Koyilandy PH Section 1 - AE
Date: 01/07/2024

Work in progress | 80% Completed

All works completed except Pump set and power connection.

Koyilandy PH Section 1 - AE
Date: 25/06/2024

Work in progress | 80% Completed

All works completed except Pump set and power connection.

Koyilandy PH Section 1 - AE
Date: 19/06/2024

Work in progress | 80% Completed

All works completed except Pump set and power connection.

Koyilandy PH Section 1 - AE
Date: 10/06/2024

Work in progress | 80% Completed

All works completed except Pump set and power connection.

Koyilandy PH Section 1 - AE
Date: 04/06/2024

Work in progress | 80% Completed

All works completed except Pump set and power connection.

Koyilandy PH Section 1 - AE
Date: 03/06/2024

Work in progress | 80% Completed

All works completed except Pump set and power connection.

Koyilandy PH Section 1 - AE
Date: 31/05/2024

Work in progress | 80% Completed

All works completed except Pump set and power connection.

Koyilandy PH Section 1 - AE
Date: 22/05/2024

Work in progress | 80% Completed

All works completed except Pump set and power connection.

Koyilandy PH Section 1 - AE
Date: 13/05/2024

Work in progress | 60% Completed

Pipe laying completed. Time extension request submitted to Division.

Koyilandy PH Section 1 - AE
Date: 02/05/2024

Work in progress | 60% Completed

Pipe laying completed. Time extension request submitted to Division.

Koyilandy PH Section 1 - AE
Date: 23/04/2024

Work in progress | 60% Completed

Pipe laying completed. Time extension request submitted to Division.

Koyilandy PH Sub Dn - AEE
Date: 02/04/2024

Work in progress | 60% Completed

Pipe laying completed. Time extension request submitted to Division.

Koyilandy PH Sub Dn - AEE
Date: 06/03/2024

Work in progress | 20% Completed

Work in progress.

Koyilandy PH Section 1 - AE
Date: 25/02/2024

Work in progress | 20% Completed

Work in progress

Vadakara PH Dn EE
Date: 14/02/2024

Work in progress | 20% Completed

Pipe supplied