Ollur AE |
Date: 24/06/2024 |
Work in progress | 56% Completed
Total pipe laid-30000m,Total connection-425nos.185 nos tagged.
Chalakudy AEE |
Date: 18/06/2024 |
Work in progress | 56% Completed
3rd and part bill submitted to Dn office on 16.04.2024
Ollur AE |
Date: 15/06/2024 |
Work in progress | 56% Completed
Total pipe laid-30000m,Total connection-425nos.185 nos tagged.
Ollur AE |
Date: 10/06/2024 |
Work in progress | 56% Completed
Total pipe laid-30000,Total connection-425nos.185 nos tagged.
Ollur AE |
Date: 27/05/2024 |
Work in progress | 30% Completed
Work in progress
Ollur AE |
Date: 14/05/2024 |
Work in progress | 30% Completed
CC 3 rd and part bill submitted
Ollur AE |
Date: 06/05/2024 |
Work in progress | 30% Completed
CC 3 rd and part bill submitted
Chalakudy AEE |
Date: 25/04/2024 |
Work in progress | 30% Completed
CC 3 rd and part bill submitted to DN office on 16.04.2024
Ollur AE |
Date: 23/04/2024 |
Work in progress | 30% Completed
Work in progress CC 3rd &part bill Submitted
Ollur AE |
Date: 15/04/2024 |
Work in progress | 30% Completed
Work in progress CC 3rd &part bill Submitted
Ollur AE |
Date: 09/04/2024 |
Work in progress | 30% Completed
CC 3rd &part bill Submitted
Ollur AE |
Date: 04/04/2024 |
Work in progress | 30% Completed
CC 3rd &part bill Submitted
Ollur AE |
Date: 20/03/2024 |
Work in progress | 30% Completed
Work in progress
Ollur AE |
Date: 13/03/2024 |
Work in progress | 30% Completed
Work in progress
Ollur AE |
Date: 04/03/2024 |
Work in progress | 30% Completed
2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -18500m , Total connection -160nos,129 nos tagged
Ollur AE |
Date: 04/10/2023 |
Work in progress | 25% Completed
2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -13524m , Total connection -100nos
Ollur AE |
Date: 30/09/2023 |
Work in progress | 25% Completed
2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -13524m , Total connection -100nos
Ollur AE |
Date: 25/09/2023 |
Ollur AE |
Date: 19/09/2023 |
Work in progress | 22% Completed
2nd and part bill submitted to DN office on 5/9/2023.110 mm HDPE=6310 m 75 mm PVC=2078 m 63 mm PVC=540 m 50 mm PVC=156 m Total=9084 m
Ollur AE |
Date: 14/09/2023 |
Ollur AE |
Date: 11/09/2023 |
Work in progress | 17% Completed
Work in Progress Total laying-5854m, Total Connection- 28nos
Ollur AE |
Date: 04/09/2023 |
Work in progress | 16% Completed
Work in Progress
Ollur AE |
Date: 26/08/2023 |
Work in progress | 15% Completed
Laying 75mm PVC Pipe ,63mm PVC pIPE,50mm PVC Pipe,110mm HDPE Pipe in Ward 6,8 .Total -2000m.
Chalakudy AEE |
Date: 21/08/2023 |
Work in progress | 15% Completed
Letter issued to contractor on 21.08.2023 for submitting the revised time shedule
Ollur AE |
Date: 18/08/2023 |
Work in progress | 15% Completed
Ward 3,Laying 75mm PVC Pipe -354m .Ward 6 63mm PVC Pipe-72m,Total connection-3nos
Ollur AE |
Date: 14/08/2023 |
Work in progress | 15% Completed
Ward 3,Laying 75mm PVC Pipe -354m .Total connection-3nos
Ollur AE |
Date: 07/08/2023 |
Work in progress | 15% Completed
Ward 3,Laying 75mm PVC Pipe -354m .Total connection-3nos
Ollur AE |
Date: 02/08/2023 |
Work in progress | 15% Completed
Ward 3,Laying 75mm PVC Pipe -354m.Total connection-3nos
Ollur AE |
Date: 29/07/2023 |
Work in progress | 15% Completed
Ward 3,Laying 75mm PVC Pipe -354m
Ollur AE |
Date: 24/07/2023 |
Work in progress | 15% Completed
Ward 3,Laying 75mm PVC Pipe -354m
Ollur AE |
Date: 19/07/2023 |
Work in progress | 15% Completed
Ward 3,Laying 75mm PVC Pipe -354m
Ollur AE |
Date: 14/07/2023 |
Work in progress | 15% Completed
Ward 3,Laying 75mm PVC Pipe -354m
Ollur AE |
Date: 10/07/2023 |
Work in progress | 15% Completed
Ward 3,Laying 75mm PVC Pipe -354m
Ollur AE |
Date: 06/07/2023 |
Work in progress | 15% Completed
Work in Progress
Ollur AE |
Date: 01/07/2023 |
Work in progress | 10% Completed
CC first and part bill submitted
Ollur AE |
Date: 27/06/2023 |
Work in progress | 10% Completed
CC first and part bill submitted
Ollur AE |
Date: 23/06/2023 |
Work in progress | 10% Completed
CC first and part bill submitted
Ollur AE |
Date: 19/06/2023 |
Work in progress | 10% Completed
CC first and part bill submitted
Ollur AE |
Date: 14/06/2023 |
Work in progress | 10% Completed
CC first and part bill submitted
Ollur AE |
Date: 12/06/2023 |
Work in progress | 10% Completed
CC first and part bill submitted
Ollur AE |
Date: 09/06/2023 |
Work in progress | 10% Completed
CC first and part bill submitted
Ollur AE |
Date: 06/06/2023 |
Work in progress | 9% Completed
CC first and part bill submitted
Ollur AE |
Date: 01/06/2023 |
Work in progress | 9% Completed
CC first and part bill submitted
Ollur AE |
Date: 29/05/2023 |
Work in progress | 9% Completed
CC first and part bill submitted
Ollur AE |
Date: 25/05/2023 |
Work in progress | 9% Completed
CC first and part bill submitted
Ollur AE |
Date: 22/05/2023 |
Work in progress | 9% Completed
CC first and part bill submitted
Ollur AE |
Date: 20/05/2023 |
Work in progress | 9% Completed
CC first and part bill submitted
Chalakudy AEE |
Date: 16/05/2023 |
Work in progress | 9% Completed
CC 1st & part bill submitted
Ollur AE |
Date: 15/05/2023 |
Work in progress | 8% Completed
CC 1st & part bill submitted
Ollur AE |
Date: 11/05/2023 |
Work in progress | 8% Completed
CC 1st & part bill submitted
Ollur AE |
Date: 10/05/2023 |
Work in progress | 7% Completed
Pipe supplied. Work not started
Ollur AE |
Date: 06/05/2023 |
Work in progress | 7% Completed
Pipe supplied. Work not started
Ollur AE |
Date: 03/05/2023 |
Work in progress | 5% Completed
Pipe supplied. Work not started
Ollur AE |
Date: 29/04/2023 |
Work in progress | 5% Completed
Pipe supplied. Work not started
Ollur AE |
Date: 24/04/2023 |
Work in progress | 5% Completed
Pipe supplied, work not started.
Ollur AE |
Date: 17/04/2023 |
Work in progress | 5% Completed
Pipe supplied. Work not started
Ollur AE |
Date: 10/04/2023 |
Work in progress | 5% Completed
Pipe supplied. Work not started
Ollur AE |
Date: 06/04/2023 |
Work in progress | 5% Completed
Pipe supplied.
Ollur AE |
Date: 03/04/2023 |
Work in progress | 5% Completed
Pipe supplied.
Ollur AE |
Date: 27/03/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 24/03/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 20/03/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 16/03/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 13/03/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 09/03/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 06/03/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 02/03/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 27/02/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 23/02/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 20/02/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 17/02/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 14/02/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 09/02/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 06/02/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 03/02/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 30/01/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 27/01/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 23/01/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 19/01/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 16/01/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 13/01/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 10/01/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 06/01/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 04/01/2023 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 31/12/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 26/12/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 23/12/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 19/12/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 12/12/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 06/12/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 01/12/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 28/11/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 24/11/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 21/11/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 17/11/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 14/11/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 11/11/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 08/11/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 04/11/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 01/11/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 28/10/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 25/10/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 21/10/2022 |
Work has started | 0% Completed
Work order issued
Ollur AE |
Date: 17/10/2022 |
Work has started | 0% Completed
Work order issued
Irinjalakkuda PH Dn EE |
Date: 12/10/2022 |
Work has started | 0% Completed
Work order issued on 10.10.22