Konni PH Sn - AE
Date: 26/06/2024

Work in progress | 33% Completed

Total tagged -218 nos Pipe laid - 90 to 160 mm PVC - 49.25 km

Konni PH Sn - AE
Date: 24/06/2024

Work in progress | 33% Completed

Total tagged -218 nos Pipe laid - 90 to 160 mm PVC - 49.25 km

Konni PH Sn - AE
Date: 16/05/2024

Work in progress | 31% Completed

Total tagged -208 nos Pipe laid - 90 to 160 mm PVC - 48.141 km

Konni PH Sn - AE
Date: 23/04/2024

Work in progress | 30% Completed

Total tagged -208 nos Pipe laid - 90 to 160 mm PVC - 47.642 km

Konni PH Sn - AE
Date: 08/04/2024

Work in progress | 29% Completed

Total tagged -110 nos Pipe laid - 90 to 160 mm PVC - 47.6 km

Konni PH Sn - AE
Date: 21/03/2024

Work in progress | 23% Completed

Pipe laid - 90 to 160 mm PVC - 39.148 km

Konni PH Sn - AE
Date: 11/03/2024

Work in progress | 23% Completed

Pipe laid - 90 to 160 mm PVC - 39.148 km

Konni PH Sn - AE
Date: 07/03/2024

Work in progress | 23% Completed

Pipe laid - 90 to 160 mm PVC - 39.148 km

Konni PH Sn - AE
Date: 28/02/2024

Work in progress | 23% Completed

Pipe laid - 90 to 160 mm PVC -38.081 km

Konni PH Sn - AE
Date: 22/02/2024

Work in progress | 23% Completed

Pipe laid - 90 to 160 mm PVC -38.081 km

Konni PH Sn - AE
Date: 15/02/2024

Work in progress | 23% Completed

Pipe laid - 90 to 160 mm PVC - 36.2 km

Konni PH Sn - AE
Date: 13/02/2024

Work in progress | 22% Completed

Pipe laid - 90 to 160 mm PVC - 35.089 km

Konni PH Sn - AE
Date: 06/02/2024

Work in progress | 20% Completed

Work in progress

Konni PH Sn - AE
Date: 29/01/2024

Work in progress | 20% Completed

Work in progress

Konni PH Sn - AE
Date: 21/01/2024

Work in progress | 20% Completed

PTAJJM052214979

Konni PH Sn - AE
Date: 12/01/2024

Work in progress | 3% Completed

Work in progress

Konni PH Sn - AE
Date: 26/12/2023

Work in progress | 3% Completed

Work in progress

Konni PH Sn - AE
Date: 18/12/2023

Work in progress | 3% Completed

Work in progress

Konni PH Sn - AE
Date: 12/12/2023

Work in progress | 3% Completed

Work in progress

Konni PH Sn - AE
Date: 04/12/2023

Work in progress | 2% Completed

Agreement Executed on 05.05.2023

Konni PH Sn - AE
Date: 29/11/2023

Work in progress | 2% Completed

Agreement Executed on 05.05.2023

Konni PH Sn - AE
Date: 25/11/2023

Work in progress | 2% Completed

Agreement Executed on 05.05.2023

Konni PH Sn - AE
Date: 20/11/2023

Work in progress | 2% Completed

Agreement Executed on 05.05.2023

Konni PH Sn - AE
Date: 13/11/2023

Work in progress | 2% Completed

Agreement Executed on 05.05.2023

Konni PH Sn - AE
Date: 07/11/2023

Work in progress | 1% Completed

Agreement Executed on 05.05.2023

Pathanamthitta PH Dn EE
Date: 05/05/2022

Work in progress | 1% Completed

Agreement Executed on 05.05.2023