North Paravur WS Sub Dn - AEE
Date: 20/01/2022

Work has been completed | 100% Completed

work fully completed. final bill submitted to division office

Kochi WS Dn EE
Date: 24/08/2021

Work in progress | 96% Completed

96% Completed

Kochi WS Dn EE
Date: 22/08/2021

Work in progress | 96% Completed

96% Completed

Kochi WS Dn EE
Date: 21/08/2021

Work in progress | 96% Completed

96% Work Completed

Kochi WS Dn EE
Date: 20/08/2021

Work in progress | 96% Completed

96% Work Completed

Kochi WS Dn EE
Date: 19/08/2021

Work in progress | 96% Completed

96% Work Completed

Kochi WS Dn EE
Date: 18/08/2021

Work in progress | 96% Completed

96% Work Completed

Kochi WS Dn EE
Date: 15/08/2021

Work in progress | 95% Completed

95% Completed

Kochi WS Dn EE
Date: 14/08/2021

Work in progress | 95% Completed

95% Completed

Kochi WS Dn EE
Date: 13/08/2021

Work in progress | 95% Completed

95% Completed

Kochi WS Dn EE
Date: 12/08/2021

Work in progress | 95% Completed

95% Completed

Kochi WS Dn EE
Date: 11/08/2021

Work in progress | 95% Completed

95% Completed

Kochi WS Dn EE
Date: 07/08/2021

Work in progress | 93% Completed

93% Completed

Kochi WS Dn EE
Date: 06/08/2021

Work in progress | 93% Completed

93 % Completed

Kochi WS Dn EE
Date: 05/08/2021

Work in progress | 93% Completed

93% Completed

Kochi WS Dn EE
Date: 04/08/2021

Work in progress | 93% Completed

93% Completed

Kochi WS Dn EE
Date: 03/08/2021

Work in progress | 93% Completed

93 % Completed

Kochi WS Dn EE
Date: 02/08/2021

Work in progress | 92% Completed

92% Completed

Kochi WS Dn EE
Date: 28/07/2021

Work in progress | 92% Completed

92 % copmleted

Kochi WS Dn EE
Date: 27/07/2021

Work in progress | 92% Completed

92 % copmleted

Kochi WS Dn EE
Date: 26/07/2021

Work in progress | 92% Completed

92 % copmleted

Kochi WS Dn EE
Date: 22/07/2021

Work in progress | 90% Completed

640 FHTC's given

Kochi WS Dn EE
Date: 21/07/2021

Work in progress | 90% Completed

635 FHTC's given

Kochi WS Dn EE
Date: 20/07/2021

Work in progress | 90% Completed

90% Completed

Kochi WS Dn EE
Date: 18/07/2021

Work in progress | 90% Completed

90% Completed

Kochi WS Dn EE
Date: 17/07/2021

Work in progress | 90% Completed

90% Completed

Kochi WS Dn EE
Date: 16/07/2021

Work in progress | 90% Completed

90% Completed

Kochi WS Dn EE
Date: 15/07/2021

Work in progress | 89% Completed

628 Nos FHTC given

Kochi WS Dn EE
Date: 14/07/2021

Work in progress | 89% Completed

614 Nos FHTC given

Kochi WS Dn EE
Date: 12/07/2021

Work in progress | 89% Completed

601 Nos FHTC given

Kochi WS Dn EE
Date: 10/07/2021

Work in progress | 89% Completed

On going

Kochi WS Dn EE
Date: 09/07/2021

Work in progress | 56% Completed

593 FHTC's given

Kochi WS Dn EE
Date: 07/07/2021

Work in progress | 53% Completed

584 FHTC's given

Kochi WS Dn EE
Date: 05/07/2021

Work in progress | 53% Completed

573 FHTC's given

Kochi WS Dn EE
Date: 01/07/2021

Work in progress | 53% Completed

564 FHTC's given, CC 4th Bill Under Verification

Kochi WS Dn EE
Date: 30/06/2021

Work in progress | 53% Completed

work in progress

Attached images

img

Kochi WS Dn EE
Date: 29/06/2021

Work in progress | 53% Completed

work in progress

Attached images

img img img img

Kochi WS Dn EE
Date: 28/06/2021

Work in progress | 53% Completed

work in Progress

Attached images

img img img

Kochi WS Dn EE
Date: 24/06/2021

Work in progress | 53% Completed

564 FHTC Given,work slow due to lockdown

Kochi WS Dn EE
Date: 17/06/2021

Work in progress | 53% Completed

564 FHTC Given,work slow due to lockdown

Kochi WS Dn EE
Date: 09/06/2021

Work in progress | 53% Completed

564 FHTC Given,work slow due to lockdown

Kochi WS Dn EE
Date: 02/06/2021

Work in progress | 53% Completed

564 FHTC Given,work slow due to lockdown

Kochi WS Dn EE
Date: 28/05/2021

Work in progress | 53% Completed

564 FHTC Given,work slow due to lockdown

Kochi WS Dn EE
Date: 20/05/2021

Work in progress | 53% Completed

564 FHTC Given

Kochi WS Dn EE
Date: 14/05/2021

Work in progress | 48% Completed

504 FHTC Given

Kochi WS Dn EE
Date: 04/05/2021

Work in progress | 47% Completed

497 FHTC Given

Kochi WS Dn EE
Date: 27/04/2021

Work in progress | 45% Completed

491 FHTC Given

Kochi WS Dn EE
Date: 16/04/2021

Work in progress | 45% Completed

475 FHTC Given

Kochi WS Dn EE
Date: 03/04/2021

Work in progress | 40% Completed

440 FHTC Given

Kochi WS Dn EE
Date: 25/03/2021

Work in progress | 40% Completed

Total 430 FHTC given

Kochi WS Dn EE
Date: 19/03/2021

Work in progress | 40% Completed

420 FHTC given

Kochi WS Dn EE
Date: 16/03/2021

Work in progress | 40% Completed

420 FHTC Given

Kochi WS Dn EE
Date: 12/03/2021

Work in progress | 32% Completed

341 FHTC Given

Kochi WS Dn EE
Date: 05/03/2021

Work in progress | 29% Completed

308 FHTC Given

Kochi WS Dn EE
Date: 19/02/2021

Work in progress | 27% Completed

285 FHTC Given

Kochi WS Dn EE
Date: 10/02/2021

Work in progress | 25% Completed

Total FHTC given is 265 Nos.

Kochi WS Dn EE
Date: 05/02/2021

Work in progress | 25% Completed

245 FHTC Given

Kochi WS Dn EE
Date: 02/02/2021

Work in progress | 25% Completed

Total No. of FHTC given 238 Nos

Attached images

img

Kochi WS Dn EE
Date: 24/12/2020

Work in progress | 9% Completed

99 FHTC Given

Kochi WS Dn EE
Date: 18/12/2020

Work in progress | 7% Completed

73 FHTC Awaeded

Kochi WS Dn EE
Date: 04/12/2020

Work in progress | 5% Completed

51 FHTC Given

Kochi WS Dn EE
Date: 23/11/2020

Work in progress | 1% Completed

13FHTC Given