| Kollam PH Dn EE |
| Date: 24/03/2023 |
Work has been completed | 100% Completed
Work completed
| Sasthamcotta WS Sn 1 - AE |
| Date: 16/03/2023 |
Work in progress | 50% Completed
Supply and Installation of 25 HP (1 No.) submersible pump set - Supply completed.
| Sasthamcotta WS Sn 1 - AE |
| Date: 06/03/2023 |
Work in progress | 50% Completed
Supply and Installation of 25 HP (1 No.) submersible pump set - Supply completed.
| Sasthamcotta WS Sn 1 - AE |
| Date: 27/02/2023 |
Work in progress | 50% Completed
Supply and Installation of 25 HP (1 No.) submersible pump set - Supply completed.
| Sasthamcotta WS Sn 1 - AE |
| Date: 22/02/2023 |
Work in progress | 50% Completed
Supply and Installation of 25 HP (1 No.) submersible pump set - Supply completed.
| Sasthamcotta WS Sn 1 - AE |
| Date: 15/02/2023 |
Work in progress | 50% Completed
Supply and Installation of 25 HP (1 No.) submersible pump set - Supply completed.
| Sasthamcotta WS Sn 1 - AE |
| Date: 07/02/2023 |
Work in progress | 50% Completed
Supply and Installation of 25 HP (1 No.) submersible pump set - Supply completed.
| Sasthamcotta WS Sn 1 - AE |
| Date: 31/01/2023 |
Work in progress | 50% Completed
Supply and Installation of 25 HP (1 No.) submersible pump set - Supply completed.
| Sasthamcotta WS Sn 1 - AE |
| Date: 23/01/2023 |
Work in progress | 50% Completed
25 HP (1no) submersible pump set - Supply completed
| Sasthamcotta WS Sn 1 - AE |
| Date: 21/01/2023 |
Work in progress | 5% Completed
Work on progress
| Sasthamcotta WS Sn 1 - AE |
| Date: 18/01/2023 |
Work in progress | 5% Completed
Agreement executed on 18.01.2023
| Sasthamcotta WS Sn 1 - AE |
| Date: 16/01/2023 |
Work in progress | 0% Completed
Work order issued, agreement not executed
| Sasthamcotta WS Sn 1 - AE |
| Date: 09/01/2023 |
Work in progress | 0% Completed
Work order issued.
| Sasthamcotta WS Sn 1 - AE |
| Date: 03/01/2023 |
Work in progress | 0% Completed
Work tendered.
| Sasthamcotta WS Sn 1 - AE |
| Date: 29/12/2022 |
Work in progress | 0% Completed
Work tendered
| Sasthamcotta WS Sub-Dn - AEE |
| Date: 21/12/2022 |
Work has started | 0% Completed
Work tenderd