| Kannur PH Sn 3 AE |
| Date: 10/09/2025 |
Work has been completed | 100% Completed
work completed, 6.4km pipe laid, 819 FHTC given
| Kannur PH Sn 3 AE |
| Date: 30/08/2025 |
Work has been completed | 100% Completed
work completed, 6.4km pipe laid, 819 FHTC given
| Kannur PH Sn 3 AE |
| Date: 08/08/2025 |
Work has been completed | 100% Completed
Work has been completed
| Kannur PH Sn 3 AE |
| Date: 31/07/2025 |
Work has been completed | 100% Completed
Work has been completed
| Kannur PH Sn 3 AE |
| Date: 19/07/2025 |
Work has been completed | 100% Completed
Work has been completed
| Kannur PH Sn 3 AE |
| Date: 14/07/2025 |
Work has been completed | 100% Completed
Work has been completed
| Kannur PH Sn 3 AE |
| Date: 30/06/2025 |
Work has been completed | 100% Completed
Final bill submitted
| Kannur PH Sn 3 AE |
| Date: 27/06/2025 |
Work has been completed | 100% Completed
final bill submitted
| Kannur PH Sn 3 AE |
| Date: 17/06/2025 |
Work has been completed | 100% Completed
final bill submitted
| Kannur PH Sn 3 AE |
| Date: 29/05/2025 |
Work has been completed | 100% Completed
final bill submitted
| Kannur PH Sn 3 AE |
| Date: 19/05/2025 |
Work has been completed | 100% Completed
final bill submitted
| Kannur PH Sn 3 AE |
| Date: 03/05/2025 |
Work has been completed | 100% Completed
final bill submitted
| Kannur PH Sn 3 AE |
| Date: 05/04/2025 |
Work has been completed | 100% Completed
final Bill submitted
| Kannur PH Sn 3 AE |
| Date: 29/03/2025 |
Work has been completed | 100% Completed
final Bill submitted
| Kannur PH Sn 3 AE |
| Date: 27/03/2025 |
Work has been completed | 100% Completed
final Bill submitted
| Kannur PH Sn 3 AE |
| Date: 03/03/2025 |
Work in progress | 85% Completed
6.4 KM pipe laid. 819 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 12/02/2025 |
Work in progress | 70% Completed
6.4 KM pipe laid. 819 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 07/02/2025 |
Work in progress | 70% Completed
6.4 KM pipe laid. 819 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 01/02/2025 |
Work in progress | 70% Completed
6.4 KM pipe laid. 860 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 29/01/2025 |
Work in progress | 70% Completed
6.4 KM pipe laid. 860 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 24/01/2025 |
Work in progress | 70% Completed
6.4 KM pipe laid. 860 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 22/01/2025 |
Work in progress | 70% Completed
6.4 KM pipe laid. 860 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 18/01/2025 |
Work in progress | 70% Completed
6.4 KM pipe laid. 860 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 16/01/2025 |
Work in progress | 70% Completed
6.4 KM pipe laid. 860 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 10/01/2025 |
Work in progress | 70% Completed
6.4 KM pipe laid. 860 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 04/01/2025 |
Work in progress | 70% Completed
6.4 KM pipe laid. 860 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 31/12/2024 |
Work in progress | 60% Completed
6.4 KM pipe laid. 855 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 24/12/2024 |
Work in progress | 60% Completed
6.4 KM pipe laid. 855 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 21/12/2024 |
Work in progress | 60% Completed
6.4 KM pipe laid. 855 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 20/12/2024 |
Work in progress | 60% Completed
6.4 KM pipe laid. 855 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 17/12/2024 |
Work in progress | 60% Completed
6.4 KM pipe laid. 855 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 16/12/2024 |
Work in progress | 60% Completed
6.4 KM pipe laid. 855 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 10/12/2024 |
Work in progress | 60% Completed
6.4 KM pipe laid. 855 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 07/12/2024 |
Work in progress | 60% Completed
6.4 KM pipe laid. 855 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 05/12/2024 |
Work in progress | 60% Completed
6.4 KM pipe laid. 855 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 02/12/2024 |
Work in progress | 60% Completed
6.4 KM pipe laid. 855 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 29/11/2024 |
Work in progress | 60% Completed
6.4 KM pipe laid. 855 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 26/11/2024 |
Work in progress | 60% Completed
6.4 KM pipe laid. 855 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 22/11/2024 |
Work in progress | 60% Completed
6.4 KM pipe laid. 855 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 19/11/2024 |
Work in progress | 60% Completed
6.4 KM pipe laid. 855 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 16/11/2024 |
Work in progress | 60% Completed
6.4 KM pipe laid. 850 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 12/11/2024 |
Work in progress | 60% Completed
6.4 KM pipe laid. 850 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 08/11/2024 |
Work in progress | 60% Completed
6.4 KM pipe laid. 850 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 07/11/2024 |
Work in progress | 60% Completed
6.4 KM pipe laid. 850 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 04/11/2024 |
Work in progress | 45% Completed
6 KM pipe laid. 836 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 02/11/2024 |
Work in progress | 45% Completed
6 KM pipe laid. 836 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 01/11/2024 |
Work in progress | 45% Completed
6 KM pipe laid. 836 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 30/10/2024 |
Work in progress | 45% Completed
6 KM pipe laid. 836 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 28/10/2024 |
Work in progress | 45% Completed
6 KM pipe laid. 836 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 26/10/2024 |
Work in progress | 45% Completed
6 KM pipe laid. 836 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 25/10/2024 |
Work in progress | 45% Completed
6 KM pipe laid. 836 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 24/10/2024 |
Work in progress | 45% Completed
6 KM pipe laid. 836 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 22/10/2024 |
Work in progress | 45% Completed
6 KM pipe laid. 836 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 21/10/2024 |
Work in progress | 39% Completed
6 KM pipe laid. 290 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 18/10/2024 |
Work in progress | 39% Completed
6 KM pipe laid. 290 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 16/10/2024 |
Work in progress | 39% Completed
6 KM pipe laid. 290 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 14/10/2024 |
Work in progress | 39% Completed
6 KM pipe laid. 290 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 10/10/2024 |
Work in progress | 39% Completed
6 KM pipe laid. 290 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 07/10/2024 |
Work in progress | 38% Completed
6 KM pipe laid. 270 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 04/10/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 01/10/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 28/09/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 26/09/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 23/09/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 20/09/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 18/09/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 12/09/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 09/09/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 06/09/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 03/09/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 30/08/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 27/08/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 24/08/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 22/08/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 19/08/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 16/08/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 12/08/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 08/08/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 05/08/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 02/08/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 30/07/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 27/07/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 23/07/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 20/07/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 19/07/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 17/07/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 15/07/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 10/07/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 06/07/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 03/07/2024 |
Work in progress | 36% Completed
6 KM pipe laid. 230 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 01/07/2024 |
Work in progress | 35% Completed
6 KM pipe laid. 220 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 27/06/2024 |
Work in progress | 35% Completed
6 KM pipe laid. 220 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 24/06/2024 |
Work in progress | 35% Completed
6 KM pipe laid. 220 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 22/06/2024 |
Work in progress | 35% Completed
6 KM pipe laid. 220 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 18/06/2024 |
Work in progress | 35% Completed
6 KM pipe laid. 220 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 13/06/2024 |
Work in progress | 35% Completed
6 KM pipe laid. 220 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 10/06/2024 |
Work in progress | 35% Completed
6 KM pipe laid. 220 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 05/06/2024 |
Work in progress | 35% Completed
6 KM pipe laid. 220 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 01/06/2024 |
Work in progress | 35% Completed
6 KM pipe laid. 220 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 29/05/2024 |
Work in progress | 32% Completed
5.2 KM pipe laid. 180 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 25/05/2024 |
Work in progress | 32% Completed
5.2 KM pipe laid. 180 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 22/05/2024 |
Work in progress | 32% Completed
5.2 KM pipe laid. 180 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 18/05/2024 |
Work in progress | 32% Completed
5.2 KM pipe laid. 180 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 14/05/2024 |
Work in progress | 30% Completed
5 KM pipe laid. 170 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 10/05/2024 |
Work in progress | 30% Completed
5 KM pipe laid. 170 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 07/05/2024 |
Work in progress | 30% Completed
5 KM pipe laid. 170 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 02/05/2024 |
Work in progress | 30% Completed
5 KM pipe laid. 170 Nos FHTC given
| Kannur PH Sn 3 AE |
| Date: 27/04/2024 |
Work in progress | 30% Completed
30 % COMPLETED.
| Kannur PH Sn 3 AE |
| Date: 24/04/2024 |
Work in progress | 30% Completed
30 % COMPLETED.