in progress.

Keezhallur PH Sn AE
Date: 31/05/2025

Work in progress | 70% Completed

Repairing of clarifloculator bridge completed .

Keezhallur PH Sn AE
Date: 22/04/2025

Work in progress | 51% Completed

Water proofing work completed.Filter has to be replaced.

Keezhallur PH Sn AE
Date: 08/04/2025

Work in progress | 50% Completed

Water proofing work on progress.

Keezhallur PH Sn AE
Date: 01/04/2025

Work in progress | 44% Completed

Water proofing work on progress.

Keezhallur PH Sn AE
Date: 27/03/2025

Work in progress | 42% Completed

Water proofing work on progress.

Keezhallur PH Sn AE
Date: 19/03/2025

Work in progress | 42% Completed

Painting to be done.

Keezhallur PH Sn AE
Date: 05/03/2025

Work in progress | 40% Completed

Package V- clariflocculator bridge repairing works are going on.

Keezhallur PH Sn AE
Date: 18/02/2025

Work in progress | 40% Completed

Package V- clariflocculator bridge repairing works are going on.

Keezhallur PH Sn AE
Date: 10/02/2025

Work in progress | 40% Completed

Package V- clariflocculator bridge repairing works are going on.

Keezhallur PH Sn AE
Date: 31/01/2025

Work in progress | 40% Completed

Package V- clariflocculator bridge repairing works are going on.

Keezhallur PH Sn AE
Date: 22/01/2025

Work in progress | 40% Completed

Package V- clariflocculator bridge repairing works are going on.

Keezhallur PH Sn AE
Date: 03/01/2025

Work in progress | 31% Completed

Package V- clariflocculator bridge repairing works are going on.

Keezhallur PH Sn AE
Date: 16/12/2024

Work in progress | 29% Completed

Package V- clariflocculator bridge repairing works are going on.

Keezhallur PH Sn AE
Date: 05/12/2024

Work in progress | 25% Completed

Package V- clariflocculator bridge repairing works are going on.

Keezhallur PH Sn AE
Date: 13/11/2024

Work in progress | 22% Completed

Package V- sludge removal works are going on.

Keezhallur PH Sn AE
Date: 02/11/2024

Work in progress | 21% Completed

Package V- sludge removal works are going on.

Keezhallur PH Sn AE
Date: 26/10/2024

Work in progress | 20% Completed

Package V- electrification works are going on.

Keezhallur PH Sn AE
Date: 24/10/2024

Work in progress | 19% Completed

Package V- electrification works are going on.

Keezhallur PH Sn AE
Date: 15/10/2024

Work in progress | 17% Completed

Electrification works are going on

Keezhallur PH Sn AE
Date: 07/10/2024

Work in progress | 15% Completed

Installation of yard lights completed, Supply and Installation of Blower completed, roofing works completed, leak works of OHSR completed

Keezhallur PH Sn AE
Date: 26/09/2024

Work in progress | 14% Completed

leak works of OHSR is going on.

Keezhallur PH Sn AE
Date: 18/09/2024

Work in progress | 10% Completed

Package V-Supply and installation of blower completed and leak rectification works of OHSR is going on.

Keezhallur PH Sn AE
Date: 10/09/2024

Work in progress | 6% Completed

package V- roofing works completed, sludge removal works are going on.

Keezhallur PH Sn AE
Date: 03/09/2024

Work in progress | 6% Completed

package V- roofing works completed, sludge removal works are going on.

Keezhallur PH Sn AE
Date: 12/08/2024

Work in progress | 6% Completed

roofing works completed. sludge removal works are going on

Keezhallur PH Sn AE
Date: 07/08/2024

Work in progress | 4% Completed

Work started. roofing works are going on.

Keezhallur PH Sn AE
Date: 05/08/2024

Work in progress | 4% Completed

Work started. roofing works are going on.

Kannur PH Dn EE
Date: 24/07/2024

Work in progress | 4% Completed

Work started. roofing works are going on.