| Keezhallur PH Sn AE |
| Date: 13/07/2026 |
Work in progress | 84% Completed
Clear water pipes and air pipe fixing work completed in filter bed 1
| Keezhallur PH Sn AE |
| Date: 06/07/2026 |
Work in progress | 84% Completed
Clear water pipe and air pipes are fitted in filter bed no.1
| Keezhallur PH Sn AE |
| Date: 26/06/2026 |
Work in progress | 80% Completed
Tile fixing work completed in filter bed No.1
| Keezhallur PH Sn AE |
| Date: 17/06/2026 |
Work in progress | 80% Completed
Tile fixing work progressing
| Keezhallur PH Sn AE |
| Date: 11/06/2026 |
Work in progress | 80% Completed
Plastering work progressing
| Keezhallur PH Sn AE |
| Date: 02/06/2026 |
Work in progress | 80% Completed
Filter Bed No.1 - Filter sand removing process completed.
| Keezhallur PH Sn AE |
| Date: 22/05/2026 |
Work in progress | 79% Completed
Filter Bed No.1- Filter sand removing process started
| Keezhallur PH Sn AE |
| Date: 12/05/2026 |
Work in progress | 79% Completed
Filter bed 3 - packing work completed
| Keezhallur PH Sn AE |
| Date: 02/05/2026 |
Work in progress | 79% Completed
Filter bed 3 - packing work completed
| Keezhallur PH Sn AE |
| Date: 25/04/2026 |
Work in progress | 79% Completed
Filter bed 3 - packing work completed
| Keezhallur PH Sn AE |
| Date: 17/04/2026 |
Work in progress | 79% Completed
Filter bed 3 - packing work completed
| Keezhallur PH Sn AE |
| Date: 08/04/2026 |
Work in progress | 79% Completed
Filter bed packing work completed
| Keezhallur PH Sn AE |
| Date: 30/03/2026 |
Work in progress | 78% Completed
Sand shortage supply order given
| Keezhallur PH Sn AE |
| Date: 27/03/2026 |
Work in progress | 78% Completed
filter bed packing chamber 1 completed
| Keezhallur PH Sn AE |
| Date: 16/03/2026 |
Work in progress | 78% Completed
filter bed packing progressing
| Keezhallur PH Sn AE |
| Date: 06/03/2026 |
Work in progress | 78% Completed
Tile fixing work completed in filter bed 3
| Keezhallur PH Sn AE |
| Date: 27/02/2026 |
Work in progress | 78% Completed
Tile fixing work completed in filter bed 3
| Keezhallur PH Sn AE |
| Date: 18/02/2026 |
Work in progress | 78% Completed
Tile fixing work progressing in filter bed 3
| Keezhallur PH Sn AE |
| Date: 09/02/2026 |
Work in progress | 78% Completed
Tile fixing work progressing in filter bed 3
| Keezhallur PH Sn AE |
| Date: 28/01/2026 |
Work in progress | 78% Completed
Tile fixing work in filter bed 3
| Keezhallur PH Sn AE |
| Date: 19/01/2026 |
Work in progress | 78% Completed
Clear water pipe and air pipes are fitted filter no.3
| Keezhallur PH Sn AE |
| Date: 14/01/2026 |
Work in progress | 78% Completed
Clear water pipe and air pipes are fitted filter no.3
| Keezhallur PH Sn AE |
| Date: 08/01/2026 |
Work in progress | 78% Completed
Clear water pipe and air pipes are fitted
| Keezhallur PH Sn AE |
| Date: 29/12/2025 |
Work in progress | 78% Completed
Thrust block concrete completed for chamber 1 - Filter bed 3
| Keezhallur PH Sn AE |
| Date: 22/12/2025 |
Work in progress | 78% Completed
Filter bed no.3- Pipe fitting work
| Keezhallur PH Sn AE |
| Date: 12/12/2025 |
Work in progress | 78% Completed
Filter bed no.3- New Pipe fitting work
| Keezhallur PH Sn AE |
| Date: 05/12/2025 |
Work in progress | 78% Completed
Filter Bed No.3- cleaning work
| Keezhallur PH Sn AE |
| Date: 28/11/2025 |
Work in progress | 78% Completed
Filter Bed No.3 Air pipes changing
| Keezhallur PH Sn AE |
| Date: 21/11/2025 |
| Keezhallur PH Sn AE |
| Date: 14/11/2025 |
| Keezhallur PH Sn AE |
| Date: 06/11/2025 |
Work in progress | 78% Completed
Filter sand not supplied, supply order given
| Keezhallur PH Sn AE |
| Date: 30/10/2025 |
Work in progress | 78% Completed
Filter sand not supplied, supply order given
| Keezhallur PH Sn AE |
| Date: 23/10/2025 |
Work in progress | 78% Completed
Filter sand not supplied, supply order given
| Keezhallur PH Sn AE |
| Date: 13/10/2025 |
Work in progress | 78% Completed
Supply order given filter sand to be supplied
| Keezhallur PH Sn AE |
| Date: 06/10/2025 |
Work in progress | 78% Completed
Supply order given filter sand to be supplied
| Keezhallur PH Sn AE |
| Date: 29/09/2025 |
Work in progress | 78% Completed
Supply order given filter sand to be supplied
| Keezhallur PH Sn AE |
| Date: 24/09/2025 |
Work in progress | 78% Completed
Valve fixing work in progress
| Keezhallur PH Sn AE |
| Date: 20/09/2025 |
Work in progress | 78% Completed
Valve fixing work in progress.
| Keezhallur PH Sn AE |
| Date: 18/08/2025 |
Work in progress | 78% Completed
Pebbles supplied
| Keezhallur PH Sn AE |
| Date: 06/08/2025 |
Work in progress | 78% Completed
Valve fixing work .
| Keezhallur PH Sn AE |
| Date: 28/07/2025 |
Work in progress | 78% Completed
Valve fixing work in progress.
| Keezhallur PH Sn AE |
| Date: 14/07/2025 |
Work in progress | 75% Completed
Repairing of compound wall in progress.
| Keezhallur PH Sn AE |
| Date: 27/06/2025 |
Work in progress | 74% Completed
Repairing of compound wall in progress.
| Keezhallur PH Sn AE |
| Date: 17/06/2025 |
Work in progress | 73% Completed
Repairing of compound wall in progress.
| Keezhallur PH Sn AE |
| Date: 31/05/2025 |
Work in progress | 70% Completed
Repairing of clarifloculator bridge completed .
| Keezhallur PH Sn AE |
| Date: 22/04/2025 |
Work in progress | 51% Completed
Water proofing work completed.Filter has to be replaced.
| Keezhallur PH Sn AE |
| Date: 08/04/2025 |
Work in progress | 50% Completed
Water proofing work on progress.
| Keezhallur PH Sn AE |
| Date: 01/04/2025 |
Work in progress | 44% Completed
Water proofing work on progress.
| Keezhallur PH Sn AE |
| Date: 27/03/2025 |
Work in progress | 42% Completed
Water proofing work on progress.
| Keezhallur PH Sn AE |
| Date: 19/03/2025 |
Work in progress | 42% Completed
Painting to be done.
| Keezhallur PH Sn AE |
| Date: 05/03/2025 |
Work in progress | 40% Completed
Package V- clariflocculator bridge repairing works are going on.
| Keezhallur PH Sn AE |
| Date: 18/02/2025 |
Work in progress | 40% Completed
Package V- clariflocculator bridge repairing works are going on.
| Keezhallur PH Sn AE |
| Date: 10/02/2025 |
Work in progress | 40% Completed
Package V- clariflocculator bridge repairing works are going on.
| Keezhallur PH Sn AE |
| Date: 31/01/2025 |
Work in progress | 40% Completed
Package V- clariflocculator bridge repairing works are going on.
| Keezhallur PH Sn AE |
| Date: 22/01/2025 |
Work in progress | 40% Completed
Package V- clariflocculator bridge repairing works are going on.
| Keezhallur PH Sn AE |
| Date: 03/01/2025 |
Work in progress | 31% Completed
Package V- clariflocculator bridge repairing works are going on.
| Keezhallur PH Sn AE |
| Date: 16/12/2024 |
Work in progress | 29% Completed
Package V- clariflocculator bridge repairing works are going on.
| Keezhallur PH Sn AE |
| Date: 05/12/2024 |
Work in progress | 25% Completed
Package V- clariflocculator bridge repairing works are going on.
| Keezhallur PH Sn AE |
| Date: 13/11/2024 |
Work in progress | 22% Completed
Package V- sludge removal works are going on.
| Keezhallur PH Sn AE |
| Date: 02/11/2024 |
Work in progress | 21% Completed
Package V- sludge removal works are going on.
| Keezhallur PH Sn AE |
| Date: 26/10/2024 |
Work in progress | 20% Completed
Package V- electrification works are going on.
| Keezhallur PH Sn AE |
| Date: 24/10/2024 |
Work in progress | 19% Completed
Package V- electrification works are going on.
| Keezhallur PH Sn AE |
| Date: 15/10/2024 |
Work in progress | 17% Completed
Electrification works are going on
| Keezhallur PH Sn AE |
| Date: 07/10/2024 |
Work in progress | 15% Completed
Installation of yard lights completed, Supply and Installation of Blower completed, roofing works completed, leak works of OHSR completed
| Keezhallur PH Sn AE |
| Date: 26/09/2024 |
Work in progress | 14% Completed
leak works of OHSR is going on.
| Keezhallur PH Sn AE |
| Date: 18/09/2024 |
Work in progress | 10% Completed
Package V-Supply and installation of blower completed and leak rectification works of OHSR is going on.
| Keezhallur PH Sn AE |
| Date: 10/09/2024 |
Work in progress | 6% Completed
package V- roofing works completed, sludge removal works are going on.
| Keezhallur PH Sn AE |
| Date: 03/09/2024 |
Work in progress | 6% Completed
package V- roofing works completed, sludge removal works are going on.
| Keezhallur PH Sn AE |
| Date: 12/08/2024 |
Work in progress | 6% Completed
roofing works completed. sludge removal works are going on
| Keezhallur PH Sn AE |
| Date: 07/08/2024 |
Work in progress | 4% Completed
Work started. roofing works are going on.
| Keezhallur PH Sn AE |
| Date: 05/08/2024 |
Work in progress | 4% Completed
Work started. roofing works are going on.
| Kannur PH Dn EE |
| Date: 24/07/2024 |
Work in progress | 4% Completed
Work started. roofing works are going on.