Koyilandy PH Section 1 - AE |
Date: 01/07/2024 |
Work in progress | 80% Completed
All works completed except Pump set and power connection.
Koyilandy PH Section 1 - AE |
Date: 25/06/2024 |
Work in progress | 80% Completed
All works completed except Pump set and power connection.
Koyilandy PH Section 1 - AE |
Date: 19/06/2024 |
Work in progress | 80% Completed
All works completed except Pump set and power connection.
Koyilandy PH Section 1 - AE |
Date: 10/06/2024 |
Work in progress | 80% Completed
All works completed except Pump set and power connection.
Koyilandy PH Section 1 - AE |
Date: 04/06/2024 |
Work in progress | 80% Completed
All works completed except Pump set and power connection.
Koyilandy PH Section 1 - AE |
Date: 03/06/2024 |
Work in progress | 80% Completed
All works completed except Pump set and power connection.
Koyilandy PH Section 1 - AE |
Date: 31/05/2024 |
Work in progress | 80% Completed
All works completed except Pump set and power connection.
Koyilandy PH Section 1 - AE |
Date: 22/05/2024 |
Work in progress | 80% Completed
All works completed except Pump set and power connection.
Koyilandy PH Section 1 - AE |
Date: 13/05/2024 |
Work in progress | 60% Completed
Pipe laying completed. Time extension request submitted to Division.
Koyilandy PH Section 1 - AE |
Date: 02/05/2024 |
Work in progress | 60% Completed
Pipe laying completed. Time extension request submitted to Division.
Koyilandy PH Section 1 - AE |
Date: 23/04/2024 |
Work in progress | 60% Completed
Pipe laying completed. Time extension request submitted to Division.
Koyilandy PH Sub Dn - AEE |
Date: 02/04/2024 |
Work in progress | 60% Completed
Pipe laying completed. Time extension request submitted to Division.
Koyilandy PH Sub Dn - AEE |
Date: 06/03/2024 |
Work in progress | 20% Completed
Work in progress.
Koyilandy PH Section 1 - AE |
Date: 25/02/2024 |
Work in progress | 20% Completed
Work in progress
Vadakara PH Dn EE |
Date: 14/02/2024 |
Work in progress | 20% Completed
Pipe supplied