| North Paravur WS Sub Dn - AEE |
| Date: 20/01/2022 |
Work has been completed | 100% Completed
work fully completed. final bill submitted to division office
| Kochi WS Dn EE |
| Date: 24/08/2021 |
Work in progress | 96% Completed
96% Completed
| Kochi WS Dn EE |
| Date: 22/08/2021 |
Work in progress | 96% Completed
96% Completed
| Kochi WS Dn EE |
| Date: 21/08/2021 |
Work in progress | 96% Completed
96% Work Completed
| Kochi WS Dn EE |
| Date: 20/08/2021 |
Work in progress | 96% Completed
96% Work Completed
| Kochi WS Dn EE |
| Date: 19/08/2021 |
Work in progress | 96% Completed
96% Work Completed
| Kochi WS Dn EE |
| Date: 18/08/2021 |
Work in progress | 96% Completed
96% Work Completed
| Kochi WS Dn EE |
| Date: 15/08/2021 |
Work in progress | 95% Completed
95% Completed
| Kochi WS Dn EE |
| Date: 14/08/2021 |
Work in progress | 95% Completed
95% Completed
| Kochi WS Dn EE |
| Date: 13/08/2021 |
Work in progress | 95% Completed
95% Completed
| Kochi WS Dn EE |
| Date: 12/08/2021 |
Work in progress | 95% Completed
95% Completed
| Kochi WS Dn EE |
| Date: 11/08/2021 |
Work in progress | 95% Completed
95% Completed
| Kochi WS Dn EE |
| Date: 07/08/2021 |
Work in progress | 93% Completed
93% Completed
| Kochi WS Dn EE |
| Date: 06/08/2021 |
Work in progress | 93% Completed
93 % Completed
| Kochi WS Dn EE |
| Date: 05/08/2021 |
Work in progress | 93% Completed
93% Completed
| Kochi WS Dn EE |
| Date: 04/08/2021 |
Work in progress | 93% Completed
93% Completed
| Kochi WS Dn EE |
| Date: 03/08/2021 |
Work in progress | 93% Completed
93 % Completed
| Kochi WS Dn EE |
| Date: 02/08/2021 |
Work in progress | 92% Completed
92% Completed
| Kochi WS Dn EE |
| Date: 28/07/2021 |
Work in progress | 92% Completed
92 % copmleted
| Kochi WS Dn EE |
| Date: 27/07/2021 |
Work in progress | 92% Completed
92 % copmleted
| Kochi WS Dn EE |
| Date: 26/07/2021 |
Work in progress | 92% Completed
92 % copmleted
| Kochi WS Dn EE |
| Date: 22/07/2021 |
Work in progress | 90% Completed
640 FHTC's given
| Kochi WS Dn EE |
| Date: 21/07/2021 |
Work in progress | 90% Completed
635 FHTC's given
| Kochi WS Dn EE |
| Date: 20/07/2021 |
Work in progress | 90% Completed
90% Completed
| Kochi WS Dn EE |
| Date: 18/07/2021 |
Work in progress | 90% Completed
90% Completed
| Kochi WS Dn EE |
| Date: 17/07/2021 |
Work in progress | 90% Completed
90% Completed
| Kochi WS Dn EE |
| Date: 16/07/2021 |
Work in progress | 90% Completed
90% Completed
| Kochi WS Dn EE |
| Date: 15/07/2021 |
Work in progress | 89% Completed
628 Nos FHTC given
| Kochi WS Dn EE |
| Date: 14/07/2021 |
Work in progress | 89% Completed
614 Nos FHTC given
| Kochi WS Dn EE |
| Date: 12/07/2021 |
Work in progress | 89% Completed
601 Nos FHTC given
| Kochi WS Dn EE |
| Date: 10/07/2021 |
Work in progress | 89% Completed
On going
| Kochi WS Dn EE |
| Date: 09/07/2021 |
Work in progress | 56% Completed
593 FHTC's given
| Kochi WS Dn EE |
| Date: 07/07/2021 |
Work in progress | 53% Completed
584 FHTC's given
| Kochi WS Dn EE |
| Date: 05/07/2021 |
Work in progress | 53% Completed
573 FHTC's given
| Kochi WS Dn EE |
| Date: 01/07/2021 |
Work in progress | 53% Completed
564 FHTC's given, CC 4th Bill Under Verification
| Kochi WS Dn EE |
| Date: 24/06/2021 |
Work in progress | 53% Completed
564 FHTC Given,work slow due to lockdown
| Kochi WS Dn EE |
| Date: 17/06/2021 |
Work in progress | 53% Completed
564 FHTC Given,work slow due to lockdown
| Kochi WS Dn EE |
| Date: 09/06/2021 |
Work in progress | 53% Completed
564 FHTC Given,work slow due to lockdown
| Kochi WS Dn EE |
| Date: 02/06/2021 |
Work in progress | 53% Completed
564 FHTC Given,work slow due to lockdown
| Kochi WS Dn EE |
| Date: 28/05/2021 |
Work in progress | 53% Completed
564 FHTC Given,work slow due to lockdown
| Kochi WS Dn EE |
| Date: 20/05/2021 |
Work in progress | 53% Completed
564 FHTC Given
| Kochi WS Dn EE |
| Date: 14/05/2021 |
Work in progress | 48% Completed
504 FHTC Given
| Kochi WS Dn EE |
| Date: 04/05/2021 |
Work in progress | 47% Completed
497 FHTC Given
| Kochi WS Dn EE |
| Date: 27/04/2021 |
Work in progress | 45% Completed
491 FHTC Given
| Kochi WS Dn EE |
| Date: 16/04/2021 |
Work in progress | 45% Completed
475 FHTC Given
| Kochi WS Dn EE |
| Date: 03/04/2021 |
Work in progress | 40% Completed
440 FHTC Given
| Kochi WS Dn EE |
| Date: 25/03/2021 |
Work in progress | 40% Completed
Total 430 FHTC given
| Kochi WS Dn EE |
| Date: 19/03/2021 |
Work in progress | 40% Completed
420 FHTC given
| Kochi WS Dn EE |
| Date: 16/03/2021 |
Work in progress | 40% Completed
420 FHTC Given
| Kochi WS Dn EE |
| Date: 12/03/2021 |
Work in progress | 32% Completed
341 FHTC Given
| Kochi WS Dn EE |
| Date: 05/03/2021 |
Work in progress | 29% Completed
308 FHTC Given
| Kochi WS Dn EE |
| Date: 19/02/2021 |
Work in progress | 27% Completed
285 FHTC Given
| Kochi WS Dn EE |
| Date: 10/02/2021 |
Work in progress | 25% Completed
Total FHTC given is 265 Nos.
| Kochi WS Dn EE |
| Date: 05/02/2021 |
Work in progress | 25% Completed
245 FHTC Given
| Kochi WS Dn EE |
| Date: 02/02/2021 |
| Kochi WS Dn EE |
| Date: 24/12/2020 |
Work in progress | 9% Completed
99 FHTC Given
| Kochi WS Dn EE |
| Date: 18/12/2020 |
Work in progress | 7% Completed
73 FHTC Awaeded
| Kochi WS Dn EE |
| Date: 04/12/2020 |
Work in progress | 5% Completed
51 FHTC Given
| Kochi WS Dn EE |
| Date: 23/11/2020 |
Work in progress | 1% Completed
13FHTC Given