Kollam Project HD |
Date: 19/10/2020 |
Work has been completed | 100% Completed
works completed
Kollam Project HD |
Date: 30/09/2020 |
Work in progress | 99% Completed
work completed
Kollam Project HD |
Date: 15/08/2020 |
Work in progress | 90% Completed
pipe laying works completed , road restoration works in progress.
Kollam Project HD |
Date: 30/07/2020 |
Work in progress | 78% Completed
2.6km laid out of 3.3km
Kollam Project HD |
Date: 10/07/2020 |
Work in progress | 75% Completed
2.5km laid out of 3.3km
Kollam Project HD |
Date: 19/06/2020 |
Work in progress | 71% Completed
laying works in progress 1.81 kms pipe laid ,3.3 km pipe supplied out of 3.3 Km
Kollam Project HD |
Date: 18/06/2020 |
Work in progress | 70% Completed
1.811Km pipe laid